CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Dorset Council
Audit and Governance Committee, Monday 27 April 2026 at 6.30pm

Audit Actions Update Report

Noted Finance 1 paper

AI summaryDorset Council's Audit and Governance Committee has noted the SWAP audit update, endorsed a new risk-based approach to managing audits, and asked for thematic focus areas at the next meeting on 29 June 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedSWAP audit update noted; risk-based governance approach endorsed
MoneyNo financial implications reported
What happens next29 June 2026Thematic focus areas to be brought to next committee
Who it affectsAudit monitoring and governanceDorset Council's audit actions and internal control oversight

What was decided

The committee noted the SWAP audit update, including the detailed progress report at Appendix 1. Report 2.1

The committee endorsed the new risk-based governance approach to managing and reporting on SWAP audits and actions. Report 2.1

The committee asked that thematic areas for focus be brought to the next meeting on 29 June 2026. Report 2.1, 4.22

Why

The committee provides independent assurance on the council's risk management, internal control, and financial reporting arrangements and needs timely, risk-based updates on audit activity. Report 3.1

The new risk-based approach places organisational risk at the heart of the committee's work, focusing attention on actions with the most significant impact on internal control and resilience. Report 1.3, 4.4, 4.5

Audit monitoring responsibility has formally transitioned from SWAP to the council's Policy, Intelligence & Performance (PIP) service, strengthening corporate alignment between assurance, performance, and risk. Report 4.1, 4.2

What happens next

The next audit progress report will be brought to the committee on 29 June 2026, continuing the thematic reporting approach. Report 4.22, 4.23

A detailed organisational learning programme and implementation plan will be developed in summer 2026, with updates on the Health & Safety Investigation Action Plan whose remaining actions are due by 31 May 2026. Report 4.14, P112

SWAP's annual review has been rescheduled from April to June 2026 to reflect completed assurance work. Report P99

Options considered

  • Chosen: Note the SWAP audit update and endorse the new risk-based approach. Supports the committee's assurance role and prioritises areas of greatest organisational risk Report 2.1, 3.1, 3.2
  • Rejected: Alternative options. Not applicable; the report presents information and does not recommend a change to policy Report P40

Implications

  • Other: There are no legal, financial, climate, wellbeing, equality, or risk implications arising directly from the report. Report 6.1, 7.1, 8.1, 9.1, 10.1, 11.1, 12.1

Who and where

  • Dorset Council's Audit and Governance Committee Report 3.1
  • SWAP (South West Audit Partnership) audit action owners across the council Report 1.1, 4.1
  • Policy, Intelligence & Performance (PIP) service, which now coordinates audit activity Report 4.1, 4.2
  • Information Governance areas including Data Maturity and ICT Assurance Mapping, which carry high inherent risk scores Report P31, P58, P59

Timeline

  • 1 January 2026 to 9 April 2026: 39 audit actions closed (6 priority 1, 19 priority 2, 14 priority 3), of which 28 were overdue Report 4.10
  • 31 March 2026: SWAP issued a progress report to Dorset Council on the implementation of the investigation audit Report 4.15
  • 7 April 2026: Most recent audit action progress updates received and recorded Report 4.16
  • 31 May 2026: Target completion date for remaining Health & Safety Investigation actions (except 1 overdue priority 2) Report 4.14, P98
  • 29 June 2026: Next Audit and Governance Committee meeting; next audit progress report and thematic focus areas to be presented Report 4.22
  • Summer 2026: Further update including detailed organisational learning programme and implementation plan to be developed Report P112

Plain English for the jargon

  • SWAP: South West Audit Partnership, the council's audit provider
  • PIP: Policy, Intelligence & Performance service within Dorset Council, which now coordinates audit activity
  • Inherent risk rating: The level of risk assuming no audit action or mitigation is in place
  • SMART: Specific, measurable, achievable, relevant, time-bound (used to describe quality audit actions)
  • SIGG: Strategic Information Governance Group
  • IAR: Information Asset Register
  • IAO: Information Asset Owner
  • SLT: Senior Leadership Team
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item206

Resolved

Decision - That the SWAP audit update provided in the report, including the detailed progress report at Appendix 1 be noted. - That the new risk-based governance approach to managing and reporting on SWAP audits and actions be endorsed. - That thematic areas for focus be bought to the next committee meeting on 29 June 2026.
Word for word from the decision Dorset published for this meeting. Source: moderngov.dorsetcouncil.gov.uk

Follow this further

Built from Dorset's papers

What the report saysPro

Report to Audit and Governance Committee

Executive summary

1.1This report provides the Audit & Governance Committee with an overview of performance relating to South West Audit Partnership (SWAP) audits and actions.

