To approve delegating the decision, in accordance with the Council’s Standing Orders, to the Executive Director – Place, in consultation with the Cabinet Member – Highways Assets and Transport, to accept Phase 3 Bus Services Improvement Plan funding to deliver long-term bus service improvements via the Department for Transport’s Network North funding, at an indicative value of £4.519m in 2024-25. To approve delegating the decision, in accordance with the Council’s Standing Orders, to the Executive Director – Place, in consultation with the Cabinet Member – Highways Assets and Transport, to accept Phase 3 Bus Services Improvement Plan funding to deliver long-term bus service improvements via the Department for Transport’s Network North funding, at an indicative value of £4.519m in 2024-25.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Bus Service Improvement Plan - Acceptance of BSIP Phase 3 Funding (Cabinet Member for Highways, Assets and Transport)
1. Divisions Affected
1.1County-wide.
2. Key Decision
2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are significant having regard to the budget for the service or function concerned (this is currently defined as £500,000) and it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.
3. Purpose
3.1To seek Cabinet approval to delegate the decision, in accordance with the Council’s Standing Orders, to the Executive Director – Place, in consultation with the Cabinet Member – Highways Assets and Transport and, to accept Phase 3 Bus Services Improvement Plan (BSIP) funding to deliver long-term bus service improvements via the Department for Transport’s Network North funding, at an indicative value of £4.519m in 2024-25. 4. Information and Analysis
4.1On 10 March 2022, Cabinet delegated authority to the Cabinet Member – Highways Assets and Transport and the Executive Director - Place, to accept the Bus Service Improvement Plan funding from the Department for Transport (DfT) (Minute No.64/22 refers). On 4 April 2022, the DfT informed the Council of an indicative award of £47.003m BSIP funding, comprising both revenue and capital funding, subject to receipt of further details. The Memorandum of Understanding (MoU) was received from the DfT and signed on 10 November 2022 under these delegated powers. Subsequently, the BSIP Year 1 funding was released to the Council in November 2022.
4.2On 23 October 2023, the Government announced the indicative allocation of a further £150m of 2024-25 funding for Local Transport Authorities (LTAs) to deliver long-term bus service improvements. This was the first instalment of a total of £1 billion, released as part of Network North - the third phase BSIP funding and is redirected funding which has been allocated to regions which were due to benefit from the cancelled HS2 investment.
4.3On 7 December 2023, the Council received notification from the DfT's Deputy Director for Local Transport, of its Phase 3 indicative allocation of up to £4.519m of revenue funding to further support delivery of Derbyshire BSIP in 2024-25. This funding is in addition to the existing Phase 1 BSIP funding allocation of £47.003m (Phase 2 was BSIP + funding which the Council did not receive).
4.4The DfT letter stated that the existing MoU in place for BSIP Phase 1 funding will apply to this additional Phase 3 funding. This letter amended the total funding allocated within the original MOU.
4.5Following the notification of the Phase 3 indicative allocation, the Enhanced Partnership (EP) Board on 20 February 2024, agreed that approval should be sought from the DfT to use the additional funding for further bus service enhancements and in addition, to request to change a proportion of funding £0.345m) from revenue to capital funding to provide for additional installation of Real Time Information (RTI) infrastructure in the County. RTI remains the single most requested bus service improvement after bus service enhancements from Derbyshire’s travelling public. Therefore, a request was formally submitted on this basis to the DfT for approval, as required, by 29 February 2024 deadline. A formal decision is currently awaited. 4.6 To avoid additional BSIP Programme delay caused by the anticipated late release of Phase 1 year 3 and Phase 3 funding (not anticipated before July 2024), approval is now sought for delegated approval to be granted to the Executive Director – Place, in consultation with the Cabinet Member - Highways, Assets and Transport to accept the Phase 3 BSIP funding settlement on behalf of the Council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.