RESOLVED to: 1) Formally approve the acceptance of the Active Travel Capability Fund grant of £0.427m provided under Section 31 of the Local Government Act, 2003 to support development of the schemes detailed in the report; 2) Approve the proposed next steps to further develop the strategic interventions as highlighted in the report; 3) Approve the initiating of public engagement activities to further develop the Active Travel Master plans; and 4) Delegate to the Executive Director - Place, in consultation with the Cabinet Member for Infrastructure and Environment, the authority to amend or modify the Active Travel Masterplan programme as required and if it remains consistent with the Council’s objectives.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Active Travel England Grant Acceptance and Proposed Spend Programme (Cabinet Member for Infrastructure and Environment)
1. Divisions Affected
1.1County-wide.
2. Key Decision
2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are significant having regard to the budget for the service or function concerned (this is currently defined as £500,000).
3. Purpose
3.1The purpose of this report is to set out the range of activity funded by Active Travel England which supports the Council’s sustainable travel ambitions.
3.2To seek Cabinet approval to:
a) Formally accept the Active Travel Capability Fund grant of £0.427m provided under Section 31 of the Local Government Act, 2003 to support development of the schemes detailed in this report. b) Approve the proposed next steps to further develop the strategic interventions as highlighted in the report.
CONTROLLED c) Approve the initiating of public engagement activities to further develop the Active Travel Master plans. d) Delegate to the Executive Director - Place, in consultation with the Cabinet Member for Infrastructure and Environment, the authority to amend or modify the Active Travel Masterplan programme as required and if it remains consistent with the Council’s objectives.
4. Information and Analysis
4.1The Council Plan Refresh 2024-25 sets out a strategic objective to develop and deliver a strategic approach to sustainable travel and integrated transport across the County. The development and implementation of an Active Travel Programme is a key planned activity to support delivery of a strong, diverse and clean economy. Working with its partner organisations, the Council has a strong track record of delivering the Programme which has provided just over 323km of new multi-user routes as part of Derbyshire’s Cycle Networks since the year 2000. More recent examples include the Chesterfield East-West Active Travel Route, Clowne Greenway, and sections of the White Peak Loop and Bolsover Loop.
4.2The Council’s Active Travel Programme encompasses delivery of both infrastructure and behavioural change programmes which support more people walking, wheeling and cycling for leisure and utility journeys. It is an ongoing programme of activity funded predominantly by external Government grants and dedicated local sources, including the Council’s Challenge Fund. Recent Cabinet approvals associated with previous Active Travel England grant offers are:
• Approval of a forward plan and acceptance of a first £0.285m allocation of Active Travel Capability and Ambition Fund grant for developing Active Travel Masterplans for Market towns in Derbyshire (Minute No. 49/23 refers). • Acceptance of £3.005m grant funding from Tranche Four of the Active Travel Fund for constructing the Little Eaton Branch Line (LEBL) as part of the Derby City to Ripley Active Travel Route and undertaking preparatory work on the remaining gaps in the White Peak Loop (WPL) around Buxton (Minute No. 90/23 refers). • Acceptance of £0.143m Active Travel Capability and Ambition Fund to extend the Active Travel Masterplan programme to development of a masterplan for the Hope Valley (Minute No 28/24 refers).
Update on Development of Active Travel Master Plans 4.3 Active Travel England (ATE) is the Government’s executive agency responsible for making walking, wheeling and cycling the preferred
CONTROLLED choice for everyone to get around. It provides funding to local authorities under two grant programmes:
• Capability Fund: to develop infrastructure plans and designs, public consultation, and evidence collection. • Active Travel Fund: development and/or construction of inclusive walking, wheeling and cycling schemes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.