RESOLVED to: 1) Approve the proposed Derbyshire regeneration pipeline - programme areas and longlist of potential projects as set out in Appendix 2 of the report; 2) Note the update to the potential range of funding streams likely to be made available by the East Midlands Combined County Authority in the immediate and medium term; 3) Approve the projects likely to be suitable for accessing early investment opportunities in 2025-26 under the East Midlands Combined County Authority’s available funding programmes; 4) Agree that the Executive Director – Place be given delegated authority to make initial funding applications to EMCCA in line with the proposed programmes and projects set out in Appendix 2 of the report; 5) Agree that the Executive Director – Place be given delegated authority to approve the acceptance of specific offers of funding for Pipeline programmes and projects, in liaison with the Director of Finance and the Cabinet Members for Infrastructure and Environment, Highways and/or Clean Growth and Regeneration, as appropriate, and to authorise any required consultation for funded projects; 6) Approves in principle: (a) the receipt of grant funding from EMCCA; (b) the addition of funded projects to the Council’s capital programme and the commercial pipeline; (c) the carrying out of public consultation in relation to proposed projects, as required: (d) the distribution of grant funding, including monies passported to the Council from EMCCA, to outside bodies where appropriate (as detailed in paragraph 4.24 of the report); and 7) Agree that officers continue to assess the Derbyshire Regeneration Pipeline (Appendix 2) and identify appropriate funding opportunities for bringing forward programmes and projects as and when they become available, including opportunities for financial year 2026-27 and beyond.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Regeneration Programme Pipeline East Midlands Combined County Authority Investment Programmes (Cabinet Member for Infrastructure and Environment)
1. Divisions Affected
1.1County-wide.
2. Key Decision
2.1This is a key decision because it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.
3. Purpose
3.1Overall, the purpose of this report is four-fold:
• To set out the Council’s Regeneration Pipeline for 2025 onwards, both at programme and project level • To outline the funding opportunities that have already emerged, and are emerging, from the East Midlands Combined County Authority (EMCCA) • To outline proposals for early priority projects, capable of taking advantage of EMCCA funding in 2025-26 • To ensure the appropriate approvals and preparations are in place to help the Council maximise the benefits of EMCCA funding at the very earliest opportunity.
CONTROLLED 3.2 In relation to these three broad areas, this report specifically seeks:
3.3Approval from Cabinet on the proposed Derbyshire regeneration pipeline - programme areas and longlist of potential projects as set out in Appendix 2.
3.4To update Cabinet on the potential range of funding streams likely to be made available by the East Midlands Combined County Authority in the immediate and medium term.
3.5To identify and seek approval for projects likely to benefit from early investment opportunities in 2025-26 under the East Midlands Combined County Authority’s available funding programmes.
3.6To agree the Executive Director – Place be given delegated authority to make initial funding applications to EMCCA in line with the proposed programmes and projects set out in Appendix 2.
3.7To agree the Executive Director – Place be given delegated authority to approve the acceptance of specific offers of funding for Pipeline programmes and projects, in liaison with the Director of Finance and the Cabinet Members for Infrastructure and Environment, Highways and/or Clean Growth and Regeneration, as appropriate, and to authorise any required consultation for funded projects.
3.8Approval in principle to:
a) the receipt of grant funding from EMCCA b) the addition of funded projects to the Council’s capital programme and the commercial pipeline c) the carrying out of public consultation in relation to proposed projects, as required d) the distribution of grant funding, including monies passported to the Council from EMCCA, to outside bodies where appropriate (as detailed in paragraph 4.24 of the report)
3.9To agree that officers continue to assess the Derbyshire Regeneration Pipeline (Appendix 2) and identify appropriate funding opportunities for bringing forward programmes and projects as and when they become available, including opportunities for financial year 2026-27 and beyond.
CONTROLLED 4. Information and Analysis
Overview: Project Funding for 2024-25 4.1 Cabinet is aware that at its meeting of 7 December 2023, Full Council agreed to the creation of the East Midlands Combined County Authority (EMCCA), with the Council (DCC) as a Constituent Member (Minute No.100/23 refers). ‘Maximising the benefits of the devolution deal’ which accompanied the creation of EMCCA has been adopted as a Council Plan objective.
4.2Cabinet has recently considered two reports relating to EMCCA funding. The first of these was in relation to the East Midlands Investment Zone (EMIZ) at its meeting of 14 November 2024 (Minute No.170/24 refers) at which, approval in principle was given: to the receipt of EMIZ grant funding; the addition of funded projects to the capital programme/commercial pipeline; and the carrying out of consultation where required.
4.3Two Council projects are to be funded by EMIZ (circa £0.245m):
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.