Children's Services Allocation of Section 106 Developer Contributions

Noted Executive 2 papers

AI summaryDerbyshire Cabinet approved allocating £2,586,409.38 of Section 106 developer contributions to school projects, with £811,772.42 to go directly to Derby Diocesan Academy Trust for Bolsover C of E Junior School.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAllocations, Hulland scheme change, and academy trust transfer
Money£2,586,409.38 to allocatePlus £811,772.42 to Derby Diocesan Academy Trust
What happens nextSpend per S106 agreementsTime limits set by each legal agreement apply
Who it affectsSchools across DerbyshireIncluding Hulland Primary and Bolsover C of E Junior

What was decided

Cabinet approved allocating S106 contributions to the projects listed in Appendix 2 of the report. Report P9

Cabinet noted a change of scheme for already approved developer contributions at Hulland Primary School. Report P9

Cabinet approved transferring £811,772.42 directly to Derby Diocesan Academy Trust to self-manage the project at Bolsover C of E Junior School, via a legal agreement between the local authority and the trust. Report P9

Why

Approving the allocations ensures the funding is spent within the time limits of the S106 legal agreements and that there is enough school capacity in the county. Report 11.1

Accepting the change of project for Hulland Primary School creates a robust audit trail for the correct use of approved S106 developer contributions. Report 11.3

Transferring funds directly to the academy trust provides efficiency in invoice payments and quicker access to funds for the self-managed scheme. Report 11.4

What happens next

Funds must be spent in line with the individual Section 106 legal agreements and within the time available. Report 11.1, 2.1

Design and project delivery will be procured either through Concertus Derbyshire Ltd or via the schools, subject to funding approval. Report 8.1

The call-in period is not being waived. Report 12.1

The money

  • £2,586,409.38 Total S106 to allocate across the projects in Appendix 2 Report 1.1
  • £53,543.97 Total S106 to repay to the Children's Services Capital budget Report 1.1
  • £811,772.42 Transfer to Derby Diocesan Academy Trust for the Bolsover C of E Junior School project Report P9

Options considered

  • Chosen: Allocate the Section 106 contributions as set out in Appendix 2. Ensures funding is spent within legal time limits and provides sufficient school capacity Report P9, 11.1
  • Rejected: Do not allocate the contributions. Funding for additional school places linked to housing growth would then have to come from Basic Need Report 6.1

Implications

  • Financial: The contributions are wholly Section 106 developer contributions: £2,586,409.38 to allocate and £53,543.97 to repay to the Children's Services Capital budget. Report 1.1
  • Legal: Projects are agreed in line with the individual Section 106 legal agreements, which have been checked and ratified by Development Section and Planning colleagues. Report 2.1
  • Equalities: No equalities impact identified. Report 5.1
  • Staffing: No human resources implications identified. Report 3.1
  • Other: Design and project delivery will be procured through Concertus Derbyshire Ltd or via the schools, subject to funding approval. Report 8.1
  • Other: The decision does not prejudice the financial sustainability or operational flexibility of any future council, does not create ongoing commitments beyond April 2028, does not trigger Section 24 considerations, and does not constrain future strategic choices of the new council(s). Report P32, P33, P34, P35

Who and where

  • Derby Diocesan Academy Trust, as recipient of £811,772.42 for Bolsover C of E Junior School Report P9
  • Hulland Primary School, subject to a change of scheme for already approved contributions Report P9, 11.3
  • Bolsover C of E Junior School, whose project will be self-managed by the academy trust Report P9
  • Derbyshire County Council Children's Services Capital budget, to receive £53,543.97 reimbursement Report 1.1
  • Schools across the county, benefiting from additional capacity funded by S106 contributions Report 11.1

Timeline

  • 2026-09-10: Cabinet decision made at the meeting

Plain English for the jargon

  • Section 106 (S106): Developer contributions secured through legal planning obligations, used here to fund additional school places linked to housing growth in the county.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item112/26

Resolved

RESOLVED to: 1) Note the receipt/availability of Section 106 funding and approve allocations to the projects outlined in Appendix 2 to the report; 2) Note the change of Scheme for already approved Developer Contributions for Hulland Primary School; 3) Note the receipt of Section 106 Developer Contributions to repay the Children’s Services Capital budget; and 4) Approve transfer of Section 106 Developer Contributions of £811,772.42 directly to Derby Diocesan Academy Trust to self-manage the project at Bolsover C of E Junior School, by way of a Legal Agreement between the Loal Authority and Academy Trust.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Cabinet

FOR PUBLICATION

DERBYSHIRE COUNTY COUNCIL

CABINET

10 September 2026

Report of the Executive Director of Children’s Services

Children’s Services Section 106 Allocations Children’s Services - Education

1. Divisions Affected

1.1County-wide

2. Key Decision

2.1This is a key decision because it is likely to result in the Council incurring expenditure which is significant having regards to the budget for the service or function concerned. This level is set at £500,000. It is also significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.

