AI summaryDerbyshire's Audit Committee notes the Q3 of 2025 to 2026 Strategic Risk Register with 19 strategic risks, including a new council acts unlawfully risk, and notes a 2026 to 2027 work programme to review risk management effectiveness.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee also notes 2026 to 2027 work programme
MoneyMultiple risk impact bandsFrom under £50,000 to over £20 million per risk
What happens next2026 to 2027 work programmeReview of risk management effectiveness
Who it affectsCouncil wide risk managementAffects all Derbyshire County Council services
What was decided
The Committee noted the strategic risk register covering 19 strategic risks, including a new risk on the council acting unlawfully. Report 8.1, P48
The Committee was asked to identify any strategic risk or risk management issue on which it requires further assurance, and to note the proposed 2026 to 2027 work programme to review the effectiveness of risk management. Report 8.1
Why
The Audit Committee is charged with providing assurance to the Council about risk management. Report 9.1
This is a regular report to the Audit Committee on the strategic risk register as required by the Council's Constitution. Report 3.1
What happens next
A new Environmental Sustainability Strategy is in development and is due for Cabinet consideration in the first quarter of 2026 to 2027, replacing the current Climate Change Strategy. Report P68
Work to set up a new Organisational Resilience Group to replace the Business Continuity Group, including recruiting a new Business Continuity Officer, is under way. Report P75, P78
The D2N2 framework for Children in Care placements is due to commence in April 2026, led by Derbyshire County Council. Report P60
The money
£1.38m Q2 revenue forecast outturn, similar to Q1 Report P36
over £6m Council's budget deficit for education support (June 2024) Report P62
in excess of £70m Highways capital programme for 2025 to 2026 with EMCCA funding Report P87
circa £40m Previous recent years' highways investment Report P87
£4.6bn Estimated national financial deficit for SEN Report P62
Options considered
Chosen: Note the strategic risk register. Regular report required by the Council's Constitution Report 3.1, 8.1
Chosen: Identify risks requiring further assurance. Part of the Committee's assurance role Report 8.1, 9.1
Implications
Financial: Multiple strategic risks carry potential financial impacts ranging from under £50,000 to over £20 million if they materialise. Report P126, P35, P39, P44, P47, P50, P59, P72, P74, P77, P82, P86, P92, P96, P99, P104
Legal: A new strategic risk on the Council acting unlawfully has been added, replacing a previous risk on legislation and regulation. Report P48, P49, P50
Risk: The Q3 register shows risks rated Amber and Red for likelihood and impact, with new or reviewed entries on the council acting unlawfully and the cultural change risk. Report P34, P48, P54, P62, P66, P97
Staffing: Ineffectual workforce planning and cultural change risks are rated Amber following organisational change pressures. Report P97, P102
Climate: The extreme weather risk was retitled from climate change risk in September 2025 and remains rated high impact. Report P64, P66, P68
Who and where
All Derbyshire County Council services and residents Report P33, P34
Adult social care service users Report P51, P53
Children in care and looked after children Report P54, P57, P60
Children and young people with special educational needs Report P61, P62
Highways network users Report P83, P87
Council workforce Report P97, P102, P107
Timeline
28 November 2025: Council submitted Uniting Derbyshire LGR proposal to Government Report P45
31 December 2025: Strategic Risk Register Quarter 3 snapshot date Report P33
April 2026: New D2N2 framework for Children in Care placements commences Report P60
First quarter of 2026 to 2027: New Environmental Sustainability Strategy due for Cabinet consideration Report P68
Late first quarter of 2026 to 2027: Construction anticipated to commence on Shipley Country Park bridge repairs Report P93
Plain English for the jargon
LGR: Local Government Reorganisation
EMCCA: East Midlands Combined County Authority
EHCP: Education, Health and Care Plan
APEX: Corporate risk database used by the Council
URN: Unique Risk Number used on the APEX risk system
Section 114 Notice: Notice issued by a Section 151 Officer when expenditure is projected to exceed income under the Local Government Finance Act 1988
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16/26
Resolved
RESOLVED that the Committee: a) Notes the strategic risk register; b) Identifies any strategic risk register or risk management issue on which the Committee requires further assurance; and c) Notes the proposed programme of work in 2026-27 to review the effectiveness of risk management.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
1.1This report provides the Audit Committee with an overview of the Council’s Strategic Risk Register updated to the end of Quarter 3 (31 December 2025).
1.2The Council’s Constitution (Appendix 8A - Financial Regulations) requires that the Audit Committee reviews the Council’s strategic risk register every six months. The purpose is to provide reassurance that the most significant risks to the Council have been property identified, and appropriate management action taken.
2. Information and Analysis
2.1The strategic risk register contains the most significant risks to the Council that are subject to active monitoring and control. The register is kept under continuous review by the Corporate Management Team (CMT) and Director of Finance (Chief Risk Officer), with support provided by the Strategy and Policy team.
2.2A summary of the current register is shown in Table 1 and includes the overall risk severity for each risk at the end of 2025-26 Quarter 3 (Q3). Greater detail about each risk is provided in Appendix 2. Full information about each risk, including narrative updates recording progress with each risk, is recorded on APEX (the corporate performance management information system) and can be shown to the Audit Committee if required.
1 CONTROLLED Table 1 – Summary of current strategic risks (2025-26 Q3)
Risk description Risk owner Target Latest Change (Risks over target are highlighted in score score from last Light Blue) (2025- quarter 26 Q3)
The County Council does not Mark Green Amber No operate within the level of Kenyon change funding available Not achieving the full benefits of Joe Battye Green Green No the devolution deal change Local Government Joe Green Amber New risk reorganisation (LGR) disrupts O’Sullivan (Q2) the delivery of Council services No change Failure to manage contracts Mark Green Amber No across the county council Kenyon change Council acts unlawfully Helen Blue Blue New risk Barrington (Q3) Safeguarding of adults at risk Simon Green Amber No Stevens change Protection of vulnerable children Adele Green Green No Glover change Inability to meet Placement Alison Green Amber No sufficiency Duty Noble change Children with special Joe Wilson Green Amber No educational needs do not change receive the support they need Failure to adapt to extreme, Claire Green Amber No adverse and more variable Brailsford change weather Failure to deliver Cabinet Claire Green Green No decision to reinstate Waste Brailsford change Treatment Centre and best value for residents Failure to deliver critical services Julie Green Amber No in emergency situations Etheridge change Failure to respond to emergency Julian Gould Green Amber No situations change Maintenance of property assets Janet Green Amber No Scholes change Failure to maintain highways Julian Gould Green Amber No assets change Failure to maintain countryside Claire Green Amber No sites and waterways Brailsford change Information governance and John Allen Amber Amber Target data security increased to Amber
2 CONTROLLED Risk description Risk owner Target Latest Change (Risks over target are highlighted in score score from last Light Blue) (2025- quarter 26 Q3)
Cultural change does not keep Julie Green Amber Actual pace with transformation Etheridge increased to Amber Ineffectual workforce planning Julie Green Amber No Etheridge change
2.3Two new risks have been added to the strategic risk register since the last report for 2025-26 Q1 and are shown in Appendix 2:
• Local government reorganisation (LGR) disrupts the delivery of Council services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Place Department Risk ManagementIt was agreed that the Chairman take a request to Cabinet to open the project to scrutiny by the Committee bearing in...
National Fraud Initiative UpdateRESOLVED that the Committee note the outcomes to date of the Council’s participation in the NFI 2024-25 exercise and ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.