Resolved
That the Head of Planning be delegated to formulate the response to Hampshire Council in consultation of the Chairman of the Strategic Planning Committee.
Strategic and Technical Planning Committee decided this item on Thursday 27 May 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Head of Planning be delegated to formulate the response to Hampshire Council in consultation of the Chairman of the Strategic Planning Committee.
That Dorset Council responds to Hampshire County Council regarding the planning application consultation on the proposed development of a quarry at Purple Haze, stating that:
a) Dorset Council is not satisfied that the Environmental Impact Assessment carried out on the proposed development provides robust evidence that all impacts, including impacts on Dorset's environment and interests, have been identified and will be appropriately mitigated. Therefore, Dorset Council objects to the detail of the proposed development and asks Hampshire County Council to ensure that further robust assessment is undertaken, and consulted on, to ensure impacts are properly understood and appropriately mitigated. Reason for Recommendation:
a) Following assessment of application documents, Dorset Council is not satisfied that the Environmental Statement submitted with the planning application provides robust evidence that all relevant impacts have been identified, and can be satisfactorily mitigated. Dorset Council considers that the applicants need to carry out further assessment to properly identify and mitigate impacts.
This report considers Hampshire County Council's consultation on the proposed development of a quarry at the Purple Haze site south of Verwood. It identifies the key issues associated with the proposed development, including those potentially affecting Dorset, and sets out further information received from specialist consultees within Dorset Council. It recommends that Dorset Council objects on the grounds that the Environmental Impact Assessment has not adequately addressed all likely impacts, and does not set out satisfactory mitigation based on robust evidence.
As a response to a planning consultation in a neighbouring authority, there are no direct financial implications associated with this decision. However, should there be unmitigated or poorly mitigated impacts from development of the site which affects Dorset, this could have financial implications for Dorset Council.
3. Well-being and Health Implications
No well-being or health matters directly related to this report and its recommendations have been identified.
No climate change related implications directly related to this report and its recommendations have been identified.
5. Other Implications
Dorset Council seeks to ensure, through its response to this consultation, that should Hampshire County Council ultimately give permission for this site, then development will occur in a sustainable manner.1
1Footnote: Issues relating to financial, legal, environmental, economic and equalities implications have been considered and any information relevant to the decision is included within the report. 6. Risk Assessment
Having considered the risks associated with this decision, the level of risk has been identified as:
Current Risk: Low
Residual Risk: Low
7. Equalities Impact Assessment
An Equalities Impact Assessment is not a material consideration in considering this application.
Appendix 1 - Comments from Dorset Council consultees
Dorset Council's Scoping Response to Hampshire County Council 10 July 2020.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Dorset Council response to consultation on proposed quarry development at Purple Haze, Verwood.Report | 2.7 MB | DownloadRead as text |
Follow Strategic and Technical Planning Committee at Dorset and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Oct 2025 | P/VOC/2023/02551 - Lyme Regis Golf Club, Timber Hill, Lyme Regis, Dorset, DT7 3HQTo grant for ... view the full minutes text for item 27. | Decided | Open |
| 23 Sep 2025 | Declarations of InterestIt was agreed that she would take part in the debate and vote on the item. | Agreed | Open |
| 30 Jun 2025 | P/FUL/2025/00591 - Rainbarrow Farm, Monkey Jump Roundabout to Junction Below Alington Place, Martinstown, DT2 9JFTo grant for the reasons set out in Sections 16 and 17 of the officer’s report. | Decided | Open |
| 14 Mar 2025 | Application to divert part of Footpath 11, Compton Abbas at Compton Abbas AirfieldSubmit the Public Path Order for the diversion of part of footpath 11, Compton Abbas, to the Secretary of State and t... | Decided | Open |
| 27 Jan 2025 | P/VOC/2024/07289 - Land south-east of Sunrise Business Park and north of the A350 Blandford Bypass, Blandford Forum.Grant the application as per the officer recommendation. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.