Derbyshire County Council
Cabinet, Thursday 4 December 2025 at 2.00pm

Regeneration Pipeline Programme: Compulsory Purchase Order to Support South Derbyshire Growth Zone

Noted Executive 5 papers

AI summaryDerbyshire County Council Cabinet approved making a Compulsory Purchase Order and Side Roads Order to assemble land for the South Derbyshire Growth Zone, on a total scheme budget of £77.04m and with £49.6m of government funding at stake.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet approved making both orders, plus delegation agreements
Money£77.04m total scheme budget£49.6m from Levelling Up Fund, £6m minimum from developers
What happens nextPublish CPO likely mid DecemberSix week objection period in local and national press
Who it affectsNot stated

What was decided

Cabinet approved making the Side Roads Order and Compulsory Purchase Order for the South Derbyshire Growth Zone, and entering into Delegation Agreements with Derby City Council and National Highways. Report P27

Officers were authorised to negotiate with objectors, settle compensation under the Compensation Code, pay reasonable professional fees for affected landowners, and appoint counsel for any Public Inquiry. Report P28

The Director of Legal and Democratic Services was authorised to make minor amendments to the CPO schedules and to take all steps needed if compensation is referred to the Upper Tribunal (Lands Chamber).

Why

Negotiated purchase remains the preferred route but extended timescales are pushing up costs and putting timely delivery and the public purse at risk. Report 6.1, 11.1

Making the CPO and SRO in parallel with negotiations is intended to keep the project programme on track and protect access to the £49.6million of Department for Transport funding. Report 6.2, 6.3, 11.1

Officers are satisfied there is a compelling case in the public interest that justifies interference with private rights, and that the orders are a proportionate means of delivering the scheme. Report 2.12, 7.5

What happens next

The CPO and SRO will be publicised and notices served on landowners, tenants and occupiers, with an objection window of about six weeks from around mid December. Report P3, 2.10

The orders will be submitted to the Secretary of State for Transport for confirmation, with a public inquiry possible if objections remain. Report 2.10

Executive Director for Place will continue negotiations with objectors and other affected landholders, with a further Cabinet report and approval needed before submission of the Full Business Case. Report P40

The money

  • £77.04m Total estimated cost of the SDGZ scheme Report 1.3
  • £49.6m Provisional allocation from the Levelling Up Fund Round 1 Report 1.1, 1.3
  • £49.6million DfT funding that would be lost if the scheme does not proceed Report 6.3
  • £4.96m LUF development funding drawn down and spent, at risk of clawback if the project fails Report 1.1, 1.3, P39
  • £6m Minimum local contribution required from developers Report 1.3
  • £2.2m Additional funding secured from partners such as Homes England and EMCCA Report 1.3
  • £19.24m Funding gap on the scheme after current allocations Report 1.3
  • £44.64m Remainder of the LUF grant, only available after Full Business Case acceptance Report P40
  • £1.5m EMCCA funding currently being used for ongoing expenditure Report P39

Options considered

  • Chosen in part: Negotiated settlement for land assembly. Remains the preferred route and will run in parallel, but cannot be pursued indefinitely without harming the public purse and programme. Report 6.1, 5.3
  • Chosen: Prepare and lay the CPO and Side Roads Orders. Needed to guarantee timely land assembly if negotiation does not succeed. Report 6.2
  • Rejected: Do nothing. Would lose access to £49.6million of DfT funding and the wider scheme benefits. Report 6.3

Implications

  • Financial: A funding gap of £19.24m remains on the £77.04m scheme; the Section 151 officer is satisfied sufficient funding options exist to treat the project as fundable, with a Full Business Case gateway to withdraw if needed. Report 1.3, P40
  • Financial: Failure to progress would risk clawback of the £4.96m LUF development funding already spent and the £1.5m EMCCA funding, with no current budget provision to cover either. Report P39, P40
  • Legal: The orders rely on multiple sections of the Highways Act 1980, and the Director of Legal and Democratic Services is satisfied the Council may lawfully exercise compulsory acquisition powers and that the public interest test is met. Report 2.1, 2.12
  • Legal: Article 1 of the First Protocol and Article 8 ECHR rights are engaged, but the scheme's public benefits make interference proportionate; the Council considers no rehousing duty arises under the Land Compensation Act 1973. Report 7.2, 7.5, 7.7
  • Staffing: Extra in-house capacity and external support are being established to manage workload across Economy and Regeneration, Highways, Legal, Property and Finance services. Report 3.1
  • Risk: Objectors who succeed at a Public Inquiry may seek an award of reasonable costs, and a working assumption for these costs is included in the project budget. Report 1.2
  • Equalities: Individual projects within the Programme are subject to equalities impact assessment at appropriate stages. Report 5.1, P59
  • Other: The Programme supports the Council Plan priority to create a green and prosperous Derbyshire. Report 6.1, P61

Who and where

  • Known and unknown landowners, tenants and occupiers of order land within the South Derbyshire Growth Zone Report 5.2, P3, 7.6
  • Derby City Council and National Highways, as delegation and trunk road partners Report 2.8
  • South Derbyshire District Council, developers, Homes England and EMCCA as funding and delivery partners Report 1.3, 5.1
  • Occupier of one house within the scheme who would be displaced, with alternative housing discussed Report 7.7
  • The public, who will be served statutory notices and may make objections Report P3, 2.10

Timeline

  • 17 June 2021: Cabinet approved the Regeneration Kick Start Fund Arrangement (Minute 100/21) Report 8.5
  • 10 March 2022 (restricted): Cabinet considered the Regeneration Programme Pipeline (Minute 80/22) Report 8.4
  • 16 June 2022: Cabinet considered the Regeneration Programme Pipeline (Minute 118/22) Report 8.3
  • 27 July 2023: Cabinet considered the South Derby Growth Zone Regeneration Pipeline Programme (Minute 117/23) Report 8.2
  • 13 March 2025: Cabinet considered the Regeneration Pipeline Programme for the South Derbyshire Growth Zone (Minute 63/25) Report 8.1
  • Likely mid December 2025: CPO to be published in local and national press for a six week period Report P3
  • 4 December 2025: Cabinet approved the making of the CPO and SRO and waived the call-in period on urgency grounds Report P30, 12.1

Plain English for the jargon

  • CPO (Compulsory Purchase Order): A legal order that allows a council to acquire land compulsorily, subject to Secretary of State confirmation.
  • SRO (Side Roads Order): An order under the Highways Act 1980 to stop up, divert or improve side roads affected by a new or improved highway.
  • SDGZ (South Derbyshire Growth Zone): The regeneration and infrastructure scheme covered by this report, including a new A50 junction and enabling infrastructure.
  • LUF (Levelling Up Fund): A UK Government capital fund from which £49.6m has been provisionally allocated to the scheme.
  • DfT: Department for Transport, which is providing the LUF funding and will receive the orders for confirmation.
  • EMCCA: East Midlands Combined County Authority, a funding and delivery partner.
  • Compensation Code: The statutory framework for assessing compensation payable to those whose land is acquired compulsorily.
  • Upper Tribunal (Lands Chamber): The tribunal that determines disputed compensation claims where parties cannot agree.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item151/25

Resolved

RESOLVED to: 1) Note the update, including the additional land to be added to the CPO, and outline of the critical next steps to ensure timely delivery of the South Derbyshire Growth Zone project; 2) Approve to proceed to deliver enabling infrastructure within the South Derby Growth Zone (“the Scheme”); 3) Approve to enter into Delegation Agreements with Derby City Council and National Highways; 4) Approve the making of the Side Roads Order (“the SRO”) followed by the Compulsory Purchase Order (“the CPO”) for the areas of land as shown in Appendices 2 and 3 taking into account the Project’s funding status in making these Orders; 5) Approve the publication and notice of the CPO and SRO being given to landowners and members of the public in accordance with statutory procedures; 6) Approve the submission of the CPO and SRO to the Secretary of State for Transport for confirmation and the taking of such steps as may be required to achieve confirmation; 7) Authorise the Director of Legal and Democratic Services, in consultation with the Executive Director – Place, to take all necessary steps in connection with the conduct and, if appropriate, settlement of such proceedings, in the event that any question of compensation is referred to the Upper Tribunal (Lands Chamber); 8) Authorise the Director of Legal and Democratic Services to appoint suitable counsel to advise and represent the Council at any Public Inquiry held in respect of the SRO and CPO; 9) Authorise the Executive Director – Place to negotiate with objectors to the CPO and SRO and other landholders impacted by the Scheme to resolve objections to the scheme, including without limitation, agreeing accommodation works and the acquisition of land and interests in land to enable the Scheme to proceed and for the Director of Legal and Democratic Services to draw up and execute any such documents as are necessary to withdraw any objections raised; 10) Approve taking ownership of land and interests in land voluntarily or pursuant to the CPO to deliver the Scheme and authorises the Director of Legal and Democratic Services to draw up and execute any such documents as are necessary to the completion such acquisitions; 11) Authorise the Executive Director – Place to negotiate the compensation and payment of the same to affected landowners in accordance with the Compensation Code; 12) Authorise the Executive Director – Place to approve payment of relevant and reasonable professional fees incurred by landowners and others with compensable interests in taking professional advice in connection with the acquisitions of their interests required for the Scheme and related compensation claims and related claims in advancing the development or implementation of the Scheme; and 13) Authorise the Director of Legal and Democratic Services, in consultation with the Executive Director – Place to make minor amends to the schedules to the CPO as may be necessary prior to making the CPO.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Cabinet

FOR PUBLICATION

DERBYSHIRE COUNTY COUNCIL

CABINET

4 December 2025

Report of the Executive Director - Place

Regeneration Pipeline Programme – Amendments to Compulsory Purchase Order to Support South Derbyshire Growth Zone (Cabinet Member for Economic Development and Regeneration)

1. Divisions Affected

1.1Aston and Melbourne and Woodville.

2. Key Decision

2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are, significant, having regard to the budget for the service or function concerned (this is currently defined as £0.500m) and is significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.

3. Purpose

3.1To provide an overview of previous decisions and work being undertaken to ensure timely delivery of the South Derbyshire Growth Zone Scheme.

3.2To address minor amendments to the Scheme and seek Cabinet approval to proceed with the necessary activity to enable delivery of the new infrastructure within the South Derby Growth Zone (“the Scheme”).

CONTROLLED 3.3 To seek Cabinet approval to make and progress a variety of legal orders, enter into formal agreements and to approve delegations required to support timely delivery of the Scheme.

4. Information and Analysis

Background 4.1 The South Derbyshire Growth Zone (SDGZ) project will bring forward major housing and commercial development through creation of enabling infrastructure which includes a new junction on the A50 Trunk Road and a link to existing roads within Infinity Park Derby (“the Scheme”). The land allocation for the proposed jobs and houses is included in the adopted South Derbyshire District Council (SDDC) Local Plan and the Derby City Local Plan, both of which have been through public inquiry and signed off by the Planning Inspectorate.

4.2The road infrastructure Scheme has planning consent. An Outline Business Case (OBC) has been approved by Government, giving provisional access to £49.6 million of grant from the Levelling Up Fund (LUF) to support construction.

4.3Since OBC approval in February 2024, the Scheme has fallen within the remit of a review of major transport programmes by Government; however, it has been confirmed that SDGZ remains within the programme and can proceed to Full Business Case (FBC) submission. Approval of the FBC itself requires that the Scheme can demonstrate it is ready to move to construction, with all necessary land assembled (in this case, via processes that include compulsory purchase) and funding secured.

4.4At its meeting on 13 March 2025, Cabinet gave its approval to an extensive set of recommendations relating to the making of legal orders for the SDGZ Scheme (Minute No. 63/25 refers). These are not repeated here in full because the purpose of this report is to seek new approvals required in order to reflect changes in the boundaries of land required and other changes since Cabinet considered the March 2025 report.

4.5A design and build contract is in place for the project under which, design of the road infrastructure is being finalised; this has allowed critical progress to be made towards both securing the required funding (beyond the £49.6m grant allocation from Government) and preparing for delivery. Work on agreements with public and private-sector partners has also progressed well during the eight months since March.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Statement of Reasons /25Appendix 2a 4 MB Download
PDF
CPO including Schedule (Tables 1 and 2) /25Appendix 2b 826 KB Download
PDF
CPO Plan /25Appendix 2c 3 MB Download
PDF
Side Roads Order /25Appendix 3a 83 KB Download
PDF
Regeneration Pipeline Programme: Compulsory Purchase Order to Support South Derbyshire Growth ZoneReport 1.9 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 17 attended
AG
Councillor Alan GravesChairman, present
RR
Councillor Robert ReaneyVice-Chairman, present
DA
Councillor Dawn AbbottCommittee Member, present
JB
Councillor Joss BarnesCommittee Member, present
CH
Councillor Charlotte HillCommittee Member, present
JL
Councillor John LawsonCommittee Member, present
SM
Councillor Simon MabbottCommittee Member, present
SR
Councillor Sam RedfernCommittee Member, present
SR
Councillor Stephen ReedCommittee Member, present
CW
Councillor Carol WoodCommittee Member, present
MK
Mark KenyonOfficer, in attendance
HB
Helen BarringtonOfficer, in attendance

All 17 on the meeting page

On this subject at Derbyshire

Search all
  1. Regeneration Pipeline Programme: Compulsory Purchase Order to Support South Derbyshire Growth ZoneThis decision
  2. Presentation on the Regeneration PipelineNoted
  3. Regeneration Project PipelineApproved
  4. Regeneration Pipeline Programme – South Derbyshire Growth ZoneNoted
  5. Regeneration Programme PipelineApproved
  6. Regeneration Pipeline Programme - South Derbyshire Growth Zone – Infinity Park Spencer Academy AccessApproved

More from Derbyshire Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... Noted Open
10 Sep 2026 To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. Approved Open
10 Sep 2026 Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... Noted Open
10 Sep 2026 Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... Approved Open