RESOLVED to approve: The withdrawal of the Masterplan formally approved by Cabinet on 20 December 2018; Continuing engagement with key stakeholders on future operational options for Elvaston Castle and Gardens Estate on the basis of the above decision; The current capital budget to be held and available for the Estate to fund delivery of the Countryside Service Enterprise Plan. The plan would include improvements for visitors and a scaled back number of low-cost, low-risk developments focused on increasing visitor numbers, to reduce the current financial subsidy, and keep the Estate maintained in line with health and safety standards; The Growth Fund of 0.050m per annum allocated to the Masterplan be transferred to the Countryside Service to fund additional staffing resource to support the delivery of the Enterprise Plan; Granting delegated authority to the Executive Director Place, in consultation with the Director of Legal and Democratic Services, to agree a new governance structure and collaboration agreement between the Council and Elvaston Castle and Gardens Trust; and Allocating funding of 0.028m to Elvaston Castle and Gardens Trust for 2025-26 financial year and for each of the following two years with a 3% uplift per annum.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Elvaston Castle and Gardens Masterplan Update (Cabinet Member for Clean Growth and Regeneration)
1. Divisions Affected
1.1Aston.
2. Key Decision
2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are, significant having regard to the budget for the service or function concerned (this is currently defined as £500,000).
3. Purpose
3.1To seek Cabinet approval for:
a) The withdrawal of the Masterplan formally approved by Cabinet on 20 December 2018. b) Continuing engagement with key stakeholders on future operational options for Elvaston Castle and Gardens Estate on the basis of this decision. c) The current capital budget to be held and available for the Estate to fund delivery of the Countryside Service Enterprise Plan. The plan will include improvements for visitors and a scaled back number of low-cost, low-risk developments focused on increasing visitor numbers, to reduce the current financial subsidy, and keep the Estate maintained in line with health and safety standards. d) The Growth Fund allocated to the Masterplan of £0.050m per annum to be transferred to the Countryside Service to fund additional staffing resource to support the delivery of the Enterprise Plan. e) Granting delegated authority to the Executive Director – Place, in consultation with the Director of Legal and Democratic Services to agree a new governance structure and collaboration agreement between the Council and Elvaston Castle and Gardens Trust. f) To allocate funding to Elvaston Castle and Gardens Trust of £0.028m for 2025-26 financial year and for each of the following two years with a 3% uplift per annum.
4. Information and Analysis
Background 4.1 On 20 December 2018, Cabinet approved the Elvaston Castle Masterplan (Minute No.306/18 refers) and reaffirmed this as the approved framework for guiding future development on 10 September 2020 (Minute No.160/20).
4.2The Masterplan was the key document, developed in partnership with Elvaston Castle and Gardens Trust (ECGT), which set out the vision and long terms objectives of the work required to provide a sustainable future for Elvaston Castle and Estate and maintain public access to the Estate. The Masterplan was also developed to help relieve the Council of significant on-going, annual maintenance and operating costs and resolve the major backlog of capital works to the buildings and landscape.
4.3The Masterplan arose from the exploration of options that had taken place over many years and the September 2020 report set out a process and allied funding strategy to deliver a £35.0m transformation of the site. The first phase of the Masterplan, for which a planning application was subsequently submitted, was to undertake improvement works to the many listed outbuildings on the Estate and build a new access road and carpark plus café. Cabinet approval for the approach was granted in 2020 subject to raising third party funding which was not fully secured at the time.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies