Derbyshire County Council
Cabinet, Thursday 4 December 2025 at 2.00pm

Markham Vale Update on Development Progress

Noted Executive 4 papers

AI summaryDerbyshire County Council Cabinet notes progress at Markham Vale between October 2024 and October 2025, and approves the activity planned to bring the project to completion.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNoted progress and approved planned future activity
Money£0.774m spent, £0.450m remainingCapital outturn 2024-25 and remaining capital expenditure
What happens nextBring project to completionActivity planned over coming years
Who it affectsMarkham Vale site and occupiersUp to 200 acres of new development land, over 600 acres of amenity land

What was decided

Cabinet noted the continuing success and progress at Markham Vale and the economic activity from October 2024 to October 2025. Report 10.1, P12

Cabinet noted and approved the activity planned over the coming years to bring the project to completion. Report 10.1, P12

Why

To give Cabinet members accurate and timely information on the development of Markham Vale and the return on investment. Report 11.1, P14

The project supports continued and sustainable growth of the Derbyshire economy, a Council Plan objective. Report 6.1, P32

What happens next

Individual plot proposals will go through public consultation as part of the planning process. Report 5.1

The budget and programme will be kept under review, with regular reports to Cabinet; a review of fees and charges has begun to ensure full cost recovery. Report 1.5, P19

Remaining capital works will be funded from capital receipts from the sale of remaining development plots, with alternative grant funding also sought. Report 1.2, P19

The money

  • £0.774m Capital outturn expenditure for 2024-25, including slippage from the previous year Report P19
  • £0.450m Estimated remaining capital expenditure on the project Report 1.2, P19
  • £1,550 per acre Current Site Facilities Charge levied on each occupier Report 1.4, P19
  • £0.240m Approximate annual revenue income from the Site Facilities Charge Report 1.4, P19
  • £0.290m Annual Site Facilities Maintenance costs Report 1.4, P19

Options considered

  • Rejected: Do nothing. Council has a Partnership Agreement with HBD to bring forward sites and secure their development Report 6.1, P3
  • Rejected: Slow down the rate of progress and deprioritise site development. Would be counter-productive to job creation and achieving the rate of return on the Council's previous investment Report P4

Implications

  • Financial: When the site is fully occupied, the service is intended to be cost neutral as the Site Facilities Charge income rises. Report 1.4, P19
  • Legal: Geldards LLP continues to advise on the Partnership Agreement between the Council and HBD and on individual development disposals. Report 2.1, P24
  • Equalities: Work with developers and new occupiers supports recruitment of labour from the local economy; walking and cycle routes help households without private vehicles access low cost travel to work. Report 5.1, P30
  • Staffing: No human resources implications directly related to this report. Report 3.1, P26
  • Other: There is close, collaborative working between Economy and Regeneration and Corporate Property services to ensure development meets the Council's objectives. Report 7.1, P34

Who and where

  • Occupiers and buyers of plots at Markham Vale Report 1.3, 1.4, P19
  • The local Derbyshire economy and workforce, including households without private vehicles Report 5.1, 6.1, P30, P32
  • Derbyshire County Council, as partner with HBD in the development Report 6.1, P3

Timeline

  • October 2024 to October 2025: Period covered by the progress and economic activity reported to Cabinet Report 10.1, P12
  • 2024-25: Capital outturn of £0.774m reported for the financial year Report P19
  • Over the coming years: Activity planned to bring the project to completion Report 10.1, P12

Plain English for the jargon

  • HBD: The Council's development partner under the Partnership Agreement for Markham Vale.
  • Markham Vale: A development site in Derbyshire where the Council and HBD are bringing forward employment land.
  • Site Facilities Charge: An index linked annual charge of £1,550 per acre paid by occupiers towards the cost of maintaining shared site areas.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item150/25

Resolved

to 1) Note the continuing success and progress made in bringing forward the development at Marham Vale and the economic activity that has taken place over the period October 2024 to October 2025; and 2) Note and approve the activity planned over the coming years to bring the project to completion.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Cabinet

FOR PUBLICATION

DERBYSHIRE COUNTY COUNCIL

CABINET

4 December 2025

Report of the Executive Director - Place

Markham Vale Update on Development Progress (Cabinet Member for Economic Development and Regeneration)

1. Divisions Affected

1.1Barlborough and Clowne, Bolsover North, Staveley, Staveley North and Whittington, and Sutton.

