Bridport (West Bay) Harbour Walls Stabilisation & Property Works
AgreedExecutive1 paper
AI summaryDorset Cabinet delegates authority to the Executive Director for Place to procure and award contracts for repairs to West Bay harbour walls A and B, and to investigate options for affected council buildings.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedFor harbour wall repair contracts, plus investigation of building options
MoneyNot stated in open papersCost estimates are in exempt Appendix 1
What happens nextInvestigate building optionsSubsequent Cabinet report if substantial works needed
Who it affectsWest Bay harbour users, businesses, visitorsHarbour Master office, toilets, kiosks also affected
What was decided
Cabinet delegated authority to the Executive Director for Place to agree the specification, procurement and award of contracts for harbour wall repairs, after consulting the Cabinet Member for Place Services and the Section 151 Officer. Report 2.1
Cabinet agreed that options for the council-owned buildings affected by ground movement should be investigated once wall works are complete. Report 2.2
A subsequent report will be presented to Cabinet if further substantial works to the buildings are required. Report 3.2
Why
Wall B has already failed and has no remaining design life, and Wall A needs urgent maintenance, creating safety risks, restricted harbour access, and flood exposure for nearby properties. Report P2, P15, P16
Delegation allows essential stabilisation and repair to proceed in a coordinated and efficient way, maintaining safety, functionality and resilience of harbour infrastructure, while providing financial oversight. Report 3.2
The full range of options for the related buildings cannot be suitably assessed until the wall works are finished. Report 3.2
What happens next
The Executive Director for Place will agree the repair specification, run procurement and award contracts, in consultation with the relevant Cabinet Member and the Section 151 Officer. Report 2.1
A series of options for the Harbour Master's office and public toilet block will be investigated once stabilisation works are complete, aligned to the Strategic Asset Management Plan. Report P4, P5, P19
A further Cabinet report will follow if substantial building works are needed, with a full Equality Impact Assessment carried out for the options considered. Report 3.2, 12.1
Options considered
Chosen: Proposed repair scheme restoring Wall B structural strength, raising its height for flood defence, and stabilising Wall A through ground stabilisation and void filling. Demonstrates the optimal engineering solution for construction delivery Report P3, P17, P21
Rejected: 12 other remediation options considered on cost, time, historic, environmental, noise and lifespan grounds. Not the optimal engineering solutions for construction delivery Report P21
To be investigated: Range of options for the Harbour Master's office and public toilet block. Cannot be fully assessed until wall works are complete Report P4, P19, 3.2
Implications
Financial: Financial implications are set out in the exempt Appendix 1, which was not provided in open papers. Report 7.1, P28
Legal: Works will follow relevant licensing, environmental and marine regulatory frameworks; building options will need to consider planning, building regulations, accessibility and marine licensing. Report 6.1, 6.2, P24, P26
Climate: Climate Wheel assessment rates the proposal as having major positive impacts on local resilience and adaptation, including against projected sea level rise; energy and waste impacts rated mixed. Report 7.3, P33, P34
Risk: Current risk identified as Medium, residual risk as Low, after mitigation. Report 11.1, P43, P44
Equalities: A full Equality Impact Assessment will be completed for the building options. Report 12.1
Other: Schemes will be designed to retain existing material, minimise new materials, vehicle movements and noise, and retain historic features where possible. Report P17, P30
Who and where
Visitors to West Bay harbour and the Jurassic Coast Report P1, P16
Local harbour businesses and kiosks trading next to the walls Report P14, P15, P16
Vessel owners with moored boats behind Wall B Report P16, P37
Harbour Master and users of the public toilets and Harbour Master's office Report P4, P14, P19
Council as harbour authority and owner of the affected buildings Report P2, P14
Timeline
Since 2023: Spend has enabled the first phase of ground stabilisation work to be completed. Report P3
3 March 2026: Cabinet considered the report and delegated authority for the next phase of works.
By the 2030s (central scenario): Met Office projects local sea level rise of 18cm relative to a 1981 to 2000 baseline. Report P34
By the 2050s (central scenario): Met Office projects local sea level rise of 29cm relative to a 1981 to 2000 baseline. Report P34
By the 2080s (central scenario): Met Office projects local sea level rise of 48cm relative to a 1981 to 2000 baseline. Report P34
By the 2080s (high impact scenario): Met Office projects local sea level rise of up to 91cm relative to a 1981 to 2000 baseline. Report P34
Plain English for the jargon
Section 151 Officer: The council's statutory chief finance officer, responsible for financial administration.
