Derbyshire County Council
Audit Committee, Tuesday 17 March 2026 at 2.00pm

Performance Monitoring and Budget Monitoring/Forecast Outturn

Approved Finance 6 papers

AI summaryDerbyshire Audit Committee noted the Q3 2025-26 forecast overspend of £0.505m, a £2.828m budget virement from Corporate Services and Transformation to Adult Social Care and Health, and adopted the Flexible Use of Capital Receipts Strategy.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedForecast revenue overspend of £0.505m for 2025-26
Money£0.505m overspendPlus £2.828m virement to Adult Social Care and Health
What happens nextCouncil meeting March 2026Full Council to consider the same report
Who it affectsAdult Social Care and HealthReceives £2.828m virement; DSG deficit £92.607m noted

What was decided

The Committee noted the Q3 2025-26 revenue budget forecast, including a net overspend of £0.505m against the Revenue Budget. Report 1.1, P7

The Committee noted a virement of £2.828m from Corporate Services and Transformation to Adult Social Care and Health. Report P10

The Committee noted the adoption of the Flexible Use of Capital Receipts Strategy and that the report will go to the Council meeting in March 2026. Report P11, P10

Why

The Council is required to outline its forecast revenue outturn to support short and medium-term financial planning and comply with Financial Regulations. Report 5.1, 10.1

The Council must maintain a balanced budget and keep the General Reserve at £35m during 2025-26. Report 10.2, 2.1

Significant inflationary and demand pressures remain in Adult and Children's Social Care, despite investment in the 2025-26 budget. Report 1.2

What happens next

The report will be considered at the Council meeting in March 2026. Report P10

Significant actions will be undertaken across the Council to reduce the revenue overspend and deliver planned savings. Report P9

Workforce implications of the budget savings programme continue to be monitored through the Budget Savings Programme Board. Report 3.1

The money

  • £0.505m Forecast net overspend against Revenue Budget 2025-26 at Q3 Report 1.1
  • £2.828m Virement from Corporate Services and Transformation to Adult Social Care and Health Report P10
  • £35m Target level of General Reserve during 2025-26 Report 10.2
  • £92.607m Forecast cumulative DSG deficit by 31 March 2026 Report 1.3
  • £14bn National DSG deficit forecast by March 2028 Report 1.3
  • 90% Share of DSG deficit accrued to March 2026 covered by High Needs Stability Grant in 2026-27 Report 1.4

Options considered

  • Chosen: Produce the budget monitoring report. Required by Financial Regulations and good financial management Report 5.1
  • Rejected: Not produce a budget monitoring report. Would be contrary to the Council's Financial Regulations Report 5.1

Implications

  • Financial: Forecast net overspend of £0.505m against the 2025-26 Revenue Budget at Q3, with continuing pressures in Adult and Children's Social Care. Report 1.1, 1.2
  • Financial: DSG cumulative deficit forecast at £92.607m by 31 March 2026; government support phases announced on 9 February 2026. Report 1.3, 1.4
  • Legal: A Section 114(3) report would be triggered if the Chief Finance Officer considered expenditure likely to exceed available resources. Report 2.2
  • Staffing: Impact of the budget savings programme on the workforce is being monitored through the Budget Savings Programme Board. Report 3.1, 3.2
  • Risk: A programme management approach to savings delivery has been introduced to manage the risk of non-delivery. Report 7.1

Who and where

  • Adult Social Care and Health Report P10
  • Corporate Services and Transformation Report P10
  • Children's Services and Safeguarding and Education Report 1.2
  • Council-wide services (savings delivery) Report P9

Timeline

  • 31 December 2025: Q3 monitoring date for revenue budget forecast Report P7, 1.1
  • 9 February 2026: Final Local Government Finance Settlement 2026-27 to 2028-29 published Report 1.4
  • March 2026: Council meeting to consider the report Report P10
  • 12 March 2026: Cabinet meeting to consider recommendations Report 9.1
  • 31 March 2026: Forecast end of 2025-26 DSG deficit position Report 1.3
  • 2026-27: Phase 1: High Needs Stability Grant covering 90% of DSG deficit accrued to March 2026 Report 1.4
  • March 2028: Statutory override on DSG deficit due to expire Report 1.3, 1.4
  • 2028-29: SEND spending to be covered by Government DEL budget Report 1.4

Plain English for the jargon

  • DSG: Dedicated Schools Grant: ring-fenced funding for schools, held separately from the general fund.
  • DEL: Departmental Expenditure Limits: central government spending limits for particular programmes.
  • Virement: Transfer of budget between service areas within the same overall budget.
  • Section 114(3): Statutory report under the Local Government Finance Act 1988, triggered if a council's expenditure is likely to exceed its available resources.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17/26

Resolved

RESOLVED that the Committee: a) Notes the update of Council Plan performance, progress with the delivery of savings, and the Revenue Budget position/forecast outturn for 2025-26 as at 31 December 2025 (Quarter 3); b) Notes the position on Reserves; c) Notes the significant actions, set out in the report, which will be undertaken across the Council, and are required to reduce the significant revenue overspend detailed in the report, and to ensure the delivery of planned savings; d) Notes that the report will be considered at the Council meeting in March 2026; e) Notes the virement of £2.828m from Corporate Services and Transformation to Adult Social Care and Health as detailed in paragraph 4.50 of the report; and f) Notes the adoption of the Flexible Use of Capital Receipts Strategy as set out in paragraph 4.49 of the report.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Audit Committee

FOR PUBLICATION

DERBYSHIRE COUNTY COUNCIL

AUDIT COMMITTEE

17 March 2026

Joint Report of the Chief Executive and Director of Finance

Performance Monitoring and Budget Monitoring/Forecast Outturn 2025-26 as at Quarter 3 (31 December 2025) (Cabinet Member for Council Efficiency (DOGE)

1. Divisions Affected

1.1County-wide.

2. Key Decision

2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are, significant, having regard to the budget for the service or function concerned (this is currently defined as £0.500m).

3. Purpose

3.1To provide Members with an update of Council Plan performance and the Revenue Budget/Forecast Outturn for 2025-26, as at 31 December 2025 (Quarter 3). The recommendations in this report are subject to approval by Cabinet on 12 March 2026. 4. Information and Analysis

4.1This report provides information on performance against the Council Plan priorities and financial performance against the 2025-26 Revenue Budget and savings plan.

4.2As at Quarter 3, the Council is forecasting a net overspend of £0.505m (£1.383m at Quarter 2) against the approved Revenue Budget for 2025- 26. Savings delivery is on track, but continuing demand and cost pressures in Children’s and Adults Social Care services are resulting in forecast expenditure being significantly in excess of budget.

4.3It should be noted that the forecast position reported full Council on 11 February 2026 was an overspend of £1.612m. This position has improved to a forecast overspend of £0.505m. This is attributable to the repayment of a loan that was in doubt being repaid which was not known about when reporting the £1.612m overspend in the Council report. This has now been factored into the forecast position giving an improved position. This is detailed in the Corporate Budgets which have changed from an underspend of £27.665m reported to full Council on 11 February to an underspend of £28.775m (a difference of £1.110m which is the rounded difference between £1.612m overspend reported to full Council on 11 February and £0.505m underspend being reported now).

4.4The forecast overspend has reduced by £0.878m since Quarter 2 due to a combination of factors across departments including savings from holding vacancies and additional income for some services and investment interest, and a reduction in the level of forecast overspend on Home to School Transport due to the forecast being updated following finalisation of contractual commitments for the new academic year. The many favourable movements in the forecast are offset by some adverse movements in the forecast, most notably an increase in the forecast overspend of £1.500m in Family Help and Children’s Social Care Services. The significant financial pressures remain across Children’s Services, but the significant pressures in Adult Social Care have been contained and whilst there is still a forecast overspend it is much reduced compared to previous years.

4.5As at Quarter 3, progress against the 25 Strategic Objectives shows that 21 (84%), have good progress, with 3 requiring review and 1 requiring action. Performance Report

4.6The Council Plan sets out the direction of the Council for 2025-2029 with a Base Plan of 25 Strategic Objectives identified. The Quarter 3 performance report is included at Appendix 2.

4.7A summary of the progress of the Strategic Objectives and details of the associated measures are included in the performance report, with brief narrative of any specific issues.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q3 Performance Report 030302026 /26Appendix 2 2.8 MB Download
PDF
Adult Care Finance Summary /26Appendix 3 151 KB Download
PDF
Children's Services Finance Summary /26Appendix 4 198 KB Download
PDF
Business Services /26Appendix 5 191 KB Download
PDF
Council Efficiency (DOGE) Finance Summary /26Appendix 6 169 KB Download
PDF
Performance Monitoring and Budget Monitoring/Forecast OutturnReport 207 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

20 of 21 attended
PP
Councillor Paul ParkinChairman, present
PO
Councillor Paul OxberryVice-Chairman, present
MB
Councillor Matthew BenfieldCommittee Member, present
MC
Councillor Mark CliffCommittee Member, present
NG
Councillor Nigel GourlayCommittee Member, apologies, sent representative
DG
Councillor Damien GreenhalghCommittee Member, apologies, sent representative
RH
Councillor Rachael HatchettCommittee Member, present
JH
Councillor Jamie HodgsonCommittee Member, present
AH
Councillor Adrian HunterCommittee Member, present
AC
Councillor Anne ClarkeCounty Councillor, present as substitute
CH
Councillor Carol HartCounty Councillor, present as substitute
DK
David KingCo-Optee, present

All 21 on the meeting page

On this subject at Derbyshire

Search all
  1. Performance Monitoring and Budget Monitoring/Forecast OutturnThis decision
  2. Performance Monitoring and Budget Monitoring/Forecast Outturn 2026/27 Quarter 1Noted
  3. Performance Monitoring and Budget Monitoring Outturn 2025-26 as at Quarter 4 (31 March 2026)Approved
  4. Performance Monitoring and Budget Monitoring Outturn 2025-26 as at Quarter 4 (31 March 2026)Decided
  5. Performance Monitoring and Budget Monitoring Outturn 2025-26 as at Quarter 4 (31 March 2026)Agreed
  6. Performance Monitoring and Budget Monitoring/Forecast OutturnNoted

More from Derbyshire Audit Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 Place Department Risk ManagementIt was agreed that the Chairman take a request to Cabinet to open the project to scrutiny by the Committee bearing in... Agreed Open
14 Jul 2026 Performance Monitoring and Budget Monitoring Outturn 2025-26 as at Quarter 4 (31 March 2026)RESOLVED that the Committee notes: a) The Council Plan performance and Revenue outturn position for 2025-26; b) The c... Decided Open
14 Jul 2026 Internal Audit Charter UpdateRESOLVED that the Committee approve the Council’s Internal Audit Charter. Approved Open
14 Jul 2026 Counter Fraud Strategy UpdateRESOLVED to approve the Counter Fraud Strategy 2026-27 as appended at Appendix 2 to the report. Approved Open
14 Jul 2026 National Fraud Initiative UpdateRESOLVED that the Committee note the outcomes to date of the Council’s participation in the NFI 2024-25 exercise and ... Noted Open