3. Purpose

3.1To inform Cabinet of the receipt of recent Section 106 developer contributions and to seek approval for their allocation to projects that will improve educational opportunities, learning environments and school capacity for children and young people across Derbyshire, in line with the individual Section 106 agreements. The proposed allocations will ensure that Section 106 Developer Contributions are invested in projects that directly benefit children and young people. The schemes will improve learning environments, support inclusion, provide additional school places where required and create spaces for targeted intervention and support. Collectively, these investments will help children access high-quality education within their local communities, reduce barriers to learning and improve educational experiences and outcomes in Derbyshire's communities.

3.2To inform Cabinet of the receipt of recent Section 106 developer contributions to repay the Children’s Services Capital budget.

3.3To inform Cabinet of a change of project at Hulland Primary School for previously approved Section 106 Developer Contributions.

3.4To seek approval to transfer Section 106 Developer Contributions directly to Derby Diocesan Academy Trust for a self-managed project at Bolsover Church of England Junior School.

4. Information and Analysis

4.1Henry Bradley Infant School – Creation of a learning area. Developer Contributions of £11,399.00 have been received with the legal agreement stating ‘contribution towards the provision and maintenance of facilities’. Therefore, a project has been identified to create a learning area within the school. The proposed project will provide a dedicated learning environment that supports children's engagement, development and intervention activities. The improvements will ensure that children can access high-quality learning spaces that are safe, welcoming and appropriate for their age and stage of development. The roof area above this room is in disrepair and therefore requires some maintenance work to ensure the space can be usable and also requires re-modelling of the space to accommodate children. The project has been costed at £14,601. The school will pay the additional cost from their own school budget.

4.2South Wingfield Primary School – Reconfiguration of Toilet Facilities to create additional classroom The proposed scheme will deliver the reconfiguration of toilet facilities at South Wingfield Primary School and enable the creation of a designated visitor holding area. This will allow the school hall to be used for educational use, providing additional teaching and learning space that will enable more children to access a broad and balanced curriculum in suitable accommodation. The project will improve the learning experience for current pupils and ensure the school can continue to meet the needs of children from the growing local community In addition, a further Section 106 contribution is anticipated from residential development AVA/2021/0948 (Land off Belper Road). A contribution of £118,362.30 towards additional educational facilities at South Wingfield Primary School is expected from this development. Subject to receipt, these funds will be allocated towards the cost of the proposed scheme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for Children's Services Allocation of Section 106 Developer Contributions /26Appendix 2 92 KB Download
PDF
Children's Services Allocation of Section 106 Developer ContributionsReport 127 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
SR
Councillor Stephen ReedChairman, present
AG
Councillor Alan GravesCommittee Member, apologies
JB
Councillor Joss BarnesCommittee Member, present
CH
Councillor Charlotte HillCommittee Member, present
JL
Councillor John LawsonCommittee Member, present
SM
Councillor Simon MabbottCommittee Member, present
PM
Councillor Paul MaginnisCommittee Member, present
PP
Councillor Paul ParkinCommittee Member, present
DP
Councillor Dan PriceCommittee Member, present
CW
Councillor Carol WoodCommittee Member, present
NC
Neil CrittendenOfficer, in attendance
HB
Helen BarringtonOfficer, in attendance

All 18 on the meeting page

On this subject at Derbyshire

Search all
  1. Children's Services Allocation of Section 106 Developer ContributionsThis decision
  2. Allocation of Funding from the Children's Services School Condition Allocation and High Needs Provision Capital AllocationNoted
  3. Allocations from the Children’s Services Capital BudgetApproved
  4. Appointment of the Executive Director of Children's ServicesNoted
  5. Children's Services Section 106 AllocationsNoted
  6. Children’s Services Determined Admissions ArrangementsApproved

More from Derbyshire Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... Noted Open
10 Sep 2026 To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. Approved Open
10 Sep 2026 Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... Noted Open
10 Sep 2026 Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... Approved Open
10 Sep 2026 Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies