AI summaryDerbyshire County Council has formally opposed large-scale solar farms and battery storage on greenfield sites. It will write to local councils, MPs and the Energy Secretary. Five other motions were deferred after a vote to extend the meeting failed.
Written from the decision and the officer reportPDF Pro
OutcomeDeferredVote to extend meeting by one hour was lost
MoneyNot stated
What happens nextNot stated
Who it affectsGreenfield sites in DerbyshireLarge-scale solar and battery storage proposals
What was decided
The Council recorded its opposition, in principle, to large-scale solar farms and battery energy storage systems on greenfield sites in Derbyshire.
The Council expressed solidarity with local residents and parish councils who raised concerns about these proposals.
The Council agreed to make its position known to Derbyshire Borough and District Councils, local MPs, and the Secretary of State for Energy Security and Net Zero.
Why
The supporting papers cite concerns about the loss of agricultural land to energy development and food security. Report P9, P12, P13
Papers argue the proposals would significantly change the rural character of the area and add to landscape and traffic impacts. Report P10, P11
Papers warn that cumulative impact of multiple large-scale projects risks undermining public confidence and places disproportionate pressure on one district. Report P15
What happens next
Officers or the Council will write to Derbyshire Borough and District Councils, local MPs and the Secretary of State for Energy Security and Net Zero setting out the position.
A motion to extend the meeting by one hour was lost, so the remaining five motions were deferred to the next meeting.
Options considered
Chosen: Pass Motion One opposing solar and BESS on greenfield sites. Decision wording records it as resolved
Rejected: Extend the meeting by one hour to 6:00 pm to consider remaining business. Vote declared lost, so meeting ended at 5:00 pm
Implications
Legal: The papers note Derbyshire County Council is not the determining planning authority for these applications; this is a position statement only. Report P11
Other: The position is symbolic, expressing council view rather than altering planning decisions made by South Derbyshire District Council. Report P11
Who and where
Local residents and parish councils in Derbyshire who have raised concerns about solar and BESS proposals Report P5
South Derbyshire District Council, as the determining planning authority for the cited applications Report P5, P11
Derbyshire Borough and District Councils, local MPs, and the Secretary of State for Energy Security and Net Zero, who will receive the Council's position
Developers of large-scale solar and battery storage schemes on greenfield sites in Derbyshire Report P8
Timeline
2025-10-08: Derbyshire County Council meeting considers Notice of Motions; Motion One is decided and motions two to six are deferred
Plain English for the jargon
BESS: Battery Energy Storage System, a facility that stores electrical energy in batteries for later release to the grid.
Greenfield site: Land that has not previously been built on, typically agricultural or undeveloped countryside.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item80/25
Resolved
1) To record its opposition, in principle, to the development of large-scale solar farms and battery energy storage systems on greenfield sites in Derbyshire. 2) To express solidarity with local residents and parish councils who have raised concerns about the impact of these proposals; and 3) To make this Council’s position known to Derbyshire Borough and District Councils, local MPs, and the Secretary of State for Energy Security and Net Zero. With the time approaching 5:00 pm and on the motion of Councillor Wheelton, duly seconded, that under rule 4.1 of the Council Procedure Rules the meeting should be extended by 1 hour to continue until 6:00 pm to enable the remaining business on the agenda to be considered. A vote was taken which was declared LOST; therefore the meeting would finish at 5pm and any remaining business would be deferred until the next meeting. Due to time constraints the remaining motions were deferred and would be ... view the full minutes text for item 80/25
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Title: Opposition to Large-Scale Solar and Battery Storage Developments in South Derbyshire Proposer of motion: Councillor Alan Graves
Background/supporting information:
These applications are current in South Derbyshire Trees / hedgerow / Site Site area (ha / habitat loss reported Key source(s) (location) acres) (what the documents say) Arboricultural survey: 321 trees, groups & hedgerows were recorded/surveyed. Reported hedgerow loss 241 m. The AIA says a small number of Oaklands individual trees would Farm 191 ha (≈ 472 need removal for Oaklands AIA / ES Solar Park acres) proposed for access/cable corridors (Arboricultural Survey & (west of the DCO area but does not publish a Applicant responses). Planning Rosliston / (project documents single “total trees to be Inspectorate+2Planning east of state ~191 ha). felled” figure in the Inspectorate+2 Walton-on- main ES docs I Trent) accessed; ancient/veteran trees and Ancient Semi- Natural Woodland are to be protected (buffers/RPAs retained). Project boards note trees and a hedge along the southern boundary; project literature refers to Stenson boundary vegetation Lane ESS retained/managed but I (east of did not find a Stenson) ~23 acres Innova Stenson Lane project published tree-by-tree — (developer-stated). page / project PDF. Innova+1 removal count in the proposed public project battery summary. Detailed ESS AIA/EcIA material is referenced on the project site / boards and would be where precise counts appear. Public notice / application summary Planning application indicates BESS on page (BESS) — site farmland; the planning area shown on submission references application Egginton ecological/landscape South Derbyshire planning documents (see BESS reports. I did not find a listing & parish note for application (Derby simple published “trees Egginton BESS DMPA/2024/0432). Road, to be removed = N” in (DMPA/2024/0432). (Area shown in Egginton) the public summary — southderbyshire.my.site.com+1 application that detail is usually in forms/drawings; see the Arboricultural council application Report or EcIA record.) appendices attached to the application. Application summary identifies boundary Arleston / hedges/trees and Manor mentions Farm Site footprint tree/hedgerow (Arleston displayed on the management; no South Derbyshire planning Lane) — council application simple total tree-count application listing Arleston page (individual app is given in the (DMOT/2025/0113 and other Solar / shows plan / red committee summary — Arleston entries). BESS line). the AIA / Tree Survey entries on appendix (part of the SDDC application) is the portal place to find the specific numbers. Land at Park Road, Overseal, Swadlincote Erection of a Battery Storage Facility along with 8.41 Hectares of Native Woodland Habitat Enhancement
Motion to be proposed:
That Council notes:
A series of recent planning applications have been submitted to South Derbyshire District Council for large-scale solar farms and battery energy storage systems (BESS).
The vast majority of the land earmarked for these projects is agricultural land.
These proposals, taken together, would represent a significant change to the rural character and landscape of South Derbyshire.
While Derbyshire County Council is not the determining planning authority for these applications, such developments have implications for the wider county, including visual impact, traffic movements, land use change, and community cohesion.
Council believes: The government obsession with Net Zero should never be delivered in a way that disrespects local communities, negatively impacts productive farmland, and over industrialises the countryside.
Agricultural land serves one purpose only; and that is for farmers to produce food and enhance Britain's food security.
Rural Derbyshire should not become home to Chinese manufactured eco deserts.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.