Strategic and Technical Planning Committee decided this item on Monday 4 March 2024. Below is the council's own wording, with the papers it was decided on.
That: a. The application to divert Footpath 1, Lyme Regis was accepted and an order made. b. The Order included provisions to modify the definitive map and statement to record the changes made as a consequence of the diversion. c. If the Order was unopposed and was considered to meet the legal tests for Order confirmation, it be confirmed by the Council. d. If the Order was opposed but the objections were not relevant to the legal tests, it be submitted to the Secretary of State for confirmation without further reference to Committee.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
Report to Strategic and Technical Planning Committee
Background
1.1In 2015, Dorset County Council received an application from West Dorset District Council to divert Footpath 1, Lyme Regis as shown on Drawing P175/23/2 attached as Appendix 1. Following changes to local government structure1 in Dorset in 2019, the application was transferred to Dorset Council.
1.2Under the Coast Protection Act 1949, Dorset Council is currently delivering Phase IV of the Lyme Regis Coast Stabilisation Works - Environmental Improvements. The works, which began in April 2013, will secure the coastline between Church Cliff and East Cliff for the next 60 years, saving up to 480 homes from damage or loss of access.
1.3As part of the engineering works the Council has constructed a new path connecting Charmouth Road car park to the eastern beach. The proposed diversion will reroute Footpath 1 onto this new path.
1.4The current definitive route of Footpath 1, Lyme Regis runs from its junction with Church Street (A3052) at point A, east and north east along East Cliff, continuing generally north east along coastal slopes then generally north north west through the allotment gardens to join Spittles Lane at point B. The current route of Footpath 1 between points A and B is approximately 504 metres long.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategic and Technical Planning Committee at Dorset and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.