Wall A and Wall B: The western and southern walls of West Bay inner harbour, maintained by Dorset Council.
SAC: Special Area of Conservation, a European protected site designation.
EA and MMO: Environment Agency and Marine Management Organisation, the regulators with oversight of the works.
Strategic Asset Management Plan: The council's plan for managing its property and land assets.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item49
Resolved
(a) That authority be delegated to the Executive Director for Place to agree a specification for required works, procurement and award of contracts for harbour wall repairs up to a maximum spend (as shown in Appendix 1 of the report to Cabinet of 3 March 2026), following consultation with the Cabinet Member for Place Services and the Section 151 Officer. (b) That a series of options for the council owned buildings affected by the localised ground movement be investigated. Reason for the decision Delegating authority for the overall harbour wall repair works would ensure that essential stabilisation and repair activity could proceed in a coordinated and efficient manner, maintaining the safety, functionality and resilience of key harbour infrastructure. Consultation with the Cabinet Member for Place Services and the Section 151 Officer would provide appropriate oversight and financial assurance. The full options for the related buildings could not be suitably assessed until the works to the walls had been completed. The options for the buildings would need to be investigated, with a subsequent report presented to Cabinet if further substantial works were required.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
The idyllic harbour at Westbay is a key visitor attraction and central point for the local community. Located on Dorset’s famous Jurassic Coast, the area strengthens the local economy with a predominant maritime and visitor focus.
Dorset Council is responsible for maintaining the harbour walls at West Bay. Walls A and B, which form the western and southern sides of the inner harbour, have deteriorated significantly, and Wall B has already failed. This has created safety risks, affected access and contributed to movement in nearby Council buildings.
Project costs are shown in exempt Appendix 1. The spend since 2023 has enabled the first phase of ground stabilisation work to be completed. This paper seeks approval to restore structural strength to Wall B, raise its height to reinstate its flood defence function, and stabilise wall A through ground stabilisation.
The condition of Wall B has also highlighted the declining state of the Harbour Master’s office and adjacent public toilets. Following the repairs to the harbour V2/25
walls, the paper seeks Cabinet’s support to investigate a series of options for the council owned buildings.
Both elements are presented together to support a coordinated approach to investment, with further transformation of the public space aligned to the Strategic Asset Management Plan to shape the final proposals.
2. Recommendation(s)
2.1That Cabinet delegate authority to the Executive Director for Place to agree a specification for required works, procurement and award of contracts for harbour wall repairs up to a maximum spend (shown in Appendix 1), following consultation with the Cabinet Member for Place Services and the Section 151 Officer.
2.2That Cabinet recommend investigating a series of options for the council owned buildings that have been affected by the localised ground movement.
3. Reason for the recommendation(s) 3.1 Delegating authority for the overall harbour wall repair works will ensure that essential stabilisation and repair activity can proceed in a coordinated and efficient manner, maintaining the safety, functionality and resilience of key harbour infrastructure. Consultation with the Cabinet Member for Place Services and the Section 151 Officer will provide appropriate oversight and financial assurance.
3.2The full options for the related buildings cannot be suitably assessed until the works to the walls have been completed. The options for the buildings will need to be investigated, with a subsequent report presented to Cabinet if further substantial works are required.
4. The report
4.1West Bay Harbour Walls
Location and function Walls A and B form the western and southern sides of the West Bay inner harbour and are critical infrastructure for the Council’s commercial harbour activity, local business operations, tourism and flood defence. Located directly behind Wall B are several council owned assets, including trading kiosks, public toilets and the Harbour Master’s office. V2/25
Failure and temporary stabilisation Wall A requires urgent maintenance, while Wall B is in extremely poor condition with no remaining design life. Wall B is also too low to provide effective flood defence, increasing the risk of inundation to nearby businesses and properties during storm events. Further deterioration would require closure of the kiosks and the Harbour Master’s office until repairs could be completed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.