RESOLVED to: 1) Note the previously delegated approvals at Appendix 2 to the report; 2) Note the return of funds to the Capital Budget at Appendix 3 to the report; and 3) Approve allocations for the project outlined at Appendix 4 to the report.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
6.1Children’s Services, in conjunction with Concertus Derbyshire and Contractors for the project have considered alternative options such as an additional phase to the overall project. However, this option would have severe financial implications as the pupils of the school would need to remain in the temporary learning village for an extended period of time, accruing even further costs to the project. After full consideration of all options, allocation of additional funding to complete the project and return the pupils to a fully operational school prove to be both cost effective to the overall project, and beneficial to pupil’s learning and staff wellbeing.
7. Implications
7.1Appendix 1 sets out the relevant implications considered in the preparation of the report.
Background papers
These background papers are held on file in the Children’s Services Development Section and include information relating to net capacity and pupil forecasting; tendering information; project plans and specifications and cost status reports.
Appendices
9.1Appendix 1 – Implications
9.2Appendix 2 – Previous Delegated Approvals
9.3Appendix 3 – Funds Received/Returned to the Capital Budget
CONTROLLED 9.4 Appendix 4 – Allocations for approval from the Children’s Services Capital Budget.
10. Recommendation(s)
That Cabinet:
a) Notes the previously delegated approvals in Appendix 2. b) Notes the return of funds to the Capital Budget in Appendix 3. c) Approves allocations for the project outlined in Appendix 4.
11. Reasons for Recommendation(s)
11.1Approval of funding for the outlined project will ensure completion, allowing pupils to return to the school.
11.2To reduce further expenditure for temporary learning facilities.
1.1The funding required for this project will be taken from the Children’s Services Capital budget. The total to allocate is £560,000.
1.2If the allocations set out in Appendix 4 are approved, taking into account the previous delegated approvals in Appendix 2 and the return of funds in Appendix 3, the unallocated Children’s Services Capital Budget will be £29,063,333
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.