2. Key Decision

2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are, significant having regard to the budget for the service or function concerned (this is currently defined as £500,000) and is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.

3. Purpose

3.1To inform Cabinet of the continuing success and progress being made in bringing forward development at Markham Vale over the period October 2024 to October 2025 and to set out the activity planned over the coming years to bring the project to completion.

4. Information and Analysis

4.1Markham Vale is the Council’s flagship regeneration project and was set up to create an attractive and viable business park over a site area of 85

CONTROLLED hectares (200 acres). Centred around the former Markham Colliery site, located between Staveley and Bolsover in the north of the County, this major regeneration project was set up in 2006 to create over 4,000 jobs, improve existing/build new roads, bring in around £170m of private sector investment and develop over 3 million ft² of commercial floor space.

4.2In short, Markham Vale was established as a catalyst for regeneration in a deprived former coalfield area of Derbyshire and sought to generate business rates income for re-investment in the Derbyshire economy over the long term. Progress on development at Markham Vale was last considered by Cabinet on 14 November 2024 (Minute No.168/24 refers) and this report serves as the annual update on progress.

4.3Members should note that Derbyshire County Council has a formal development partnership with Henry Boots Development (HBD) to help attract suitable investors and occupiers to the site.

Overview 4.4 To date, the Markham Vale project has brought forward 178 of the 200 acres available for development. Of the 178 acres created, 165 acres are now either fully developed or have buildings under construction. An additional 11.7 acres of land that formed part of the original 200 acres has been developed by others, bringing the total to 190 acres of the proposed 200 acres developed to date.

4.5Progress is demonstrated through a number of indicators, one of which is job creation measured via an annual survey undertaken in March each year. The 2025 survey recorded 2927 full time equivalent jobs had been created on the estate, more than were originally employed at the colliery when it was working at the height of its operations. This is an increase of around 200 jobs on the 2024 figures and more detailed examination shows that whilst some companies have contracted in response to the wider global economics, others have expanded and increased the size of their workforce. Furthermore, anecdotal evidence indicates that over the last five months (since the time of the 2025 survey), there has been further growth in some companies which will no doubt show in next year’s survey.

4.6The significant progress made over the last 12 months in bringing forward individual development sites and construction of new buildings is summarised below:

CONTROLLED Markham Vale East 4.7 Refer to Appendix 2 Drawing 33A1451-1E Development Land Use and Availability WEST & EAST – Note the red shaded areas indicate the plots that currently are either unprepared or undeveloped, red-blue indicate plot sales that are close to completion at the time of compiling this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
/25Appendix 2 2 MB Download
PDF
/25Appendix 3 1.1 MB Download
PDF
/25Appendix 4 1.8 MB Download
PDF
Markham Vale Update on Development ProgressReport 134 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 17 attended
AG
Councillor Alan GravesChairman, present
RR
Councillor Robert ReaneyVice-Chairman, present
DA
Councillor Dawn AbbottCommittee Member, present
JB
Councillor Joss BarnesCommittee Member, present
CH
Councillor Charlotte HillCommittee Member, present
JL
Councillor John LawsonCommittee Member, present
SM
Councillor Simon MabbottCommittee Member, present
SR
Councillor Sam RedfernCommittee Member, present
SR
Councillor Stephen ReedCommittee Member, present
CW
Councillor Carol WoodCommittee Member, present
MK
Mark KenyonOfficer, in attendance
HB
Helen BarringtonOfficer, in attendance

All 17 on the meeting page

On this subject at Derbyshire

Search all
  1. Markham Vale Update on Development ProgressThis decision
  2. Markham Vale Update on Development ProgressNoted
  3. Markham Vale ProgressNoted
  4. Markham Vale ProgressAgreed

More from Derbyshire Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... Noted Open
10 Sep 2026 To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. Approved Open
10 Sep 2026 Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... Noted Open
10 Sep 2026 Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... Approved Open
10 Sep 2026 Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... Approved Open