RESOLVED to: 1) Note the findings resulting from the due diligence work carried out on the outline business case; 2) Approve the recommendation to deliver the project via a master developer who would work with the council to deliver the overall vision, and its individual component parts and to come back to Cabinet for approval of the recommended partner following that process; 3) Approve the recommended procurement route for the master developer via a competitive, two stage, flexible tender procedure and delegate to the Executive Director for Corporate Services and Transformation the ability to oversee the tender process and negotiate the final details ahead of a report back to Cabinet before final appointment.; 4) Note the cost of the next steps for the project, including the submission of the outline planning application, enabling works to the site, further work to develop and de-risk the project and develop the Council’s requirements and specialist support for the procurement process and approve expenditure against the sum of £4.244m allocated in the capital programme for these purposes; 5) Authorise the procurement of specialist consultants and legal advisors as necessary to support the procurement of a master developer and initial site enabling works; and 6) Authorise the Executive Director – Corporate Services and Transformation, in consultation with the Director of Legal and Democratic Services to procure and appoint such consultants as may be required to deliver the next steps.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Report of the Executive Director – Corporate Services and Transformation
Smedley's Hydro Development (Cabinet Member for Corporate Services and Budget)
1. Divisions Affected
1.1County Wide
2. Key Decision
2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are significant having regard to the budget for the service or function concerned (this is currently defined as £500,000) and it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.
3. Purpose
3.1In November 2022 CMT/Cabinet received and noted the findings of the Strategic Outline Business Case (SOBC) appraising options for the future use of County Hall and approved a shortlist of four options to be taken forward to the next stage – Outline Business Case - for more detailed analysis of the deliverability and benefits of each.
CONTROLLED 3.2 In January 2024 the outcome of that detailed analysis was presented to cross party members, local businesses and other key stakeholders and a report taken to cabinet, who approved the recommended option for the future of County Hall in which the Council moves to a smaller new office building on the Matlock site and the main County Hall campus is regenerated to deliver a mixed use development, including hotel, event and conferencing facilities, new homes and business and community spaces, being Option 3 in the SOBC. Delegation was given to the Director of Property, in consultation with the Director of Legal and Democratic Services the power to procure and appoint such consultants as may be required for due diligence and development of the Option 3, along with provision in the capital programme to support this work.
3.3The purpose of this report is to: • Update members on the outcome of that due diligence work and analysis of the business case, including testing and removing risk from the financial case, technical assessments on the buildings and engagement with the market. • Make a recommendation to move forward with the project as far as the next governance gateway, which will involve further risk mitigation, enabling works and procuring a master developer to work with the council to deliver the overall vision, and its individual component parts and to come back to Cabinet with the recommended partner for approval following that process. • To ask Cabinet note that the costs for moving to the next stage governance gateway have been included in the 25-26 Capital Programme and approve that expenditure. • To seek Cabinet approval to delegate to the Executive Director of Corporate Services and Transformation, in consultation with the Director of Legal and Democratic Services the power to procure and appoint such consultants as may be required including where appropriate the extension or variation of existing contracts and to oversee the procurement process for the master developer, prior to final cabinet approval
4. Information and Analysis
4.1Derbyshire County Council, like many other local authorities, is transforming the way in which it works and delivers services. Focusing on work being what you do and not where you go, and enabling its workforce to operate in flexible ways, utilising a hub approach across the county. This approach supports a responsive and agile culture, reduces journey times and carbon footprint and supports a model for a more efficient corporate estate.
CONTROLLED 4.2 The need to reduce the size of the corporate estate to an affordable size, whilst still supporting dynamic and effective service delivery, has become increasingly vital as pressure on available budgets grows and is a strategic objective in the Council Plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.