Written from the decision and the officer reportPDF Pro
OutcomeApprovedSeven items, programmes and strategies
Money£27.535m new borrowingPlus £3.230m maintenance programme
What happens nextCouncil approval in FebruaryFinal sign off needed
Who it affectsCouncil finances and servicesCapital programme, borrowing, investments
What was decided
Cabinet recommended that Council approves the new Capital Starts Programme with new borrowing of £27.535m, and approves procurement and contract awards to be signed off by Executive Directors under their Departmental Scheme of Delegation. Report 10.1, 4.1
Cabinet recommended that Council approves the detailed Planned Asset Maintenance Programme of £3.230m for 2026-27. Report 10.2, 4.2
Cabinet recommended that Council adopts the Treasury Management, Investment, Capital, Minimum Revenue Provision, and Flexible Use of Capital Receipts strategies for 2026-27. Report 10.3, 10.4, 10.5, 10.6, 10.7
Why
The Council must adopt a Treasury Management Strategy, an Investment Strategy and a Capital Strategy each year under the Local Government Act 2003 and the relevant CIPFA codes and statutory guidance. Report 11.3, 11.4, 11.5
Capital expenditure must form a programme, prioritised to match the Council Plan, make the most of scarce resources and comply with CIPFA's Prudential Code for Capital Finance in Local Authorities (2021). Report 11.2
The Council is committed to good financial management and compliance with applicable laws and regulations. Report 11.1
What happens next
Full Council to consider the seven recommendations in February. Report 11.2
Executive Directors to approve contract awards under their Departmental Scheme of Delegation once the programme is approved. Report 10.1
The capital programme approval process will be repeated each February. Report 11.2
The money
£27.535m Total new borrowing for the new Capital Starts Programme Report 4.1
£8.873m New borrowing required in 2026-27 Report 4.1
£6.786m New borrowing required in 2027-28 Report 4.1
£5.936m New borrowing required in 2028-29 Report 4.1
£4.216m New borrowing required in 2029-30 Report 4.1
£1.724m New borrowing required after 2030 Report 4.1
£3.230m Planned Asset Maintenance Programme for 2026-27 Report 4.2
Options considered
Chosen: Produce the report and recommend the strategies to Council. The Council is required to adopt a Capital Programme, Treasury Management Strategy, Investment Strategy and Capital Strategy each year Report 6.1
Rejected: Not produce the report. Would contravene the Council's Financial Regulations and other legislation and statutory guidance Report 6.1
Implications
Financial: Implications considered in preparing the report are set out in Appendix 1. Report 7.1, 9.1
Legal: Adoption of the Treasury Management Strategy is needed to meet the Council's legal obligation under the Local Government Act 2003 to have regard to the CIPFA Code. Report 11.3
Risk: The Treasury Management Strategy covers management of cash flow, borrowing, investments and the associated risks. Report 4.3
Who and where
Derbyshire County Council's overall finances, borrowing and investment balances Report 4.3, 4.4
Council services supported by capital expenditure and asset maintenance Report 4.5, 4.2
Residents and users of local public services Report 4.5
Timeline
2026-27: £8.873m new borrowing required Report 4.1
2027-28: £6.786m new borrowing required Report 4.1
2028-29: £5.936m new borrowing required Report 4.1
2029-30: £4.216m new borrowing required Report 4.1
After 2030: £1.724m new borrowing required Report 4.1
Each February: Council approves the capital programme Report 11.2
Plain English for the jargon
MRP: Minimum Revenue Provision, the amount set aside from revenue to repay debt used to finance capital expenditure
CIPFA: Body whose Prudential Code and Treasury Management Code the Council is required to follow
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item20/26
Resolved
RESOLVED to recommend to Council to: 1) Approve the new Capital Starts Programme as set out in appendix two to the report and approve the procurement and award of contracts which support the delivery of the Capital Programme. All contract awards will then be subject to approval by Executive Directors (via an Executive Director Report) under the relevant Departmental Scheme of Delegation; 2) Approve the detailed Planned Asset Maintenance Programme for 2026-27 as set out in appendix three to the report; 3) Adopt the Treasury Management Strategy for 2026-27 set out in appendix four to the report; 4) Adopt the Investment Strategy for 2026-27 set out in appendix five to the report; 5) Adopt the Capital Strategy for 2026-27 as set out in appendix six to the report; 6) Adopt the Minimum Revenue Provision Statement for 2026-27 as set out in Appendix seven to the report; and 7) Adopt the flexible use of the Capital Receipts Strategy as set out in Appendix eight to the report.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
3.1To obtain approval for proposals for submission to Council relating to the Capital Starts Programme and the Treasury Management, Investment and Capital Strategies. The report also includes a Minimum Revenue Provision (MRP) policy and a Flexible Use of Capital Receipts Strategy.
