AI summaryDorset Council Cabinet agrees in principle to join a nine-authority New Forest mitigation strategy, allowing it to resume granting planning permissions for new homes in parts of eastern Dorset.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedJoins nine authority partnership to mitigate recreation impact
Money£400 per dwellingFor eastern Dorset area, inflation-linked via RPI
What happens nextInterim payments to NFNPAUntil new partnership scheme is established
Who it affectsResidential developers in eastern DorsetWithin 13.8km or 15km of New Forest Heaths
What was decided
Cabinet agreed in principle to the New Forest Strategic Access Management and Monitoring Strategy 2025, with any minor changes delegated to the Cabinet Member for Planning and Emergency Planning. Report 2.1
The strategy will be applied within the 13.8km buffer and a 15km buffer for larger sites, allowing the council to resume granting residential planning permissions. Report 2.1, 1.4
As an interim step, secured developer funding will be transferred to the New Forest National Park Authority to extend its existing mitigation scheme while the partnership scheme is set up. Report 1.7, 4.7
Why
Natural England has advised that the council should not authorise new residential development within the 13.8km and 15km impact zones without appropriate mitigation, and the council is currently refusing such applications. Report 1.4, 3.1
Joining the partnership avoids the need for Dorset Council to develop its own separate mitigation scheme, which would delay consents because the council has no jurisdiction over the New Forest. Report 3.3, 5.1
The strategy also reduces the risk of the council failing to meet housing needs in the affected parts of Dorset. Report 10.1, 5.1
What happens next
A legal agreement between the council and the New Forest National Park Authority will be finalised to allow transfer of developer contributions to the current and any future mitigation scheme. Report 1.7, 4.7, 6.2
The Cabinet Member for Planning and Emergency Planning will agree guidance on proportional contributions for other overnight accommodation, in consultation with the Corporate Director for Planning. Report 2.1
Unused interim funds will be transferred into the new partnership scheme once it is established. Report 1.7, 3.2
The money
£400 per dwelling Developer contribution for eastern Dorset area within the New Forest impact zone Report 1.6
around £22 million Total cost of the mitigation package across all measures for the strategy Report 4.5
around 45,000 dwellings in total Anticipated housing growth covered by the strategy across the zone of influence to 2036 Report 4.4
Options considered
Chosen: Join the nine-authority New Forest SAMM partnership strategy. Provides a coordinated long-term mitigation approach and avoids the need for a standalone Dorset scheme that would delay planning consents. Report 2.1, 3.3, 5.1
Rejected: Do not adopt the strategy and continue refusing consents within the impact zone. Would leave the council unable to meet the housing needs of the affected parts of Dorset and would create reputational risk. Report 5.1, 10.1
Implications
Legal: As competent authority under the Habitats Regulations, the council must consider impacts on protected habitats and cannot grant consents for development causing harm unless imperative reasons of overriding public interest apply, which is not the case here. Report 6.1
Financial: Mitigation is funded through developer contributions secured via the planning process, so there is no direct cost to the council. Report 7.1
Risk: The current risk is identified as High and the residual risk as Low once the strategy is in place. Report P48, P49
Environment and climate: Strategy projects are expected to have a major positive impact on the New Forest Heaths protected sites and support the Nature Positive Dorset 2030 target. Report 8.1, P36, P37
Other: Failure to put a mechanism in place would create reputational issues for Dorset and prevent the council meeting housing needs in the affected area. Report 10.1
Who and where
Residents and applicants seeking planning permission for new homes in the 13.8km impact zone and 15km zone for larger sites in eastern Dorset Report 1.4, 1.5
Residential developers building within the defined buffers, who will pay a £400 per dwelling contribution (index-linked) Report 1.6, 7.1
The New Forest National Park Authority and the other eight local authorities in the partnership Report 1.5, 4.1
Visitors and wildlife of the New Forest Heaths protected sites Report 1.1, 8.1
Timeline
To 2036: Strategy covers anticipated housing growth of around 45,000 dwellings across the zone of influence, with review based on latest evidence and monitoring Report 4.4
80 years (perpetuity) for some costs; 5 or 10 year review periods for others: Duration over which mitigation project costs are committed under the strategy Report 4.5
Annually: Developer contributions will be uplifted using the Retail Prices Index Report 1.6
Plain English for the jargon
SAMM Strategy: Strategic Access Management and Monitoring Strategy, a framework for managing and monitoring visitor access impacts on protected heathland sites.
SAC/SPA/Ramsar: Special Area of Conservation, Special Protection Area, and Ramsar wetland site: international nature conservation designations protecting the New Forest Heaths.
NFNPA: New Forest National Park Authority, the body leading the partnership mitigation scheme.
Zone of influence: The 13.8km buffer (and 15km for larger sites) around the New Forest Heaths within which new housing is judged to add to recreational pressure on the protected sites.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
(i) That the New Forest Strategic Access Management and Monitoring Strategy 2025, be agreed in principle. Any minor changes to the final version of the Strategy, be delegated to the Cabinet Member for Planning and Emergency Planning in consultation with the Corporate Director for Planning. (ii) That the Strategy be applied within the 13.8km buffer and 15km buffer for larger sites to allow planning permissions to be granted (iii) That as an interim arrangement, secured funding be transferred to the New Forest National Park Authority (NFNPA) to extend their existing mitigation scheme whilst the new partnership scheme was established (iv) That, authority be delegated to the Cabinet Member for Planning and Emergency Planning in consultation with the Corporate Director for Planning for the agreement of guidance on proportional contributions for other over-night accommodation. Reason for the decision The New Forest Strategic Access Management and Monitoring Strategy provided a long-term solution, and temporary arrangement, expanding the existing mitigation scheme to cover affected parts of Dorset. This would enable permissions to be granted in the interim. Joining the partnership scheme avoided the need for Dorset Council to develop its own complex alternative, which would delay planning consents.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
1.1Evidence commissioned by the New Forest National Park Authority (NFNPA) identifies a likely significant increase in impact of recreational activities on the New Forest Heaths (the New Forest SAC/SPA/Ramsar) arising from the increase in population that results from new development. The New Forest Heaths are protected under the Habitat Regulations, and the impact is similar to that on the Dorset Heaths.
1.2The evidence looks at the impacts of visitors to the New Forest Heaths. It considers the distance people travel to the heaths and how this influences their activities and visits. It draws together some project types that could mitigate the impact of the increase in visitor activity.
1.3As a much larger area and with the higher profile that the National Park brings, the New Forest Heaths attract visitors from much further afield than Dorset Heaths. The evidence concludes that 75% of visitors travel from areas up to V2/25
13.8km from the New Forest Heaths boundary. This includes eastern parts of Dorset. The evidence also indicates that larger developments of around 200 dwellings and over within 15km of the New Forest Heaths boundary are likely to have a significant effect on the New Forest Heaths and a second buffer is applicable to these sites (see Appendix 2).
1.4Reflecting the evidence of recreational impact on the New Forest Heaths sites, Natural England have issued advice that the Council should not be authorising any additional residential development within the 13.8km impact zone or 15km for larger sites, without first securing appropriate mitigation. At present, Dorset Council is not granting planning permission for any residential development within either impact zone.
1.5The NFNPA have led a group of 9 local authorities in developing a New Forest Strategic Access Management and Monitoring Strategy 2025 (Appendix 1) that will enable the Council to resume granting planning permission in the identified impact zones. The strategy requires a contribution from new residential development towards the provision of mitigation in a similar way to the existing Dorset Heathlands Planning Framework.
1.6The contributions vary between the affected local authorities based on frequency of visit and likely activity. For the eastern Dorset area within the impact zone, a contribution of £400 per dwelling is required. Contributions to the mitigation scheme will be subject to inflation annually using the Retail Prices Index. A proportionate approach will be applied to other over-night accommodation in a similar fashion to that for the Dorset Heaths and this will be developed on proportional contributions basis.
1.7An agreement to enable the transfer of funds has been drawn up between the Council and NFNPA (yet to be signed) to enable mitigation to be secured. As a temporary measure the Council will pay into the NFNPA’s existing mitigation scheme whilst a new scheme and governance structures are established. Unused monies from this interim scheme will be transferred into the new scheme once established. The agreement for transfer of funds has been written such that it can also be applied to the new partnership scheme once established.
2. Recommendation(s)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.