Resolved
RESOLVED to: Approve the allocations for the project outlined in Appendix 2 to the report.
Cabinet approved this item on Wednesday 18 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to: Approve the allocations for the project outlined in Appendix 2 to the report.
6.1Children’s Services, in conjunction with Concertus Derbyshire and Contractors for the project have considered alternative options such as an additional phase to the overall project. However, this option would have severe financial implications as the pupils of the school would need to remain in the temporary learning village for an extended period of time, accruing even further costs to the project. After full consideration of all options, allocation of additional funding to complete the project and return the pupils to a fully operational school prove to be both cost effective to the overall project, and beneficial to pupil’s learning and staff wellbeing.
7. Implications
7.1Appendix 1 sets out the relevant implications considered in the preparation of the report.
These background papers are held on file in the Children’s Services Development Section and include information relating to net capacity and pupil forecasting; tendering information; project plans and specifications and cost status reports.
9.1Appendix 1 – Implications
9.2Appendix 2 – Further Allocations for approval
10. Recommendation(s)
That Cabinet:
a) Approves allocations for the project outlined in Appendix 2. 11. Reasons for Recommendation(s)
11.1Approval of funding for the outlined project will ensure completion, allowing pupils to return to the school.
11.2To reduce further expenditure for temporary learning facilities.
12. Is it necessary to waive the call in period?
12.1No
Report Nicola Ward Contact [email protected] Author: details: Appendix 1 Implications
Financial
1.1The funding required for this project will be taken from the Children’s Services Capital budget. The total to allocate is £1,285,780.
1.2If the allocations set out in Appendix 2 are approved, the unallocated Children’s Services Capital Budget will be as detailed below:-
Year Type of Opening Delegated Funding Allocations Balance Funding Balance Approval Received/ in this £ £ s Returned Report 2015-16 Basic 105,869 105,869 Need & School Condition 2016-17 Basic 347,387 347,387 Need & School Condition 2017-18 Basic 921,339 921,339 Need & School Condition 2018-19 Basic 794,779 794,779 Need & School Condition 2019-20 Basic 367,013 367,013 Need & School Condition 2020-21 School 0.00 0.00 Condition 2021-22 School 0.00 0.00 Condition 2022-23 School 0.00 0.00 Condition 2023-24 (for Basic 10,942,185 10,942,185 schemes to be Need delivered by Sept 2024) 2023-24 School 2,485,645 1,285,780 1,199,865 Condition 2024-25 School 9,125,147 9,125,147 Condition 2024-25 (for Basic 4,448,963 4,448,963 schemes to be Need delivered by Sept 2025) 2025-26 (for Basic 575,563 575,563 schemes to be Need delivered by Sept 2026) Total 30,113,890 1,285,780 28,828,110
Legal
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
for Approval of Additional Funding: Bramley Vale Primary School /24Appendix 2 | 66 KB | Download |
PDF |
Approval of Additional Funding: Bramley Vale Primary SchoolReport | 99 KB | DownloadRead as text |
Follow Cabinet at Derbyshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... | Noted | Open |
| 10 Sep 2026 | To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. | Approved | Open |
| 10 Sep 2026 | Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... | Noted | Open |
| 10 Sep 2026 | Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... | Approved | Open |
| 10 Sep 2026 | Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.