AI summaryDerbyshire County Council Cabinet noted more than £41m of the 2025-26 Highways Capital Programme and approved new procurement pipeline entries for highways maintenance and improvement schemes.
Written from the decision and the officer reportPDF Pro
OutcomeNotedThree-part decision: note spend, note further funding, approve pipeline
Money£41.000m noted2025-26 Highways Capital Programme funded via EMCCA
What happens nextProcurement adverts from May 2026First contract start dates 01/04/2026
Who it affectsHighway users and suppliersCouncil as Highway Authority, external providers, road users
What was decided
Cabinet noted that more than £41.000m of the 2025-26 Highways Capital Programme has been delivered, funded by an allocation from the East Midlands Combined County Authority (EMCCA), which now passes down the former Department for Transport highways maintenance and integrated transport grant. Report P9, 1.1
Cabinet noted further funding for specific schemes outside the traditional maintenance allocation, including the Safer Roads Fund, A6 Retaining Walls and Countywide landslips. Report P10
Cabinet approved additions to the Place Department Commercial Pipeline for highways capital and related duties, as set out in Appendix 2. Report P10, 9.2
Why
The recommendation is to provide transparency on actual costs to the end of quarter 3 of the approved 2025-26 Highways Capital Programme. Report 11.1
Publishing intent to procure requires additions to the Place Commercial Pipeline under procurement rules. Report 11.2, 2.4
What happens next
Procurement adverts for the new pipeline entries will run from May 2026, with first contract starts on 01/04/2026 and the latest on 31/12/2026. Report P37, P38, P40, P43
Services will continue to be delivered using a mixed economy model of in-house teams, the Council's Professional Services Partner and other external providers. Report 3.1
The money
£41.000m 2025-26 Highways Capital Programme noted, funded by EMCCA allocation Report P9
£3,000,000 CRSTS Station Road landslip, Bakewell, EMCCA funded Report P43
Options considered
Chosen: Continue delivering the Capital Programme as planned. Delivery is critical, with weather and unforeseen events noted as risks that may delay schemes [6.1] Report 6.1, 10.1
Rejected: Use external resource to supplement in-house Highway Operations. Considered as a contingency for adverse weather impacts on in-house delivery [6.2] Report 6.2
Implications
Legal: Council must maintain the highway in a safe condition under Section 41 of the Highways Act 1980, give advance notice or apply for permits under the Traffic Management Act 2004, and prepare a Local Transport Plan under the Local Transport Act 2008. Report 2.1, 2.2, 2.3
Legal: All procurement must comply with the Council's Standing Orders and Financial Regulations and the Procurement Act 2023 and related regulations. Report 2.4
Financial: EMCCA passported the 2025-26 highways maintenance and integrated transport block allocations to the Council, accepted by Cabinet on 24 July 2025; EMCCA Transport Capital Revenue funding was accepted on 16 October 2025. Report 1.1
Staffing: Services continue using a mixed economy of in-house delivery, the Professional Services Partner and external providers. Report 3.1
Other: Highways Capital Programme delivery is a Council Headline Initiative within the Council Plan 2021-2025. Report P30
Who and where
The Council as Highway Authority, delivering its duties under the Highways Act 1980 Report 2.1, P30
External suppliers and the Council's Professional Services Partner, who may bid for new pipeline contracts Report 3.1, P37, P38, P40
Highway users across Derbyshire, including at specific locations such as A54, A57, A6, Barlow, Beeley, Edale and Bakewell Report P38, P40, P41, P42, P43
Timeline
14/11/2024: Previous Cabinet report on Local Transport Plan Highways Capital Programme 2025-26 (Minute No. 171/24) Report 8.1
24/07/2025: Cabinet accepted EMCCA highways maintenance and integrated transport allocations (Minute No. 98/25) Report 1.1
01/04/2026: Earliest planned contract start dates for new pipeline entries Report P37, P40
01/05/2026: First planned procurement advert dates for Drainage, Surveys, Bridge maintenance contracts Report P37, P40
31/12/2026: Latest planned contract start date, for the Signs (1200) procurement Report P38
Plain English for the jargon
EMCCA: East Midlands Combined County Authority, which now passes highways maintenance funding to Derbyshire
DfT: Department for Transport, previously the direct source of the annual highways grant
CRSTS: City Region Sustainable Transport Settlement, the EMCCA fund used for named landslip schemes
VRS: Vehicle Restraint System, the safety barriers referenced in the fencing procurement
DPIA: Data Privacy Impact Assessment, to be applied where appropriate
SISP: Supplier Information Security Policy, to be applied where appropriate
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item29/26
Resolved
RESOLVED to: 1) Note in excess of £41.000m of the 2025-26 Highways Capital Programme, funded by allocation received from East Midlands Combined County Authority (EMCCA), including the annual direct grant from Central Government for Highways Maintenance and Integrated Transport, previously received direct from the Department for Transport (DfT); 2) Note the further funding received to deal with specific schemes not included within the allocated funding of the more “traditional” maintenance schemes in the Capital Programme, including the Safer Roads Fund, A6 Retaining Walls and Countywide landslips; and 3) Approve additions to the Place Department Commercial Pipeline in pursuit of the Highways Capital and associated highways duties, as set out in Appendix 2.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Update on the Progress of Delivering the 2025-26 Highways Capital Programme (Cabinet Member for Potholes, Highways and Transport)
1. Divisions Affected
1.1County-wide.
2. Key Decision
2.1This is not a Key Decision.
3. Purpose
3.1To report on the progress of delivering in excess of £41.000m of the 2025-26 Highways Capital Programme, funded by allocation received from East Midlands Combined County Authority (EMCCA), including the annual direct grant from Central Government for Highways Maintenance and Integrated Transport, previously received direct from the Department for Transport (DfT).
3.2To note the further funding received to deal with specific schemes not included within the allocated funding of the more “traditional” maintenance schemes in the Capital Programme, including the Safer Roads Fund, A6 Retaining Walls and Countywide landslips.
3.3To approve additions to the Place Department Commercial Pipeline in pursuit of the Highways Capital and associated highways duties.
CONTROLLED 4. Information and Analysis
4.1The 2025-26 Highway Capital Programme was composed of highway maintenance and integrated transport schemes in accordance with the Council’s Asset Management Strategy. The Programme of delivery includes a further number of carriageway maintenance schemes. These were proposed in response to the impacts upon the network from several bouts of severe weather, and feedback from residents and members, and to help mitigate future severe weather impacts upon the network.
4.2Given the uncertainties around project inflation costs and unplanned severe weather events, a proportion of the annual grant was allocated as a contingency sum. The use of this is governed by the Highways Capital Programme Board, chaired by the Highways Director.
4.3The Council has and will continue to deliver the schemes through the mixed economy model of in-house resources, with support from external design and construction providers and suppliers. These will be commissioned through the Council’s professional services partner contract and previously approved local and national frameworks in order to deliver best value to the Council and to its residents.
4.4Schemes managed by the in-house teams include footway resurfacing, minor carriageway resurfacing and repairs, minor structures, reactive capital improvements, drainage investigations, highway improvements, road safety, rights of way, cycle routes and greenways. Schemes identified for delivery from external provider support has been packaged up to deliver greater value for money for the Council.
4.5Approved Capital Funding has increased annually for the Highway Maintenance and Integrated Transport blocks from £23.113m in 2019- 20 to £41.174m in 2025-26 – see Table
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.