AI summaryDorset Cabinet agrees to seek a single leisure operator and extends three centre contracts by two years while the procurement strategy is developed.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedSingle leisure operator to be procured, Max Associates recommissioned
Money£5,000 for strategyFunded from leisure revenue budget, exact savings unknown
What happens nextStrategy back to Cabinet September 2026Place and Resource Overview to review wider report February 2026
Who it affectsThree leisure centresFerndown, Blandford, Dorchester Sports Centre contracts extended
What was decided
Cabinet approved commissioning Max Associates to develop a procurement strategy for a single leisure contract operator across the council's leisure centres. Report 2.1
Cabinet agreed the procurement strategy would return to Cabinet in September 2026 for final approval. Report 2.2
The Service Manager for Leisure, Arts and Cultural Services was authorised to extend the contracts for Ferndown, Blandford and Dorchester Sports Centre by two years from 1 April 2026, with an option for a further year. Report 2.3, 4.15
Why
An appraisal of management options found that a single contracted operator was best able to meet council priorities, financial objectives and service delivery needs, and could enable a significant annual revenue reduction. Report 3.1, 4.5, 4.7
A procurement strategy was needed to set the timetable, market tendering approach, service specifications, contract length and risk position before going to market. Report 3.2, 4.10
Extending existing contracts keeps the three centres open and operational during the strategy development, procurement and mobilisation to a new operator. Report 3.3, 4.15
What happens next
Place and Resource Overview to consider the wider leisure facilities report in February 2026, followed by Cabinet in March 2026, before Max Associates is recommissioned. Report 4.13
The Service Manager for Leisure, Arts and Cultural Services to agree the contract extensions under PCR15 Reg 72 modification provisions. Report 1.4, 2.3
Cabinet to consider and give final approval to the Dorset Leisure Centres Procurement Strategy in September 2026. Report 2.2
The money
£5,000 Cost of commissioning Max Associates for the procurement strategy report, funded from the leisure revenue budget Report 4.13
Options considered
Chosen: Procure a single external leisure operator. Lowest cost and best able to meet priorities, financial objectives and service delivery; identified as most suitable in the evaluation matrix Report 3.1, 4.7, 4.8, 7.1
Rejected: Continue in-house management of leisure centres. Would require a higher level of financial subsidy and less likely to deliver key service and performance outcomes Report P31
Rejected: Set up a Local Authority Trading Company (LATC). Would require a higher level of financial subsidy and less likely to deliver key service and performance outcomes Report P31
Rejected: Continue with mixed management models (in-house, contract, concession). Single operator option offers the most significant annual revenue reduction and best delivery of outcomes Report 1.1, 4.4, 4.7
Implications
Legal: Contract extensions to be made under PCR15 Reg 72 modification provisions; reviewed and approved by Procurement and Legal Services, with the extension not exceeding 50% of original contract value. Report 1.4, 6.2
Financial: A single contracted operator could enable a significant annual revenue reduction, though actual savings will not be known until a procurement exercise has taken place, given the volatility of the leisure market. Report 1.3, 4.7, 7.1
Staffing: Staff at in-scope centres currently managed in-house would transfer to a new operator under TUPE regulations. Report 4.11
Equalities: An equality impact assessment identifies the need to monitor future legislative changes on the use of changing rooms; current service provision will remain the same during the extension.
Climate: No known environmental impact at this stage; the future procurement strategy will consider facility investment, potentially including retrofit for energy efficiency and renewable energy generation. Report 8.1
Risk: Risk level assessed as Low (current and residual); the additional one-year extension option gives time contingency if a contractor is not appointed before the two-year extension expires. Report 4.15
Who and where
Users of Ferndown Leisure Centre, Blandford Leisure Centre and Dorchester Sports Centre, whose contracts are being extended by two years Report 1.1, 2.3, 4.4
Staff at in-scope leisure centres currently managed in-house, who would transfer to a new operator under TUPE Report 4.11
Bridport Leisure Centre and Redlands Community Sports Hub, which are proposed to be excluded from the procurement process Report 4.12
Current leisure contractors at the three extended centres, whose contracts will be modified under PCR15 Reg 72 Report 1.4, 2.3, 4.15
Max Associates, to be recommissioned to develop the procurement strategy Report 2.1, 4.13
Timeline
February 2026: Wider leisure facilities report due to be considered by Place and Resource Overview Report 4.13
March 2026: Wider leisure facilities report due to be considered by Cabinet Report 4.13
31 March 2026: Current leisure contracts at Ferndown, Blandford and Dorchester Sports Centre expire Report 1.1, 4.4
1 April 2026: Two-year contract extensions for the three centres begin, with option of a further one year Report 2.3
September 2026: Dorset Leisure Centres Procurement Strategy to be brought back to Cabinet for final approval Report 1.4, 2.2
18 months (estimated): Length of the procurement exercise for a single external leisure contractor Report 4.10
Plain English for the jargon
PCR15 Reg 72: A regulation under the Public Contracts Regulations 2015 that allows modification of existing contracts under defined conditions, including where a change cannot be made for economic or technical reasons without significant inconvenience or substantial duplication of cost.
TUPE: Transfer of Undertakings (Protection of Employment) regulations, which protect employees when a business or service transfers to a new employer.
LATC: Local Authority Trading Company, a company set up by a local authority to deliver services, typically operating commercially.
Concession: An arrangement where a leisure centre is leased to an operator who manages it, distinct from a contract where the council directly commissions services.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14
Resolved
(i) That the procurement of a single leisure contract operator, be agreed and Max Associates be recommissioned to develop the Dorset Leisure Centres Procurement Strategy required to achieve this. (ii) That the Dorset Leisure Centres Procurement Strategy be brought back to Cabinet for consideration and final approval of the strategy’s recommendations in September 2026. (iii) That the Service Manager for Leisure, Arts and Cultural Services be authorised to agree contract extensions for Ferndown Leisure Centre, Blandford Leisure Centre and Dorchester Sports Centre for a further 2 years from the 1 April 2026 with an option for a further 1 year. Reason for the decision Procuring a single leisure contractor was best able to meet Council priorities and financial goals. A procurement strategy would set the timetable, tendering approach, service specifications, and risk management. Extending current contracts ensured centres stayed open during this process and transition.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
1.1The Council currently has a mixture of management models across its leisure centres which include in-house management, centres managed by third party operators under a contract and centres leased to operators to manage as a concession. The leisure contracts at Ferndown Leisure Centre, Blandford Leisure Centre and Dorchester Sports Centre expire on 31 March 2026.
1.2The Council has recently carried out a detailed appraisal of the options for future leisure management as part of the wider leisure facilities strategy work. The purpose being to decide which of the following standard delivery models is best able to meet the Council priorities, financial objectives and service delivery requirements.
1.3The option to go out to the open market to procure a contract with a single operating partner could enable a significant annual revenue reduction. A contracted leisure service with a single operator is also considered most likely to deliver key service and performance outcomes.
1.4The Council needs two years to develop and agree a procurement strategy and undertake the complex procurement exercise necessary to procure and transition to a single operator. To maintain service provision during this period; existing leisure contracts need to be extended by applying PCR15 Reg 72 – Modification of Contracts. These modifications have been approved by Procurement and V2/25
Legal Services. It is advised that the option of an additional year is agreed to provide time contingency. The detailed procurement strategy referred to will be brought back to Cabinet in September 2026 for consideration and approval.
2.0Recommendation(s)
That Cabinet
2.1Agrees to the procurement of a single leisure contract operator and to re- commission Max Associates to develop the Dorset Leisure Centres Procurement Strategy required to achieve this.
2.2Agrees that the Dorset Leisure Centres Procurement Strategy be brought back to Cabinet for consideration and final approval of the strategy’s recommendations in September 2026.
2.3Agrees that the Service Manager for Leisure, Arts and Cultural Services is authorised to agree contract extensions for Ferndown Leisure Centre, Blandford Leisure Centre and Dorchester Sports Centre for a further 2 years from the 1 April 2026 with an option for a further 1 year.
3.0Reason for the recommendation(s)
3.1Following a review of leisure centre management options, procuring a leisure contractor to operate all the Council’s in-scope leisure centres is best able to meet the Council priorities, financial objectives and service delivery requirements.
3.2Following a procurement strategy will enable the Council to consider and set out the timetable, the best way to approach and manage the market tendering process, the specification of services for each of the centres in scope, the length and type of contract, the Council’s position on risk and to control and manage the delivery of any investment programmes.
3.3The extension of the existing leisure contracts will enable the leisure centres to remain open and operational during the development of the procurement strategy, the procurement process and the mobilisation to a single leisure operator. 4.0 Management Options
4.1The Council fully recognises the significant role which its leisure offer plays in preventative health, both in terms of physical and mental wellbeing, and the potentially positive impact this has in reducing the call on many of its statutory services. V2/25
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.