Cabinet, Thursday 30 July 2026 at 12.00pm

Variation to Delivery Arrangements for South Derbyshire Growth Zone Project

Approved Executive 1 paper

AI summaryCabinet approves activities to raise the South Derbyshire Growth Zone scheme budget from £77.040m to £89.100m, delegate authority for additional at-risk spend, and pursue National Highways Growth and Housing Accelerator funding to close an £11.600m gap.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedNote cost rise to £89.100m, approve FBC submission
Money£89.100m total scheme costUp from £77.040m, £11.600m gap remains
What happens nextSubmit Full Business CaseTo National Highways GHA fund
Who it affectsSDGZ project partners and successor authorityCross-boundary project, LGR vesting 1 April 2028

What was decided

Cabinet noted scheme costs rising from £77.040m to £89.100m based on the current programme and sequencing of early works. Report P20

Cabinet approved submission of a Full Business Case to National Highways for Growth and Housing Accelerator funding to address the funding gap. Report P20

Cabinet delegated authority to the Executive Director, Place, in liaison with the Cabinet Member for Highways, to enter collaboration agreements, bring forward 2028-29 EMCCA funding if needed, approve evidence-led additional spend at risk, and move expenditure from Stage 2 to Stage 1, extending Stage 1 to 31 March 2028.

Why

To enable delivery of the SDGZ scheme in line with Levelling Up Fund criteria, manage risk, minimise project extensions and maximise efficiency. Report 11.1

Not approving additional at-risk spend would make meeting LUF timeframes impossible, risking clawback of £4.960m development funding and potentially some EMCCA funding already spent. Report 6.1

No alternative fund has been identified that could replace the £49.600m LUF allocation, and pausing would undermine the delivery programme and may jeopardise the Public Inquiry. Report 6.2

What happens next

Submit a Full Business Case to National Highways for Growth and Housing Accelerator funding to close the £11.600m funding gap. Report P20, 1.2

Enter collaboration agreements with local authority partners and key stakeholders to share financial risks.

Ensure Levelling Up Funding is defrayed by March 2029, with Stage 1 of the construction contract extended up to 31 March 2028. Report P49

The money

  • £89.100m Total SDGZ scheme cost based on current programme Report 1.2, P20
  • £77.040m Previous scheme cost baseline Report P20
  • £49.600m Levelling Up Fund allocation (LUF Round 1) Report 1.1, P29
  • £4.960m LUF development funding, 10%, already drawn down and at clawback risk Report 1.1, 1.3
  • £11.600m Remaining funding gap after secured contributions Report 1.2, P30
  • £6.000m Minimum local contribution from developers Report 1.2
  • £4,000,000 EMCCA grant, £1.5m secured, £2.5m pending FBC Report P29
  • £697,558 Other local sources including Homes England capacity funding Report P29
  • £18,640,000 S106/Roof Tax from future development, subject to FBC Report P29
  • £4,590,000 Early enabling works delivered in kind by developer Wilson Bowden Report P29

Options considered

  • Rejected: Do nothing. Risk of clawback of £4.960m LUF development funding and possible EMCCA funds already spent; cannot meet LUF timeframes Report 6.1
  • Rejected: Pursue alternative funding arrangements. No fund identified to replace £49.600m LUF allocation; pausing would undermine delivery and may jeopardise Public Inquiry Report 6.2
  • Chosen: Instruct evidence-led additional spend at risk to maintain an achievable delivery programme and protect Levelling Up Fund eligibility. Recommended option to keep scheme on track and meet LUF criteria Report 6.3