3.2This report should be read alongside the following reports to this Council meeting: the Reserves Position and Reserves Policy Report, the Budget Consultation Results Report for 2026-27 and the Revenue Budget Report 2026-27.
4 Information and Analysis
Capital Programme
4.1In line with previous years, the proposed new Capital Starts Programme has been evaluated and it is recommended to proceed with new borrowing of £27.535m for new projects commencing over the period. New borrowing of £8.873m will be required in 2026-27, £6.786m in 2027-28 £5.936m in 2028-29, £4.216m in 2029-30 and £1.724m after 2030. The detailed proposals are set out in Appendix 2 of this Report.
4.2A detailed list of the Planned Maintenance Programme of £3.230m for 2026-27 is set out in Appendix 3 of this Report.
Treasury Management and Investment Strategies
4.3The Treasury Management Strategy Report for 2026-27 (Appendix 4) sets out the Council’s management of its cash flow, borrowing and investments and the management of its associated risks.
4.4The Investment Strategy Report for 2026-27 (Appendix 5) deals with the management of the Council’s balances and reserves, managing the balance between risk and return.
Capital Strategy and Capital Financing
4.5The Capital Strategy for 2026-27 (Appendix 6) provides a high-level overview of how capital expenditure and capital financing contribute to the provision of local public services.
Minimum Revenue Provision (MRP) Policy 4.6 The Minimum Revenue Provision Statement for 2026-27 (Appendix 7) sets out how the amount to be put aside to repay debt used to finance capital expenditure is to be calculated.
Flexible Use of Capital Receipts Strategy 4.7 The Flexible use of capital receipts strategy for 2026-27 (Appendix 8) details the use of capital receipts for qualifying expenditure
Consultation
5.1No consultation is required.
Alternative options considered
6.1N/A – the Council is required to have an approved new Capital Starts Programme, and to adopt a Treasury Management Strategy, an Investment Strategy and a Capital Strategy each year. Not producing a Capital Programme Approvals, Treasury Management and Capital Strategies report would be contra to the Council’s Financial Regulations and other legislation and statutory guidance.
7 Implications
7.1Appendix One sets out the relevant implications considered in the preparation of the report. 8 Background Papers
8.1Not applicable.
Appendices
9.1Appendix 1 – Implications.
9.2Appendix 2 – New Capital Starts Programme for 2026-27.
9.3Appendix 3 – Planned Asset Maintenance Programme for 2026-27.
9.4Appendix 4 – Treasury Management Strategy Report for 2026-27.
9.5Appendix 5 – Investment Strategy Report for 2026-27.
9.6Appendix 6 – Capital Strategy for 2026-27.
9.7Appendix 7 – Minimum Revenue Provision Statement for 2026-27.
9.8Appendix 8 – Flexible Use of Capital Receipts.
Recommendations
That Cabinet recommends to Council that it:
10.1Approves the new Capital Starts Programme set out in Appendix Two and approves the procurement and award of contracts which support the delivery of the Capital Programme. All contract awards will then be subject to approval by Executive Directors (via an Executive Director Report) under the relevant Departmental Scheme of Delegation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.