RESOLVED to: Note the receipt/availability of Section 106 funding and approve allocations to the projects outlined in Appendix 2; Approve the transfer of reimbursement to Basic Need 2017-18 to 2018-19 in the sum of £152,153.79 for Langley Mill Academy; Note the additional planning reference in relation to overall allocated Section 106 funds totalling £604,858 for Heanor Gate and the removal of previously allocated £50,000, providing a corrected allocation of £554,858.47; Approve the transfer of reimbursed Section 106 funds in the sum of £304,097.34 for Heanor Gate from Basic Need 2016-17 to add to the continuing expansion project; Note corrections to balances for Heanor Gate S106 Cabinet paper of 22 February 24, detailed above and in Appendix 2; and Note the reimbursement of S106 receipt to Basic Need Capital Budgets.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Report of the Executive Director of Children’s Services
Children’s Services Section 106 Allocations (Cabinet Member for Education)
1. Divisions Affected
1.1County-wide
2. Key Decision
2.1This is a key decision because it is likely to result in the Council incurring expenditure which is significant having regards to the budget for the service or function concerned. This level is set at £500,000. It is also significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.
3. Purpose
3.1To inform Cabinet of the receipt of recent Section 106 developer contributions and to seek approval for the allocation of those contributions to projects in line with the individual Section 106 agreements. 3.2 To inform Cabinet of Section 106 funding returned to the incorrect capital budget year for Langley Mill Academy on 25 July 2024 Children’s Services Section 106 cabinet paper and to seek approval for these funds to be transferred to the correct Capital Budget year. 3.3 To inform Cabinet of a missed planning reference relating to the Section 106 funds to Heanor Gate within a S106 Cabinet report of 22 February 2024. 3.4 To inform Cabinet of incorrectly allocated receipt of Section 106 funds for Heanor Gate to reimburse the Children’s Services Capital Budget Basic Need 2016-17. These funds should instead have been allocated to the continuing project. 3.5 To inform Cabinet of incorrectly reported amounts within the 22 February report relating to Planning Reference AVA/2014/0817 and incorrect total approved allocations figure, detailed in Appendix 2.
4. Information and Analysis
4.1Appendix 2 details the Section 106 contributions that have been received by the Authority. The Appendix details the schools that are to benefit from the investment, together with the planned projects.
4.2On 25 July 2024, Cabinet approved the reimbursement of the Children’s Services Capital Basic Need 2017-18 of £152,153.79 from Section 106 funds for Langley Mill Academy. This was incorrect and instead the 2018-19 Basic Need budget should have been reimbursed. Approval is sought to transfer this amount from 2017-18 to 2018-19 to reconcile the Children’s Services Capital budget.
4.2On 10 July 24, Cabinet approved receipt of Section 106 funds, Heanor Gate from AVA/2015/0403 Shipley Lakeside in the sum of £304,097.34. These funds were approved to repay Children’s Services Basic Need 2016-17. However, these funds should have been added to the project as there are further triggers of Section 106 expected from this development to later utilise in the repayment of the Children’s Services Budget. Approval is requested to add receipt of these Section 106 funds to the project and adjust the 2016-17 Basic Need budget accordingly. Appendix 2 will outline the reallocation of these funds to the project and reconcile the Basic Need 2016-17 budget in the October Children’s Services Capital Expenditure Cabinet paper.
4.3On 22 February 24, Cabinet approved a Section 106 paper seeking to allocate £604,858 to Heanor Gate from planning reference AVA/2014/0817, Heanor Road, Smalley. However, the amount of £604,858 should have noted two planning references. The approved planning reference, AVA/2014/0817 infact totalled £302,309.68 made up of £140,815.03; £6,431.48; £147,167.66; £6,720.19 and £1,175.32. The remainder of £302,548.79 related to the missed planning reference AVA/2012/1157, Heanor Road, Smalley. However, this figure was incorrect as it included £50,000.00 that had already been approved by cabinet on 29 July 2020 and should therefore have been deducted from this amount, totalling £252,548.79, making the overall allocated S106 £554,858.47. For accuracy and preciseness, the missing planning reference and correct balance has been added to this paper and the overall project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.