Resolved
RESOLVED that the Committee notes the reports of the External Auditor.
Audit Committee decided this item on Tuesday 18 March 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Committee notes the reports of the External Auditor.
Audit Committee Derbyshire County Council County Hall Matlock Derbyshire DE4 3AG
28 February 2025
Dear Committee Members
Derbyshire Pension Fund
Follow-up letter to our Audit Completion Report in relation to the 2023/24 audit
As required by International Standards on Auditing (UK), this letter communicates an update on progress on concluding upon those matters that were marked as outstanding within our Audit Completion Report follow up letter, which was presented to the Audit Committee on 3 December 2024. The outstanding matters and conclusions reached are set out below:
Audit area Status Findings and conclusion reached Investment assets Complete We completed the outstanding work. Our work has testing – Level 3 provided the required assurance, and we have no matters assets to report.
Notes to the accounts Complete We completed our work. Note 14 discloses the Related Party Transactions and in this note the Fund discloses that its equity shareholding in LGPS Central is accounted for at historic cost. The value is highly immaterial at £1.3m, and our audit work confirmed the fair value of the investment is different by only a trivial amount. We discussed with the Pension Fund the disclosures in the accounts and the accounting requirement to value equity investments at fair value. We further identified disclosure misstatements, which have been corrected by the Management and are included in Appendix A.
IT Controls audit work Complete Work has been completed and there are no matters to report.
Consistency Complete We have reviewed the financial statements disclosed in Statement the Annual Report and confirmed these are consistent with the financial statements included in the signed 2023/24 Derbyshire County Council financial statements.
Signed financial Complete The signed financial statements and letter of statements and letter representation have been received. of representation Audit area Status Findings and conclusion reached Audit review and Complete Our audit quality control procedures are now complete. control procedures Minor disclosure adjustments were made to the final financial statements in response to our final checks.
Post balance sheet Complete We have reviewed post balance sheet events up to the events date of signing the audit opinion. There are no matters to report.
If you wish to discuss any of the points raised in this letter, then please do not hesitate to contact me on [phone removed]. Yours sincerely
Alastair Newall Key Audit Partner Appendix A – Disclosure misstatements
Management corrected the draft financial statements for the following disclosure misstatements:
• Note 1 Basis of Preparation: The going concern disclosure was updated to reflect the Code requirements. • Note 5 Assumptions made and other estimation uncertainty: 'Actuarial Present Value of Promised Retirement Benefits' disclosure was removed to comply with IAS 1 requirements. • Note 5 Assumptions made and other estimation uncertainty: The note was updated to include disclosure of a relevant legal case. • Note 13 Basis of Valuation: Non-Investment assets or liabilities are also included in the note as financial instruments. • An additional note (Note 22) was added to disclose ‘Subsequent Events’
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Derbyshire Pension Fund: Audit Completion follow-up letter 2023-24 Final /25Report | 137 KB | DownloadRead as text |
PDF |
To consider the reports of the External AuditorReport | 681 KB | Download |
Follow Audit Committee at Derbyshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Place Department Risk ManagementIt was agreed that the Chairman take a request to Cabinet to open the project to scrutiny by the Committee bearing in... | Agreed | Open |
| 14 Jul 2026 | Performance Monitoring and Budget Monitoring Outturn 2025-26 as at Quarter 4 (31 March 2026)RESOLVED that the Committee notes: a) The Council Plan performance and Revenue outturn position for 2025-26; b) The c... | Decided | Open |
| 14 Jul 2026 | Internal Audit Charter UpdateRESOLVED that the Committee approve the Council’s Internal Audit Charter. | Approved | Open |
| 14 Jul 2026 | Counter Fraud Strategy UpdateRESOLVED to approve the Counter Fraud Strategy 2026-27 as appended at Appendix 2 to the report. | Approved | Open |
| 14 Jul 2026 | National Fraud Initiative UpdateRESOLVED that the Committee note the outcomes to date of the Council’s participation in the NFI 2024-25 exercise and ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.