Implications

  • Financial: Scheme cost has risen from £77.040m to £89.100m; £4.960m LUF development funding and some EMCCA funding are at risk of clawback if the scheme does not progress; £44.640m LUF grant only available on FBC acceptance by DfT. Report 1.2, 1.3, P32
  • Legal: Procurements and variations comply with Standing Orders, Financial Regulations and statutory procurement rules; collaboration agreements will be reviewed by the Director of Legal and Democratic Services; Public Inquiry implications benefit from internal and external legal review. Report 2.1, 2.2, 2.3
  • Legal: Legal agreements including land and access are likely to need to be novated to a successor authority following Local Government Reorganisation on 1 April 2028, when the project will be at mid-construction stage. Report 3.1, P38
  • Equalities: An Equalities Impact Assessment has been completed and is being updated to reflect finalised designs. Report 6.1, P44
  • Risk: All LUF spend must be completed by March 2029; expenditure in advance of LUF receipt may be at risk of clawback; risks being managed through continuous engagement with DfT and partners. Report 8.1, P49, 1.3
  • Other: Human Rights Act 1998 Convention rights may be engaged in the CPO and Side Roads Order process, as detailed in the 4 December 2025 Cabinet Paper. Report 8.2, P50
  • Staffing: Regeneration portfolio has significant workload implications for Economy and Regeneration, Highways, Legal, Property and Finance; external support secured and additional in-house capacity being established. Report 4.1, P40

Who and where

  • Derby City Council, South Derbyshire District Council and Derbyshire County Council as cross-boundary partners Report 3.1, P38
  • East Midlands Combined County Authority (EMCCA) as a key funding and delivery partner Report 1.2, P29
  • Developer Wilson Bowden Developments providing in-kind early enabling works Report P29
  • National Highways as potential GHA Fund provider Report 1.2, P20
  • Department for Transport as LUF grant administrator Report 1.3, 5.3
  • Homes England and other key stakeholders contributing to the funding package Report 1.2
  • Parish and town councils and residents in the South Derbyshire Growth Zone and Garden Village area Report 5.2
  • Any successor local authority after 1 April 2028 LGR vesting day Report 3.1, P38

Timeline

  • Apr-26: Current funding position reported and FBC work to be progressed Report P28
  • 31 March 2028: Latest end date for Stage 1 of the construction contract if extended
  • 1 April 2028: Local Government Reorganisation vesting day; project at mid-construction stage Report 3.1, P38
  • 2028-29: EMCCA funding allocation that may be brought forward if required
  • March 2029: Deadline by which Levelling Up Funding must be defrayed Report P49

Plain English for the jargon

  • SDGZ: South Derbyshire Growth Zone
  • LUF: Levelling Up Fund, a UK Government capital grant programme
  • EMCCA: East Midlands Combined County Authority, the regional devolved authority
  • GHA Fund: National Highways Growth and Housing Accelerator Fund, a potential new funding source
  • FBC: Full Business Case, the detailed funding submission to Government
  • OBC: Outline Business Case, an earlier stage business case
  • CPO: Compulsory Purchase Order, a legal power to acquire land
  • SRO: Side Roads Order, a legal order affecting road infrastructure
  • LGR: Local Government Reorganisation, the restructuring of councils
  • S106: Section 106 planning obligation requiring developer contributions
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item101/26

Resolved

RESOLVED to: 1) Approve activities to increase the South Derbyshire Growth Zone project budget, bring forward necessary work and expenditure to ensure the continued timely delivery capital project and specifically to: a) Note the increase in Scheme costs from £77.040m to £89.100m based on the programme and sequencing of early works and activity to mitigate associated risks; b) Approve the submission of a Full Business Case for National Highways Growth and Housing Accelerator funding to help to address the identified funding gap; c) Authorise the Executive Director – Place to enter into collaboration agreements or equivalent with local authority partners and other key stakeholders to support partnership working and the appropriate sharing of financial risks; d) Delegate authority to the Executive Director - Place, in liaison with the Cabinet Member - Highways, to bring forward the 2028-29 East Midlands Combined County Authority (EMCCA) funding allocation for the Scheme for earlier use if required, subject to the submission of a Full Business Case and agreement with EMCCA; e) Delegate authority to the Executive Director - Place, in liaison with the Cabinet Member - Highways to approve evidence-led levels of additional spend of allocated funding at risk to ensure the scheme remains deliverable within the required timeframe and ensure Levelling Up Funding can be defrayed by March 2029 to reflect the grant funding requirements; and f) Delegate authority to the Executive Director - Place, in liaison with the Cabinet Member - Highways to move necessary expenditure from Stage 2 of the construction contract into Stage 1 (Stage 1 – Pre-Construction & Stage 2 – Construction), using an appropriate proportion of any available funding in advance of receipt of the LUF grant, and extend the end date of Stage 1 up to 31 March 2028 as required.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Cabinet

FOR PUBLICATION

DERBYSHIRE COUNTY COUNCIL

CABINET

Thursday, 30 July 2026

Report of the Executive Director - Place

Variation to Delivery Arrangements for South Derbyshire Growth Zone Project (Cabinet Member for Highways)

1. Divisions Affected

1.1Aston and Melbourne and Woodville.

2. Key Decision

2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are significant having regard to the budget for the service or function concerned (this is currently defined as £500,000) and it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.

3. Purpose

3.1To seek Cabinet approval for activities to increase the South Derbyshire Growth Zone (SDGZ) project budget, bring forward necessary work and expenditure to ensure the continued timely delivery of the capital project and specifically to:

i. Note the increase in scheme costs from £77.040m to £89.100m based on the current programme and sequencing of early works and activity to mitigate associated risks. ii. Approve the submission of a Full Business Case (FBC) for National Highways Growth and Housing Accelerator funding to help to address the identified funding gap. iii. Authorise the Executive Director – Place to enter into collaboration agreements or equivalent with local authority partners and other key stakeholders to support partnership working and the appropriate sharing of financial risks. iv. Subject to the approval of recommendation iii, delegate authority to the Executive Director - Place, in liaison with the Cabinet Member - Highways, to bring forward the 2028-29 East Midlands Combined County Authority (EMCCA) funding allocation for the scheme for earlier use if required, subject to the submission of an EMCCA Full Business Case and agreement with EMCCA. v. Subject to the approval of recommendation iii, delegate authority to the Executive Director - Place, in liaison with the Cabinet Member - Highways to approve evidence-led levels of additional spend of allocated funding at risk to ensure the scheme remains deliverable within the required timeframe and ensure Levelling Up Funding can be defrayed by March 2029 to reflect the grant funding requirements. vi. Delegate authority to the Executive Director - Place, in liaison with the Cabinet Member - Highways to move necessary expenditure from Stage 2 of the construction contract into Stage 1 (Stage 1 – Pre- Construction & Stage 2 – Construction), using an appropriate proportion of any available funding in advance of receipt of the LUF grant, and extend the end date of Stage 1 up to 31 March 2028 as required.

4. Information and Analysis

4.1The SDGZ project is a key part of the approved Regeneration Pipeline (16 October 2025 Minute No. 122/25). It will bring forward major housing and commercial development through creation of enabling infrastructure which includes a new junction on the A50 Trunk Road and a link to existing roads within Infinity Park Derby (“the Scheme”). The land allocation for the proposed commercial and housing development is included in the adopted South Derbyshire District Council (SDDC) Local Plan and the Derby City Local Plan, both of which have been through examination in public and signed off by the Planning Inspectorate.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Variation to Delivery Arrangements for South Derbyshire Growth Zone ProjectReport 135 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 17 attended
AG
Councillor Alan GravesChairman, present
SR
Councillor Stephen ReedVice-Chairman, present
JB
Councillor Joss BarnesCommittee Member, present
CH
Councillor Charlotte HillCommittee Member, present
JL
Councillor John LawsonCommittee Member, present
SM
Councillor Simon MabbottCommittee Member, present
PM
Councillor Paul MaginnisCommittee Member, present
PP
Councillor Paul ParkinCommittee Member, present
DP
Councillor Dan PriceCommittee Member, apologies
CW
Councillor Carol WoodCommittee Member, present
NC
Neil CrittendenOfficer, in attendance
CB
Claire BrailsfordOfficer, in attendance

All 17 on the meeting page

More from Derbyshire Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... Noted Open
10 Sep 2026 To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. Approved Open
10 Sep 2026 Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... Noted Open
10 Sep 2026 Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... Approved Open
10 Sep 2026 Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies