AI summaryDorset Council Cabinet approved the £4,987k Swanage Beach coastal protection outline business case, unlocking £4,007k of external grant to recharge the beach, build a new rock groyne and reinforce the seawall.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedOutline business case and budget approved
Money£4,987k total project costIncludes £4,007k external grant
What happens nextSubmit to Environment Agency by 31 March 2026Deadline before funding rule change
Who it affectsSwanage seafront, residents and visitorsOver 110 properties at flood and erosion risk
What was decided
Cabinet approved the Swanage Beach Coastal Protection Scheme outline business case and the related budget allocation in the Capital programme. Report 2.1
Cabinet authorised submission of the outline business case to the Environment Agency's National Project Assurance Service and ongoing draw-down of all external Flood Defence Grant-in-Aid and Local Levy funding.
Authority to procure and award the works and professional services was delegated to the Executive Director for Place, in consultation with the Section 151 Officer and the Cabinet Member for Place Services.
Why
Scheme delivery is needed to provide resilience against coastal erosion and flooding at Swanage, where the existing seawall could fail as early as 2029 and over 110 properties are at risk. Report 3.1, P13, P14
National flood funding rules change on 1 April 2026, so the outline business case must be submitted before 31 March 2026 to avoid extensive rework, delays and extra cost.
The £4.987m project requires Cabinet approval before it can be considered for the external Environment Agency funding. Report P37
What happens next
Submit the outline business case to the Environment Agency's National Project Assurance Service before 31 March 2026.
Continue alignment with the Bournemouth, Christchurch and Poole Council Poole Bay Strategy to share mobilisation, materials and cost efficiencies. Report P4, P24
Procure and award the construction works and professional services through delegated authority, with construction delivery currently estimated for 2028. Report P5
£330k Local Levy funding (external, pre-construction work in 2026/27) Report 7.1, P35
£190k Additional Dorset Council capital match funding Report 7.1, P34
£460k Existing Dorset Council capital spend to date Report P3, P34
£650k Total Dorset Council capital commitment after additional £190k Report 7.1, P34
Options considered
Chosen: Beach recharge with a new rock groyne control structure and additional seawall protection. Restores standard of protection, best value for money, lower build and carbon risk, and enables cost efficiencies through alignment with the BCP recharge programme. Report 4.4, P19, P20, P21, P22, P23, P24
Rejected: Ten alternative options (longlist of 11 in total) including more intrusive engineered defences. Lower scoring on flood and erosion risk reduction, value for money, environmental impact, buildability, affordability or consenting risk under the multicriteria analysis. Report 5.1, P27
Implications
Financial: Dorset Council must add £190k of capital to reach a £650k total commitment, alongside £4,007k of external grant and £330k of Local Levy. Report 7.1, P34, P35, P36
Legal: Dorset Council is the coast protection authority under the Coastal Protection Act 1949 and Flood and Water Management Act 2010; regulatory licences will be needed from the Environment Agency, Natural England and the Marine Management Organisation. Report 6.1, 6.2
Equalities: No adverse effects have been identified in the equality impact assessment. Report 12.1, 13.2
Climate: The design reuses existing beach material to cut waste, vehicle movements and new materials, and the project will increase climate resilience. Report 8.1
Risk: Current risk for the decision is rated High, reducing to a residual Low risk after mitigation. Report 11.1, P47, P48
Who and where
Over 110 properties on Swanage seafront at risk of coastal flooding and erosion Report P13
Owners and users of critical public infrastructure and local amenities in Swanage Report P2, P13
Swanage's local economy and tourism visitors Report P2
Bournemouth, Christchurch and Poole Council through shared Poole Bay Strategy delivery Report P4, P24
Timeline
31 March 2026: Deadline to submit outline business case to the Environment Agency before funding rule change
1 April 2026: New national flood funding rules take effect
2026/27: Pre-construction work to be completed using £330k Local Levy funding Report 7.1
2028: Current estimate for project delivery Report P5
as early as 2029: Existing Swanage seawall projected to fail without intervention Report P14
Plain English for the jargon
FCERM: Flood and Coastal Erosion Risk Management
OBC: Outline Business Case
BCP: Bournemouth, Christchurch and Poole Council
Local Levy: Funding raised through regional flood and coastal committees to support local flood defence work
Flood Defence Grant-in-Aid: Central government funding administered by the Environment Agency for flood and coastal erosion risk management schemes
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item48
Resolved
(a) That the outline business case be approved. (b) That the budget allocation within the Capital programme and as detailed in Table 1.0 section 7 of the report,be approved. (c) That the Outline Business Case be submitted to the Environment Agency’s National Project Assurance Service. (d) That the draw-down of all external Flood Defence Grant-In-Aid and Local Levy funding be authorised, on an ongoing basis throughout the duration of the project. (e) That authority be delegated to the Executive Director for Place in consultation with the Section 151 Officer and Cabinet Member for Place Services, to procure and award the works and associated professional services. Reason for the decision · Scheme delivery was required to provide resilience against coastal erosion and flooding. · National flood funding rules change on 1 April 2026, the outline business case must be submitted before 31 March 2026 to avoid the risk of extensive rework, delays, and additional costs under the new requirements. · The outline business case setting out the £4.987m project required cabinet approval before it could be considered for external funding.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
Swanage seafront requires additional protection to provide resilience to flooding and coastal erosion. The primary purpose of this paper is to seek cabinet’s approval to bid for £4 million of external funding to replenish beach levels, install a new rock groyne control structure and provide additional protection to the seawall. The recommended approach includes sustaining the effectiveness of the beach and existing groyne structures, which together play a vital role in reducing the risks of coastal flooding and erosion.
Swanage Beach is a key coastal asset that provides flood and erosion protection to the town, supports critical infrastructure and key amenities, and attracts thousands of visitors each year. Protecting the seafront supports economic growth and enhances resilience.
The total project cost is estimated at £4.657m, with a current spend of £460k. This paper seeks additional investment of £190k from Dorset Council in match funding to secure external funding of £4.007m.
The project is in continued alignment with the wider Bournemouth, Christchurch and Poole Council (BCP) Poole Bay Strategy project, which is fundamental to the delivery approach of the scheme. Ongoing collaboration enables shared efficiencies V2/25
and cost savings; without this alignment, these benefits would be lost, and the project would no longer be economically viable to deliver. Project delivery is currently estimated in 2028. 2. Recommendation(s)
2.1Approve the Swanage Beach Coastal Protection Scheme outline business case. 2.2 Approve budget allocation within the Capital programme as detailed in Table 1.0 section 7. 2.3 Authorise the submission of the Outline Business Case to the Environment Agency’s National Project Assurance Service. 2.4 Authorise the draw-down of all external Flood Defence Grant-In-Aid and Local Levy funding, ongoing throughout the project. 2.5 That the decision to procure and award the works and associated professional services be delegated to the Executive Director of Place in consultation with the Section 151 Officer and the Cabinet Member for Place Services.
3. Reason for the recommendation(s)
3.1Scheme delivery is required to provide resilience against coastal erosion and flooding. 3.2 National flood funding rules change on 1 April 2026, the outline business case must be submitted before 31 March 2026 to avoid the risk of extensive rework, delays, and additional costs under the new requirements. 3.3 The outline business case setting out the £4.987m project requires cabinet approval before it can be considered for external funding.
4. The report
4.1Strategic priority
(a) Protection of Swanage seafront is supported by the Dorset Council Plan, “Our seaside communities are particularly exposed to rising sea levels which can lead to coastal erosion, flooding, and damage to infrastructure.’ In preparing for the challenges of climate change, ‘we are committed to helping our communities, ecosystems, and economies adapt to the unavoidable impacts of climate change’.
(b) This scheme aligns with central government’s approach which sets out the long-term ambition to create a nation more resilient to future flood and coastal erosion risk. V2/25
Background
Swanage’s existing coastal defences are deteriorating. Beach levels have been steadily falling, leaving over 110 properties, critical public infrastructure and the local economy at increasing risk from coastal flooding and erosion.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.