1.2The report presents an update on progress made since the last committee report in January 2026, including actions completed, actions still outstanding and those overdue. All audits and actions are assessed using the council’s risk scoring matrix, as defined in the risk management framework.

1.3Our new approach places organisational risk at the heart of the Committee’s work. By using risk scoring to identify where the council faces its greatest exposure, we can focus attention on the actions that have the most significant impact on strengthening internal control and resilience. This ensures committee time is focused on the areas where timely intervention delivers the greatest benefit, supported by a clear and proportionate framework for addressing overdue actions. The full SWAP audit portfolio has been risk -assessed and is presented as an annex to this report.

1.4This report presents a thematic approach to assurance updates and reporting, aligned to the council’s principal risks and scored with an inherent risk rating that is, the level of risk should no audit action be undertaken or mitigation be in place.

1.5Based on these risk assessments as well as direction from the committee’s chairs, thematic key areas of focus this quarter are:

• ICT Assurance Mapping • Data Maturity

1.6For these areas, audit action activity has been collated providing a rounded and meaningful narrative to support an assurance discussion. In addition, audit action owners are reporting directly to the same committee on aligned areas of business, with the council’s risk appetite and audit requirements helping to frame these broader discussions

Recommendations

2.1That the committee: • notes the SWAP audit update provided in this report, including the detailed progress report at Appendix 1. • endorses the new risk-based governance approach to managing and reporting on SWAP audits and actions • identifies priority thematic areas for focus at the next committee meeting on 29 June 2026.

Reason for the recommendations

3.1The Audit & Governance Committee is responsible for providing independent assurance on the adequacy and effectiveness of the Council’s risk management framework, internal control environment, and financial reporting arrangements. The Committee therefore requires timely, risk based updates on audit activity to enable it to discharge its assurance role effectively and to maintain oversight of areas where organisational exposure is greatest.

3.2The recommendations support the committee in fulfilling its constitutional function to promote and maintain high standards of governance and ensure that audit findings are managed in a transparent and accountable manner. By presenting audit progress through a structured, risk aligned approach, the report strengthens Members’ ability to scrutinise internal control, identify weaknesses, and seek appropriate assurance from audit action owners. 3.3 The transition of audit monitoring from SWAP to the Policy, Intelligence & Performance (PIP) service has strengthened corporate alignment between assurance, performance, and risk.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit Actions Update ReportReport 168 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 32 attended
GS
Councillor Gary SuttleChair, present
SF
Councillor Spencer FlowerVice-Chair, present
BB
Councillor Belinda BawdenCommittee Member, present
NE
Councillor Neil EysenckCommittee Member, present
JH
Councillor Jill HaynesCommittee Member, apologies
AP
Councillor Andrew ParryCommittee Member, present
AT
Councillor Andy ToddCommittee Member, present
BE
Councillor Beryl EzzardCommittee Member, present
RH
Councillor Ryan HollowayCommittee Member, present
CK
Councillor Chris KippaxCommittee Member, present
RO
Roger OngCo-Optee, present
SR
Simon RoachCo-Optee, present

All 32 on the meeting page

On this subject at Dorset

Search all
  1. Audit Actions Update ReportThis decision
  2. Approval of the Harbours Marine Safety Plan and update on Port Marine Safety Code Audit ActionsApproved

More from Dorset Audit and Governance Committee

All decisions
MeetingDecisionOutcome
3 Aug 2026 Recruitment to the Independent Remuneration Panel Report- That support was sought from South-West Councils to fulfil the role of chair of the panel; - That an open recruitme... Decided Open
3 Aug 2026 Exempt BusinessThat the press and the public be excluded for the following item(s) in view of the likely disclosure of exempt inform... Decided Open
27 Apr 2026 Risk Management UpdateDecision - That the selected Strategic Risks and their associated risk appetites, as context for the committee’s cons... Noted Open
27 Apr 2026 Corporate Complaints PolicyIt was agreed that a report would be brought back in six months to review the revised policy. Decision That the Audit... Agreed Open
27 Apr 2026 Exempt BusinessThat the press and the public be excluded for the following item(s) in view of the likely disclosure of exempt inform... Decided Open