Resolved
That the Committee notes the progress report of the External Auditors.
Audit Committee decided this item on Friday 28 February 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee notes the progress report of the External Auditors.
DRAFT Auditor’s Annual Report Derbyshire County Council – year ended 31 March 2024
February 2025 Contents
01 Introduction 02 Audit of the financial statements 03 Commentary on VFM arrangements 04 Other reporting responsibilities 05 Audit of the Pension Fund
A Appendix A: Further information on our audit of the Council’s financial statements B Appendix B: Further information on our audit of the Pension Fund’s financial statements
Our reports are prepared in the context of the ‘Statement of Responsibilities of auditors and audited bodies’ and the ‘Appointing Person Terms of Appointment’ issued by Public Sector Audit Appointments Limited. Reports and letters prepared by appointed auditors and addressed to the Council are prepared for the sole use of the Council and we take no responsibility to any member or officer in their individual capacity or to any third party. Forvis Mazars LLP – Park View House, 58 The Ropewalk, Nottingham NG1 5DW Tel: 0115 964 4744 – www.forvismazars.com/uk Forvis Mazars LLP is the UK firm of Forvis Mazars Global, a leading global professional services network. Forvis Mazars LLP is a limited liability partnership registered in England and Wales with registered number OC308299 and with its registered office at 30 Old Bailey, London, EC4M 7AU. Registered to carry on audit work in the UK by the Institute of Chartered Accountants in England and Wales. Details about our audit registration can be viewed at www.auditregister.org.uk under reference number C001139861. VAT number: GB 839 8356 73
2 Introduction 01 Introduction
Purpose of the Auditor’s Annual Report Our Auditor’s Annual Report (AAR) summarises the work we have undertaken as the auditor for Derbyshire County Council (‘the Council’) for the year ended 31 March 2024. Although this report is addressed to the Council, it is designed to be read by a wider audience including members of the public and other external stakeholders. Our responsibilities are defined by the Local Audit and Accountability Act 2014 and the Code of Audit Practice (‘the Code’) issued by the National Audit Office (‘the NAO’). The remaining sections of the AAR outline how we have discharged these responsibilities and the findings from our work. These are summarised below.
Opinion on the financial statements Value for Money arrangements We expect to issue an audit report which includes a disclaimer of opinion. This means our In our audit report we will report that we are not satisfied arrangements were in place for the audit report will not express an opinion on the financial statements and no assurance will be Council to secure economy, efficiency and effectiveness in its use of resources, this is because provided. It is necessary to issue a disclaimer of opinion as amendments to the Account and we are issuing two recommendations in relation to significant weaknesses in those Audit Regulations introduced a statutory deadline for publication of the Council’s financial arrangements that are relevant to the 2023/24 financial year. Section 3 provides our statements. We are unable to complete the audit procedures necessary to obtain sufficient commentary on the Council’s arrangements and a summary of our recommendations, and the appropriate audit evidence on which to base our opinion before the date the Council weaknesses identified. publishes its audited financial statements.
Wider reporting responsibilities At the date of reporting our work on the Council’s Whole of Government Accounts return remains incomplete whilst we wait for final instructions from the National Audit Office.
4 Audit of the financial statements 02 Audit of the financial statements
Our audit of the financial statements
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
DCC Draft AAR 23-24 final /25Report | 3.1 MB | DownloadRead as text |
PDF |
To consider the reports of the External AuditorReport | 2.4 MB | Download |
Follow Audit Committee at Derbyshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Place Department Risk ManagementIt was agreed that the Chairman take a request to Cabinet to open the project to scrutiny by the Committee bearing in... | Agreed | Open |
| 14 Jul 2026 | Performance Monitoring and Budget Monitoring Outturn 2025-26 as at Quarter 4 (31 March 2026)RESOLVED that the Committee notes: a) The Council Plan performance and Revenue outturn position for 2025-26; b) The c... | Decided | Open |
| 14 Jul 2026 | Internal Audit Charter UpdateRESOLVED that the Committee approve the Council’s Internal Audit Charter. | Approved | Open |
| 14 Jul 2026 | Counter Fraud Strategy UpdateRESOLVED to approve the Counter Fraud Strategy 2026-27 as appended at Appendix 2 to the report. | Approved | Open |
| 14 Jul 2026 | National Fraud Initiative UpdateRESOLVED that the Committee note the outcomes to date of the Council’s participation in the NFI 2024-25 exercise and ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.