Resolved

Decision (a) That the Lyme Regis Environmental Improvement Scheme Phase 5 Outline Business Case as set out at Appendix A, be agreed. (b) That Cabinet authorises the submission of the Outline Business Case to the Environment Agency’s National Project Assurance Board. (c) That Cabinet authorises the use of allocated S106 derived funds as contributions toward the scheme construction costs. (d) That Cabinet authorises officers to progress the scheme to its completion, including construction, pending necessary expenditure approvals. Reason for the decision As owner and coast protection authority, the Council is responsible for maintenance and repair of the Grade 1 Listed Cobb harbour structures to an appropriate standard. This project will provide coastal protection to 37 properties as well as maintain the recreational and heritage value of Lyme Bay, and continued operation of Lyme Regis Harbour.
Word for word from the decision Dorset published for this meeting. Source: moderngov.dorsetcouncil.gov.uk

Follow this further

Built from Dorset's papers

What the report saysPro

Report to Cabinet

Recommendation

1. Agrees the Lyme Regis Environmental Improvement Scheme Phase 5 Outline Business Case (Appendix A). 2. Authorises for the submission of the Outline Business Case to the Environment Agency’s National Project Assurance Board. 3. Authorises the use of allocated S106 derived funds as contributions toward the scheme construction costs. 4. Authorises officers to progress the scheme to its completion, including construction, pending necessary expenditure approvals. Reason for Recommendation:

As owner and coast protection authority, the Council is responsible for maintenance and repair of the Grade 1 Listed Cobb harbour structures to an appropriate standard.

This project will provide coastal protection to 37 properties as well as maintain the recreational and heritage value of Lyme Bay, and continued operation of Lyme Regis Harbour. The Cobb is an important tourist attraction and its loss would have an adverse effect on the local economy.

Preparatory work has revealed significant signs of scour which is destabilising the structure. Surfacing is generally poor; restricting access for the less-abled, the landing quay is not fit-for-purpose and utility services to the Cobb Buildings and landing quay are in poor condition.

To extend the operational life of The Cobb, repair and reinforcement of the structure need to be undertaken.

1. Report

1.1Strategic Priority

a) The scheme fits within the priorities of the Dorset Council plan 2020 to 2024. The proposals within the outline business case fit within the Unique Environment priorities of the council, where it has committed to:

 deliver services in ways that protect our natural, historic and cultural environments;

 lead and support communities to respond to climate and ecological change;

 protect Dorset’s natural biodiversity; and

 support the Environment Agency on flood protection projects.

b) The scheme is Phase 5 of the Lyme Regis Environmental Improvement Strategy Plan (2002). See Section 9 (Background papers).

1.2Background a) The Cobb enables a working harbour, is an important historic structure, a major tourist attraction and a fundamental element of the town’s coast defences. The harbour structures, with their rock extensions, form a bay which protects the town frontage from storm waves and keeps the sand and shingle beaches stable.

b) Progressive movement of the structure is ongoing, and this is apparent in cracking and slab separation in both the low and high walkways as the main wall gradually spreads. Cracks and damage to wall facing are also apparent and raise concern over loss of core material and collapse during storm conditions. Scour at the base of walls is evident and widespread, having a destabilising effect upon the structure.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Lyme Regis Environmental Improvement Scheme Phase 5 Outline Business CaseReport 371 KB DownloadRead as text
PDF
Lyme Regis Environmental Improvments: appendixAppendix 1.6 MB Download

At this meeting

Whole meeting

Who was there

8 of 34 attended
SF
Councillor Spencer FlowerChairman, apologies
PW
Councillor Peter WharfVice-Chair, present
GC
Councillor Graham Carr-JonesCommittee Member, apologies
RB
Councillor Ray BryanCommittee Member, present
TF
Councillor Tony FerrariCommittee Member, present
LM
Councillor Laura MillerCommittee Member, present
AP
Councillor Andrew ParryCommittee Member, present
GS
Councillor Gary SuttleCommittee Member, present
JH
Councillor Jill HaynesCommittee Member, present
DW
Councillor David WalshCommittee Member, present
MP
Matt ProsserOfficer, in attendance
AD
Aidan DunnOfficer, in attendance

All 34 on the meeting page

On this subject at Dorset

Search all
  1. Lyme Regis Environmental Improvement Scheme Phase 5 Outline Business CaseThis decision
  2. P/FUL/2025/07525 - Holmbush Car Park, Pound Street, Lyme Regis, DT7 3HXDecided
  3. P/LBC/2025/05844 - Lyme Regis Harbour, The Cobb, Lyme Regis, DT7 3JJDecided
  4. P/VOC/2023/02551 - Lyme Regis Golf Club, Timber Hill, Lyme Regis, Dorset, DT7 3HQDecided
  5. P/VOC/2025/01606 - Uplyme Road Business Park, Uplyme Road, Lyme RegisApproved
  6. P/FUL/2025/01232 The Lower Site Uplyme Road, Lyme RegisApproved

More from Dorset Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 July 2026 (period 4) financial management report 26/27Decision (a) That the Senior Leadership Team’s forecast as of July 2026 including progress in addressing demand for s... Noted Open
8 Sep 2026 Additional Procurement Pipeline Report - over £500k (2026 - 27) and Modern Slavery Transparency Statement 2025 - 2026Decision (a) Cabinet considered the contents of the report (of 8 September 2026) in respect of proposed additional mo... Approved Open
8 Sep 2026 Exempt BusinessDecision That the press and the public be excluded for the following item(s) in view of the likely disclosure of exem... Decided Open
28 Jul 2026 Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ... Noted Open
28 Jul 2026 Dorset Local Visitor Economy Partnership Destination Management Plan(a) That the Dorset Local Visitor Economy Partnership Destination Management Plan (DLVEPDM) be adopted and (b) That a... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies