Capital Budget Monitoring and Forecast 2026/27 Quarter 1 (30 June 2026)

Noted Executive 3 papers

AI summaryDerbyshire Cabinet noted the Q1 2026/27 capital programme position, with a forecast underspend of £10.430m against a total programme of £866.775m to 2029-30.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCurrent position on 2026-27 capital programme monitoring noted
Money£10.430m forecast underspendAgainst total programme of £866.775m to 2029-30
What happens nextNot stated
Who it affectsCapital programme to 2029-30Includes SEND expansion and County Hall redevelopment

What was decided

Cabinet noted the current position on the monitoring of the Council's Capital Programme for 2026-27. Report 10.1

Why

To ensure the Council complies with best practice in providing regular capital reports on estimates and expenditure to key stakeholders. Report 11.1

What happens next

No call-in waiver is required, and no further decisions are specified in the report. Report 12.1

The money

  • £10.430m Forecast overall underspend on the Capital Programme to 2029-30 Report 1.1
  • £866.775m Total approved Capital Programme over its life to 2029-30 Report 1.1

Options considered

  • Rejected: Do Nothing. The Council's Financial Regulations require preparation and submission of regular reports to Cabinet on projected expenditure and resources compared with approved estimates. Report 6.1

Implications

  • Financial: Forecast underspend means no expectation that borrowing costs will exceed the estimates included in the revenue budget projections. Report 1.3
  • Financial: Schemes are funded from Government grants, other grants, capital receipts, borrowing, reserves and revenue contributions; borrowing carries interest and debt repayment revenue costs. Report 1.2
  • Staffing: Some capital schemes have been reprofiled into future years, extending demand for specialist resources, with workforce planning implications for SEND expansion and Occupational Therapy services linked to Disabled Facilities Grant adaptations, plus the County Hall Redevelopment and digital infrastructure programmes. Report 4.1
  • Other: Some programmes may continue beyond 2028 and will be considered through formal Local Government Reorganisation processes to ensure successful transition to the new Councils. Report 3.1
  • Legal: No direct legal implications arising from this report. Report 2.1

Who and where

  • Council departments delivering the Capital Programme Report 9.1, 1.1
  • Successor councils being established under Local Government Reorganisation for activity continuing beyond 2028 Report 3.1
  • Service users of expanded SEND provision and Disabled Facilities Grant adaptations Report 4.1

Timeline

  • 30 June 2026: Q1 2026/27 capital programme monitoring position reported Report 10.1
  • 2026-27 to 2029-30: Period covered by the £866.775m total Capital Programme Report 1.1
  • Beyond 2028: Some capital programmes may continue and will be handled through formal LGR processes Report 3.1

Plain English for the jargon

  • LGR: Local Government Reorganisation, the process of restructuring local councils
  • SEND: Special Educational Needs and Disabilities
  • Disabled Facilities Grant: Grant funding for home adaptations to help disabled people live independently
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item114/26

Resolved

RESOLVED to: Note the current position on the monitoring of the Council’s Capital Programme for 2026-27.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Cabinet

FOR PUBLICATION

DERBYSHIRE COUNTY COUNCIL

CABINET

Thursday, 10 September 2026

Report of the Director of Finance

Capital Budget Monitoring and Forecast 2026/27 Quarter 1 (30 June 2026) (Cabinet Member for Finance and Efficiency (DOGE))

1. Divisions Affected

County-wide

2. Key Decision

2.1This is report informs Cabinet on the current position and forecast outturn of the Capital budget for 2026-27.

3. Purpose

3.1To inform Cabinet of the latest Capital budget monitoring position as at 30 June 2026.

4. Information and Analysis

4.1The report includes Cabinet approved schemes that have been active during this financial year, including schemes which are to be closed in year. All schemes have a nominated budget holder who is responsible for ensuring the scheme stays within budget, and who provides the projected spend figures. The schemes have been approved over several previous years in addition to the current year. 4.2 The 2026-27 new capital programme approved by Full Council in February 2026 was £77.883m. The proposed new starts programme for 2026-27, along with funding streams, as shown in Table 2, has been evaluated and it was recommended to proceed with the new borrowing of £27.535m for new projects commencing over the specified period. The timeline for the new borrowing is £8.873m in 2026-27, with additional borrowing of £6.786m in 2027-28, £5.936m in 2028-29, £4.216m in 2029-30 and £1.724m post 2030. More details on each individual scheme are set out below in table.

Table 1 – Proposed New capital Starts from 2026-27 onwards

New Projects 2026-27 2027-28 2028-29 2029-30 2030+ Total Department £m £m £m £m £m £m Adult Social 1.724 1.724 1.724 1.724 1.724 8.620 Care & Health Children’s 30.722 2.412 2.412 2.412 0.000 37.958 Services Corporate 3.845 2.650 1.800 0.080 0.000 8.375 Services and Transformation Place 41.592 0.000 0.000 0.000 0.000 41.592 Total 77.883 6.786 5.936 4.216 1.724 96.545

Table 2 - Funding of the approved New Capital Programme

Funding 2026-27 2027-28 2028-29 2029-30 2030+ Total Stream £m £m £m £m £m £m Grants and 69.010 0.000 0.000 0.000 0.000 69.010 Contributions Borrowing 8.873 6.786 5.936 4.216 1.724 27.535 Total 77.883 6.786 5.936 4.216 1.724 96.545

4.3The total approved project budgets for schemes being monitored this year (which includes schemes from prior years which date back to 2012, total £866.775m, there is a forecast variance of £75.919m over the life of these projects. Part of this total includes £65.488m of expenditure that has been profiled to be spent in future years. (see below table 3). Table 3 – Projected Outturn 2026-27

Expenditure

Year end Capital Programme Total Approved Prior Years Variance as at projected Budget Expenditure 31.03.27 spend to date

£m £m £m £m Adult Social Care & Health 82.848 73.568 79.299 (3.549) Childrens Services 241.413 147.913 224.686 (16.727) CST 60.405 23.348 55.299 (5.106) Place 482.109 323.364 431.572 (50.537) Grand Total 866.775 568.193 790.856 (75.919)

4.4Adult Social Care & Health - projected variance of £0.373m

4.5Adult Care has a capital budget allocation of £1.724m for 2026-2027 financial year. There has been a change in the process with DFG Adaptations for 2026-2027 onwards which means that only a proportion of the Occupational Therapists time will be charged to the Capital budget.

4.6The DFG Adaptations project for 2026-27 has not commenced yet, but the full budget allocation has been included in the Adults Social Care and Health line in the table above and is showing a Nil variance for Quarter 1.

4.7At Quarter 1, the Directorate is forecasting an overall underspend of £3.549m, primarily due to completion of the projects that reported favourable variances. The table below sets out the projects with the greatest spend below/over the approved budget that will be started, part delivered or completed in 2026-27, together with the variance. Table 4 - Adult Social Care and Health

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Projected Capital Spend by Department /26Appendix 2 124 KB Download
PDF
Top Ten Capital Projects by Budget value /26Appendix 3 92 KB Download
PDF
Capital Budget Monitoring and Forecast 2026/27 Quarter 1 (30 June 2026)Report 184 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
SR
Councillor Stephen ReedChairman, present
AG
Councillor Alan GravesCommittee Member, apologies
JB
Councillor Joss BarnesCommittee Member, present
CH
Councillor Charlotte HillCommittee Member, present
JL
Councillor John LawsonCommittee Member, present
SM
Councillor Simon MabbottCommittee Member, present
PM
Councillor Paul MaginnisCommittee Member, present
PP
Councillor Paul ParkinCommittee Member, present
DP
Councillor Dan PriceCommittee Member, present
CW
Councillor Carol WoodCommittee Member, present
NC
Neil CrittendenOfficer, in attendance
HB
Helen BarringtonOfficer, in attendance

All 18 on the meeting page

On this subject at Derbyshire

Search all
  1. Capital Budget Monitoring and Forecast 2026/27 Quarter 1 (30 June 2026)This decision
  2. Allocations from the Children’s Services Capital BudgetApproved
  3. Capital budget monitoring and forecast as at Quarter 3Noted
  4. Capital budget monitoring and forecast as at Quarter 1 2025-26Noted
  5. Children's Services SEND Capital Budget (High Needs Provision Capital) AllocationsApproved
  6. Children's Services SEND Capital Budget (High Needs Provision Capital) AllocationsApproved

More from Derbyshire Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... Noted Open
10 Sep 2026 To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. Approved Open
10 Sep 2026 Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... Noted Open
10 Sep 2026 Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... Approved Open