Resolved
RESOLVED to: Note the current position on the monitoring of the Council’s Capital Programme for 2026-27.
AI summaryDerbyshire Cabinet noted the Q1 2026/27 capital programme position, with a forecast underspend of £10.430m against a total programme of £866.775m to 2029-30.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED to: Note the current position on the monitoring of the Council’s Capital Programme for 2026-27.
FOR PUBLICATION
DERBYSHIRE COUNTY COUNCIL
CABINET
Thursday, 10 September 2026
Report of the Director of Finance
Capital Budget Monitoring and Forecast 2026/27 Quarter 1 (30 June 2026) (Cabinet Member for Finance and Efficiency (DOGE))
1. Divisions Affected
County-wide
2. Key Decision
2.1This is report informs Cabinet on the current position and forecast outturn of the Capital budget for 2026-27.
3. Purpose
3.1To inform Cabinet of the latest Capital budget monitoring position as at 30 June 2026.
4. Information and Analysis
4.1The report includes Cabinet approved schemes that have been active during this financial year, including schemes which are to be closed in year. All schemes have a nominated budget holder who is responsible for ensuring the scheme stays within budget, and who provides the projected spend figures. The schemes have been approved over several previous years in addition to the current year. 4.2 The 2026-27 new capital programme approved by Full Council in February 2026 was £77.883m. The proposed new starts programme for 2026-27, along with funding streams, as shown in Table 2, has been evaluated and it was recommended to proceed with the new borrowing of £27.535m for new projects commencing over the specified period. The timeline for the new borrowing is £8.873m in 2026-27, with additional borrowing of £6.786m in 2027-28, £5.936m in 2028-29, £4.216m in 2029-30 and £1.724m post 2030. More details on each individual scheme are set out below in table.
Table 1 – Proposed New capital Starts from 2026-27 onwards
New Projects 2026-27 2027-28 2028-29 2029-30 2030+ Total Department £m £m £m £m £m £m Adult Social 1.724 1.724 1.724 1.724 1.724 8.620 Care & Health Children’s 30.722 2.412 2.412 2.412 0.000 37.958 Services Corporate 3.845 2.650 1.800 0.080 0.000 8.375 Services and Transformation Place 41.592 0.000 0.000 0.000 0.000 41.592 Total 77.883 6.786 5.936 4.216 1.724 96.545
Table 2 - Funding of the approved New Capital Programme
Funding 2026-27 2027-28 2028-29 2029-30 2030+ Total Stream £m £m £m £m £m £m Grants and 69.010 0.000 0.000 0.000 0.000 69.010 Contributions Borrowing 8.873 6.786 5.936 4.216 1.724 27.535 Total 77.883 6.786 5.936 4.216 1.724 96.545
4.3The total approved project budgets for schemes being monitored this year (which includes schemes from prior years which date back to 2012, total £866.775m, there is a forecast variance of £75.919m over the life of these projects. Part of this total includes £65.488m of expenditure that has been profiled to be spent in future years. (see below table 3). Table 3 – Projected Outturn 2026-27
Expenditure
Year end Capital Programme Total Approved Prior Years Variance as at projected Budget Expenditure 31.03.27 spend to date
£m £m £m £m Adult Social Care & Health 82.848 73.568 79.299 (3.549) Childrens Services 241.413 147.913 224.686 (16.727) CST 60.405 23.348 55.299 (5.106) Place 482.109 323.364 431.572 (50.537) Grand Total 866.775 568.193 790.856 (75.919)
4.4Adult Social Care & Health - projected variance of £0.373m
4.5Adult Care has a capital budget allocation of £1.724m for 2026-2027 financial year. There has been a change in the process with DFG Adaptations for 2026-2027 onwards which means that only a proportion of the Occupational Therapists time will be charged to the Capital budget.
4.6The DFG Adaptations project for 2026-27 has not commenced yet, but the full budget allocation has been included in the Adults Social Care and Health line in the table above and is showing a Nil variance for Quarter 1.
4.7At Quarter 1, the Directorate is forecasting an overall underspend of £3.549m, primarily due to completion of the projects that reported favourable variances. The table below sets out the projects with the greatest spend below/over the approved budget that will be started, part delivered or completed in 2026-27, together with the variance. Table 4 - Adult Social Care and Health
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Projected Capital Spend by Department /26Appendix 2 | 124 KB | Download |
PDF |
Top Ten Capital Projects by Budget value /26Appendix 3 | 92 KB | Download |
PDF |
Capital Budget Monitoring and Forecast 2026/27 Quarter 1 (30 June 2026)Report | 184 KB | DownloadRead as text |
Follow Cabinet at Derbyshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... | Noted | Open |
| 10 Sep 2026 | To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. | Approved | Open |
| 10 Sep 2026 | Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... | Noted | Open |
| 10 Sep 2026 | Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... | Approved | Open |
| 10 Sep 2026 | Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.