AI summaryDerbyshire Cabinet noted 2025-26 capital outturn of £114.130m, with £11.168m financed by borrowing and £228.629m reprofiled into future years.
Written from the decision and the officer reportPDF Pro
OutcomeDecided2025-26 capital spend reported to Cabinet
Money£114.130m spent, £11.168m borrowingPlus £228.629m reprofiled into later years
What happens nextBudgets reprofiled into future years£228.629m moved from 2025-26 to later years
Who it affectsCounty-wideAll council directorates and residents
What was decided
Cabinet noted that 2025-26 capital expenditure was £114.130m, financed by grants, capital receipts and reserves, leaving £11.168m to be financed by borrowing. Report P63
Cabinet noted that capital budgets totalling £228.629m will be reprofiled into future years. Report 4.5, P63
Why
The report summarises overall delivery of the capital programme and use of resources to finance it. Report P64
Reporting the outturn supports good financial management and complies with the Council's Financial Regulations and Budget Monitoring Policy. Report P59, 6.1
What happens next
The 2025-26 capital outturn is a draft position which may be amended during preparation of the final Statement of Accounts. Report 4.3
A further report on future options for the New Waste Treatment Facility in Derby will go to Cabinet later in the year. Report P46
The money
£114.130m Total capital expenditure in 2025-26 Report 4.3, P58
£11.168m Balance financed by borrowing in 2025-26 Report 4.42, P58
£228.629m Capital budgets reprofiled into future years Report 4.5
£244.463m Overall underspend against approved capital programme Report 4.4, P16
£16.016m Budgets released to reduce the capital programme balance Report 4.5, 1.2
£1.387m Funded from reserves in 2025-26 Report 4.41, P58
£96.067m Capital grants and contributions used in 2025-26 Report P58
£29.964m Total value of asset disposals achieved in 2025-26 Report 4.40
£94.456m Total value of approved new Capital Starts 2025-26 to 2027-28 Report 4.2
Options considered
Rejected: Not producing a budget monitoring report. Would be contrary to the Council's Financial Regulations and Budget Monitoring Policy Report P59, 6.1
Implications
Financial: Borrowing to fund capital expenditure creates future revenue pressure through interest charges and debt repayment. Report 1.3
Financial: There is no expectation that borrowing costs will exceed the estimates included in the revenue budget projections. Report 1.4
Legal: External legal advice has been sought over leaking flat roofs at Darley Dale and Heanor Specialist Care Centres, with litigation a possible outcome. Report P23, P24
Risk: Some Adult Social Care and Health projects carry risk of additional funding being needed if latent defects cannot be recovered from contractors. Report P23, P24
Staffing: No immediate workforce implications, but future workforce planning implications may arise from underlying transformation and capital projects. Report 4.2
Children's Services (298 schemes with £22.928m spent in 2025-26) Report P27
Place directorate, including highways and transport projects Report P42
Corporate Services and Transformation directorate (175 projects, £6.301m spent in 2025-26) Report P33
Timeline
12 February 2025: Council approved the Capital Strategy for 2025-26 including new starts of £94.456m Report 4.2
11 February 2026: Full Council approved increasing the maximum planned use of Flexible Capital Receipts in 2025-26 to £12.200m Report P49
2025-26: Capital expenditure of £114.130m incurred across the four directorates Report 4.3
August 2026: Smedley's Hydro outline planning application to be determined Report 4.22
Autumn 2026: Little Eaton Branch Line cycle network expected to complete Report P48
End of 2026: Bus Service Improvement Plan programme due to finish; any unspent grant returned to DfT Report P45
2026-27: £170.868m of capital budgets reprofiled into this year Report 4.5
2027-28: £37.914m of capital budgets reprofiled into this year Report 4.5
Plain English for the jargon
Flexible Capital Receipts (FCR): Capital receipts that the Government has allowed to be used to fund revenue costs of efficiency or transformation projects.
EMCCA: East Midlands Combined County Authority, which now passports Department for Transport funding to Derbyshire.
Disabled Facilities Grant (DFG): Grant funding used to install aids and adaptations in residents' own homes, awarded up to £30,000 per application.
S106: Section 106 planning obligations paid by developers to fund specific infrastructure in defined areas.
LGR: Local Government Reorganisation, the planned restructuring of local government in the area.
Levelling Up Fund (LUF): Central government fund from which Derbyshire Dales District Council was awarded money to regenerate Ashbourne town centre.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item95/26
Resolved
RESOLVED to: 1) Note that the capital expenditure for the financial year 2025-26 was £114.130m and that it was financed using grants, capital receipts, and the use of reserves leaving £11.168m to be financed by borrowing and that capital budgets totalling £228.629m will be reprofiled into future years.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Capital Outturn for 2025-26 (Cabinet Member for Finance and Efficiency (DOGE))
1. Divisions Affected
1.1County-wide
2. Key Decision
This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are significant having regard to the budget for the service or function concerned (this is currently defined as £500,000) and it is likely to be significant in terms of its effect on communities living.
3. Purpose
3.1This report provides Members with details of the Capital Programme Outturn position for the financial year 2025-26 and details of the financing of the capital expenditure.
4. Information and Analysis
4.1The Capital Strategy for 2025-26 approved by Council on 12 February 2025 provides a high-level overview of how capital expenditure and capital financing contribute to the provision of local public services. 4.2 It included the proposed new Capital Starts Programme commencing over the three years 2025-26 to 2027-28 which was approved at the meeting. The value of these new projects totalled £94.456m. The financing approved for these new projects was £38.483m of capital grants and £55.973m of additional borrowing. New borrowing of £9.528m will be required in 2025-26, £10.305m in 2026-27 and £36.140m in 2027-28.
4.3Capital expenditure incurred in delivering capital projects during 2025- 26 totalled £114.130m. It should be noted that this is a draft position which may be subject to amendment as the final technical adjustments are made whilst producing the Statement of Accounts. The breakdown of this expenditure by Directorate is shown in the table below. Appendix 2 provides a summary of the expenditure incurred and what will be incurred in future years.
Spend Actual Variance before Spend in Total against Directorate Budget 2025-26 2025-26 Spend Budget £m £m £m £m £m Adult Social Care & Health 93.701 78.330 7.814 86.144 7.557 Childrens Services 219.206 136.274 22.928 159.202 60.004 CST 60.693 26.609 6.301 32.910 27.783 Place 518.007 291.801 77.087 368.888 149.119 Total 891.607 533.014 114.130 647.144 244.463
4.4The budget for the current approved capital programme including the new starts in 2025-26 was £891.607m. The spend on the projects in the programme prior to 2025-26 was £533.014m and the spend in 2025-26 was £114.130m giving a total spend of £647.144m on projects that were being delivered in 2025-26 and an underspend of £244.463m.
4.5The reason for this underspend is that £228.629m of the capital expenditure and budgets have been deferred. • 2026-27 - £170.868m • 2027-28 - £37.914m • 2028-29 - £15.081m • 2029-30 - £4.764m and then budget holders have confirmed that £16.016m of budgets can be released to reduce the capital programme balance.
4.6The largest projects that have been started, part delivered or completed in 2025-26 are detailed below by Directorate. Adult Social Care and Health
Scheme Spend (Under)/ Major Schemes Budget to date Overspend £m £m £m Belper Integrated Specialist Facilities 15.613 14.879 (0.734) Centre – Ada Belfield Bennerley Avenue - Care Home 15.000 13.951 (1.049) Darley Dale Spec Care Cent - Meadow View 10.520 10.439 (0.081) Heanor Specialist Community Care Centre – 9.750 8.968 (0.782) Florence Shipley DFG Major Adaptations 2023-24 6.463 6.001 (0.462) DFG Major Adaptations 2024-25 5.729 5.985 0.256 FCR ASCH – Direct care efficiencies 5.000 4.379 (0.621) Total of 6 largest schemes 68.075 64.602 (3.473)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.