Smedley's Hydro Development

Noted Executive 3 papers

Cabinet noted this item on Thursday 13 March 2025. Below is the council's own wording, with the papers it was decided on.

Item52/25

Resolved

RESOLVED to: 1) Note the findings resulting from the due diligence work carried out on the outline business case; 2) Approve the recommendation to deliver the project via a master developer who would work with the council to deliver the overall vision, and its individual component parts and to come back to Cabinet for approval of the recommended partner following that process; 3) Approve the recommended procurement route for the master developer via a competitive, two stage, flexible tender procedure and delegate to the Executive Director for Corporate Services and Transformation the ability to oversee the tender process and negotiate the final details ahead of a report back to Cabinet before final appointment.; 4) Note the cost of the next steps for the project, including the submission of the outline planning application, enabling works to the site, further work to develop and de-risk the project and develop the Council’s requirements and specialist support for the procurement process and approve expenditure against the sum of £4.244m allocated in the capital programme for these purposes; 5) Authorise the procurement of specialist consultants and legal advisors as necessary to support the procurement of a master developer and initial site enabling works; and 6) Authorise the Executive Director – Corporate Services and Transformation, in consultation with the Director of Legal and Democratic Services to procure and appoint such consultants as may be required to deliver the next steps.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Cabinet

FOR PUBLICATION

DERBYSHIRE COUNTY COUNCIL

CABINET

Thursday, 13 March 2025

Report of the Executive Director – Corporate Services and Transformation

Smedley's Hydro Development (Cabinet Member for Corporate Services and Budget)

1. Divisions Affected

1.1County Wide

2. Key Decision

2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are significant having regard to the budget for the service or function concerned (this is currently defined as £500,000) and it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.

3. Purpose

3.1In November 2022 CMT/Cabinet received and noted the findings of the Strategic Outline Business Case (SOBC) appraising options for the future use of County Hall and approved a shortlist of four options to be taken forward to the next stage – Outline Business Case - for more detailed analysis of the deliverability and benefits of each.

CONTROLLED 3.2 In January 2024 the outcome of that detailed analysis was presented to cross party members, local businesses and other key stakeholders and a report taken to cabinet, who approved the recommended option for the future of County Hall in which the Council moves to a smaller new office building on the Matlock site and the main County Hall campus is regenerated to deliver a mixed use development, including hotel, event and conferencing facilities, new homes and business and community spaces, being Option 3 in the SOBC. Delegation was given to the Director of Property, in consultation with the Director of Legal and Democratic Services the power to procure and appoint such consultants as may be required for due diligence and development of the Option 3, along with provision in the capital programme to support this work.

3.3The purpose of this report is to: • Update members on the outcome of that due diligence work and analysis of the business case, including testing and removing risk from the financial case, technical assessments on the buildings and engagement with the market. • Make a recommendation to move forward with the project as far as the next governance gateway, which will involve further risk mitigation, enabling works and procuring a master developer to work with the council to deliver the overall vision, and its individual component parts and to come back to Cabinet with the recommended partner for approval following that process. • To ask Cabinet note that the costs for moving to the next stage governance gateway have been included in the 25-26 Capital Programme and approve that expenditure. • To seek Cabinet approval to delegate to the Executive Director of Corporate Services and Transformation, in consultation with the Director of Legal and Democratic Services the power to procure and appoint such consultants as may be required including where appropriate the extension or variation of existing contracts and to oversee the procurement process for the master developer, prior to final cabinet approval

4. Information and Analysis

4.1Derbyshire County Council, like many other local authorities, is transforming the way in which it works and delivers services. Focusing on work being what you do and not where you go, and enabling its workforce to operate in flexible ways, utilising a hub approach across the county. This approach supports a responsive and agile culture, reduces journey times and carbon footprint and supports a model for a more efficient corporate estate.

CONTROLLED 4.2 The need to reduce the size of the corporate estate to an affordable size, whilst still supporting dynamic and effective service delivery, has become increasingly vital as pressure on available budgets grows and is a strategic objective in the Council Plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for Smedley's Hydro Development /25Appendix 2 58 KB Download
PDF
/25Appendix 3 7.2 MB Download
PDF
Smedley's Hydro DevelopmentReport 308 KB DownloadRead as text

At this meeting

Whole meeting
47/25To approve, as a correct record, the non-exempt minutes of the meeting held on 20 February 2025Approved 48/25Memorandum of Understanding with Khmelnytskyi Region in UkraineApproved 49/25Performance Monitoring and Budget Monitoring/Forecast Outturn 2024-25 as at Quarter 3 (31 December 2024)Noted 50/25Capital budget monitoring and forecast as at Quarter 3 2024-25Noted 51/25One Council Support Functions Budget VirementApproved
52/25Smedley's Hydro DevelopmentThis decision
53/25High Needs Block Funding Settlement 2025-26Noted 54/25Early Years Block Funding Settlement 2025-26Noted 55/25Central School Services Block Funding Settlement 2025-26Noted 56/25Childcare Expansion Capital Grant Funding AllocationsApproved 57/25Supplemental Substance Misuse Treatment and Recovery Grant: Funding in 2025/26Approved 58/25Additional Government stop smoking funding 2025/26Agreed 59/25Centralisation of ICT Budgets Across the CouncilApproved 60/25Care Home Fee Proposals 2025-26Agreed 61/25Home Care and Day Care Fees 2025-26Agreed 62/25Approval to extend the Bus Service Improvement Plan Programme and associated Delegated Powers in 2025-26Approved 63/25Regeneration Pipeline Programme – South Derbyshire Growth ZoneNoted 64/25Regeneration Programme PipelineApproved 65/25Rejuvenating the Glapwell Countryside SiteNoted 66/25Exclusion of the PublicDecided 67/25To approve, as a correct record, the exempt minutes of the meeting held on 20 February 2025Private 68/25Approval to Extend the Supported Tendered Local Bus Service Contracts to Facilitate their Transition to the East Midlands Combined County AuthorityPrivate 69/25Derbyshire Constabulary Contract Extension for Vehicle Maintenance, Service, Repair and Breakdown, Accident Damage and CommissioningPrivate 70/25Extension to Financial Value of the Contract for the Design, Supply, Installation and Maintenance of Intelligent Transport SystemsPrivate 71/25Acceptance of Grant from Department for Transport for Safer Roads FundPrivate

Who was there

8 of 18 attended
BL
Councillor Barry LewisChairman, present
SS
Councillor Simon SpencerVice-Chairman, present
CC
Councillor Charlotte CupitCommittee Member, present
AD
Councillor Alex DaleCommittee Member, present
CH
Councillor Carol HartCommittee Member, apologies
NH
Councillor Natalie HoyCommittee Member, present
TK
Councillor Tony KingCommittee Member, present
JP
Councillor Julie PattenCommittee Member, present
CR
Councillor Carolyn RenwickCommittee Member, present
EA
Emma AlexanderOfficer, in attendance
HB
Helen BarringtonOfficer, in attendance
CH
Chris HenningOfficer, in attendance

All 18 on the meeting page

More from Derbyshire Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... Noted Open
10 Sep 2026 To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. Approved Open
10 Sep 2026 Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... Noted Open
10 Sep 2026 Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... Approved Open
10 Sep 2026 Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies