Budget Consultation Results

Decided Executive 1 paper

AI summaryDerbyshire Cabinet notes the views of 2,188 residents and other respondents to its 2026-27 budget consultation, to feed into Full Council budget proposals in February 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCabinet will take account of respondents' views
MoneyNot stated
What happens nextFull Council meeting11 February 2026
Who it affectsDerbyshire residents and businessesAll users of council services

What was decided

Cabinet will take into account the views of consultation respondents when forming its Revenue Budget 2026-27 proposals to Full Council. [D]

Cabinet received the results of the pre-budget survey of 2,188 residents, scrutiny committee feedback, and statutory consultation with business ratepayers. [4.3] [4.4] [4.20] [4.28] Report 4.3, 4.4, 4.20, 4.28

Why

The Council has a legal duty to consult ratepayer representatives on its annual expenditure proposals and to consult local people under the Local Government Act 1999. [2.2] [2.3] Report 2.2, 2.3

Members must have due regard to the Equality Act 2010 and the impact of the budget on people with protected characteristics. [11.3] Report 11.3

By law the Council must set and deliver a balanced budget over the short and medium term. [2.9] Report 2.9

What happens next

Full Council will consider the 2026-27 Revenue Budget and Council Plan on 11 February 2026. [4.3] [4.26] Report 4.3, 4.26

Individual saving proposals will be subject to separate targeted consultation where required, ahead of any implementation decisions in 2026-27. [4.18] [4.19] Report 4.18, 4.19

Prescribed information must be sent to business ratepayer representatives no later than 15 February. [2.2] Report 2.2

Options considered

  • Rejected: Do nothing. Not legally possible because consulting on the Revenue Budget is a statutory requirement. [5.1] Report 5.1

Implications

  • Legal: Statutory duty under section 65 of the Local Government Finance Act 1992 to consult business ratepayers, with prescribed information required by 15 February. [2.2] Report 2.2
  • Legal: Chief Finance Officer must issue a section 114(3) report if expenditure is likely to exceed available resources. [2.10] Report 2.10
  • Equalities: An initial corporate Equality Impact Assessment has been carried out on the proposed budget and identified areas at risk of adverse impact, which will need full Equality Impact Assessment and targeted consultation. [5.4] [5.5] [5.6] Report 5.4, 5.5, 5.6
  • Financial: Outcomes of the consultations should be used to inform service planning and help determine budget priorities. [1.1] Report 1.1
  • Risk: If proposed savings and efficiencies do not progress, alternative savings will need to be found to meet the legal duty to set a balanced budget. [4.27] Report 4.27

Who and where

  • Derbyshire residents, who gave 2,188 responses to the pre-budget survey between 6 June 2025 and 10 August 2025. [4.4] [4.5] Report 4.4, 4.5
  • Business ratepayers, consulted via the East Midlands Chamber of Commerce, CBI East Midlands and the Nottinghamshire and Derbyshire Federation of Small Businesses. [4.28] Report 4.28
  • People sharing protected characteristics under the Equality Act 2010, who may be more affected by reductions to frontline services. [5.6] [11.3] Report 5.6, 11.3
  • Users of services including Children's Services, Adult Social Care and SEND provision, where demand is placing significant financial pressure. [4.22] Report 4.22

Timeline

  • 6 June 2025 to 10 August 2025: Pre-budget engagement survey ran for nine weeks, receiving 2,188 responses. [4.4] Report 4.4
  • 4 December 2025: Cabinet approved the budget timetable and consultation arrangements. [4.1] Report 4.1
  • 11 December 2025: Resources Scrutiny Committee considered the 2026-27 budget timetable and pre-budget engagement. [4.20] Report 4.20
  • 12 January 2026: Cabinet considered specific budget proposals. [4.18] [4.23] Report 4.18, 4.23
  • 14 January 2026: Resources Scrutiny Committee considered the savings proposals and provided feedback to Cabinet. [4.23] [4.26] Report 4.23, 4.26
  • 29 January 2026: Cabinet meeting at which this report was considered. [4.26] Report 4.26
  • 11 February 2026: Full Council meeting to set the 2026-27 Revenue Budget and agree the new Council Plan. [4.3] [4.26] Report 4.3, 4.26
  • By 15 February: Deadline for sending prescribed information to business ratepayer representatives. [2.2] Report 2.2

Plain English for the jargon

  • Revenue Budget: The council's planned day-to-day income and spending for the financial year, covering services rather than long-term assets. [3.1]
  • Pre-budget engagement survey: A 'Knock and Drop' paper survey of a random sample of households, run by an external market research company. [4.5]
  • Equality Impact Assessment (EIA): An assessment of the likely impact of a policy or budget on people with protected characteristics under the Equality Act 2010. [5.4]
  • MTFP (Medium-Term Financial Plan): The council's multi-year financial planning document covering income and savings projections. [4.24]
  • Section 114(3) report: A statutory report the Chief Finance Officer must issue if the council's expenditure is likely to exceed its available resources, triggering restrictions on new spending commitments. [2.10]
  • BME: Black and Minority Ethnic, used as a demographic category in the survey analysis. [4.9]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19/26

Resolved

To take into account the views of the consultation respondents when formulating its proposals to Full Council regarding the Revenue Budget for 2026-27. To take into account the views of the consultation respondents when formulating its proposals to Full Council regarding the Revenue Budget for 2026-27.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Cabinet

Purpose of the report

3.1To enable Cabinet to consider the outcome of the Council’s budget consultation exercises in formulating its budgetary proposals to Full Council regarding the Revenue Budget for 2026-27.

3.2This report should be read alongside the following reports to this meeting: the Reserves Position and Reserves Policy Report, the Revenue Budget Report 2026-27 and the Capital Programme Approvals, Treasury Management and Capital Strategies for 2026-27 Report. 4. Information and Analysis

4.1The production of the Council’s budget is undertaken in accordance with the requirements of the Council’s Constitution. The Constitution requires that a timetable is publicised by Cabinet for making proposals to the full Council in relation to the annual Revenue Budget, along with arrangements for consultation with stakeholders, which should be for a period of not less than six weeks. Cabinet approved the timetable on 4 December 2025.

4.2A key element of the Council’s budget setting process is consultation with stakeholders.

4.3As a result of the Council’s approach, which combines pre-budget engagement via a survey targeting a random sample of households and specific and targeted consultation the Resources Scrutiny Committee and statutory consultation with business ratepayers, the Council has obtained a blend of both quantitative and qualitative information. This has supported the 2026-27 budget setting process, ensuring budget proposals are aligned with the outcomes and strategic objectives in the new Council Plan (2026-27 to 2029-30) that will be agreed alongside the budget at Full Council in February 2026. It will also form the basis for further work, to build a better insight into residents’ views about the Council, their local area and services. The following engagement and consultation activities were performed.

Pre-Budget Engagement

4.4The pre-budget engagement survey ran for nine weeks, starting on 6 June 2025 and completing on 10 August 2025. A total of 2,188 responses were received. Please note however, that not all respondents responded to every question.

4.5The 2025 Survey using a ‘Knock and Drop’ methodology which was outsourced to a market research company to conduct the fieldwork on the Council’s behalf. This methodology sees a paper copy of the questionnaire being delivered to a randomised sample of households across Derbyshire, with the fieldworker then returning at an appointed time to collect the completed questionnaire, or to assist the resident in its completion should assistance be required. This approach targets a random sample of households and provides the opportunity to reach residents who are digitally excluded or require support to engage.

4.6The survey provides results on how much residents support a range of broad options to save money or generate extra revenue (detailed in Appendix Two). Respondents also had the opportunity to make suggestions on other possible saving or revenue generating proposals, in order that they could inform the proposed budget. 4.7 Respondents to the survey were broadly representative of the age bands when compared with the Derbyshire average (2024 Mid-year population estimates).

4.8Based on responses to the survey, there was an element of overrepresentation of residents who identified as having a physical or mental health condition or illness lasting or expected to last 12 months when compared with the results from the 2021 Census (ONS). A total of 27% of respondents identified themselves as having a disability, of which 9% stated that their day-to-day activities were limited a lot.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget Consultation ResultsReport 386 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
AG
Councillor Alan GravesChairman, present
RR
Councillor Robert ReaneyVice-Chairman, present
DA
Councillor Dawn AbbottCommittee Member, present
JB
Councillor Joss BarnesCommittee Member, present
CH
Councillor Charlotte HillCommittee Member, present
JL
Councillor John LawsonCommittee Member, present
SM
Councillor Simon MabbottCommittee Member, present
SR
Councillor Sam RedfernCommittee Member, present
SR
Councillor Stephen ReedCommittee Member, present
CW
Councillor Carol WoodCommittee Member, apologies
NC
Neil CrittendenOfficer, in attendance
MK
Mark KenyonOfficer, in attendance

All 18 on the meeting page

On this subject at Derbyshire

Search all
  1. Budget Consultation ResultsThis decision
  2. Budget Consultation ResultsNoted
  3. Budget Consultation ResultsNoted
  4. Budget Consultation ResultsNoted
  5. Budget Consultation ResultsNoted
  6. Budget Consultation ResultsDecided

More from Derbyshire Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... Noted Open
10 Sep 2026 To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. Approved Open
10 Sep 2026 Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... Noted Open
10 Sep 2026 Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... Approved Open
10 Sep 2026 Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies