AI summaryDorset Council's Audit and Governance Committee noted strategic risks on digital information and cyber security, considered the adequacy of controls, and asked for a progress update on the risk scoring matrix review at the next meeting on 29 June 2026.
Written from the decision and the officer reportPDF Pro
OutcomeNotedConsidered risk controls and appetites for data and security risks
MoneyNot stated
What happens next29 June 2026Next risk management update with Q4 data and matrix review progress
Who it affectsDorset Council's risk management frameworkStrategic risks across all directorates and risk scoring approach
What was decided
The committee noted the selected Strategic Risks (Risk 22 on Digital Information Management and Risk 91 on Cyber Security) and their risk appetites, as context for two other papers at the same meeting. Report 1.2, P18, P19
The committee considered the adequacy of current risk controls and the appropriateness of the stated risk appetite for each principal risk. Report P8
The committee noted the Quarter 3 risk data in Appendix A and agreed to receive an update on the review of the Risk Scoring Matrix at the next risk management update on 29 June 2026. Report 1.6, 1.7, 4.7
Why
The report is the first under a new thematic approach agreed on 12 January 2026, designed to give the committee deeper independent assurance on the council's risk management framework and internal control environment. Report 1.1, 4.1, P13
Risk 22 and Risk 91 were chosen because they sit at the higher end of the risk profile with significant potential impact on operational resilience, information integrity and service continuity. Report 1.2, 4.2
A risk-based approach to decision-making is intended to remain proportionate and aligned with organisational objectives and key deliverables. Report 3.1
What happens next
Work continues with directorate leads to review and strengthen the Risk Scoring Matrix, with clearer impact and likelihood definitions, automation, and better alignment with risk appetite. A progress update is due at the 29 June 2026 meeting. Report 1.4, 4.4, P22
The Policy, Intelligence and Performance Service is aligning Southwest Audit Partnership (SWAP) audit activity with the council's risk management framework; a detailed update will come through the Audit actions update Report at this meeting. Report 1.5, 4.5
The committee is invited to identify any areas for future focus or where deeper assurance may be required ahead of the next thematic review on 29 June 2026. Report P8, 4.7
Options considered
Rejected: Alternative options considered. The report states no alternative options were considered. Report 5.1
Implications
Legal: No direct legal implications, though unmanaged risks could compromise the council's ability to meet statutory obligations. Report 6.1
Financial: No direct financial implications, though unmanaged risks could threaten financial stability, and any new risk controls with budget impacts would follow the Scheme of Delegation and Constitution. Report 7.1
Equalities: No specific equality implications arising from this report, although the Corporate Risk Register identifies several risks in this category. Report 12.1
Climate: No specific natural environment, climate or ecology implications arising from this report, although the Corporate Risk Register identifies several risks in this category. Report P33
Other: No specific health or well-being implications arising from this report, although the Corporate Risk Register identifies several risks in this category. Report 9.1
Who and where
Dorset Council, through its strategic risk profile across Adults and Housing, Children's Services, Corporate Development, Legal and Democratic, Place, and Public Health and Prevention directorates Report 4.6, P60, P72, P83, P94, P99, P118
The Audit and Governance Committee, in its role of providing independent assurance on risk management and internal control Report P13, 4.1
Residents and service users, who could be affected by the outcomes of risks such as adult safeguarding, housing supply, waste disposal and coastal defences Report P62, P68, P113, P108
Timeline
12 January 2026: Committee agreed the new thematic approach to risk reporting. Report 4.1, 14.1
27 April 2026: This meeting; first thematic Risk Management Update considered. Report P50, 4.1
29 June 2026: Next Risk Management Update, to include Quarter 4 data, an update on the Risk Scoring Matrix review, and further thematic analysis. Report 1.4, 1.7, 4.7, P22
Plain English for the jargon
SWAP: Southwest Audit Partnership, the body providing internal audit services.
Principal Risk: A high-level category of risk within the Risk Management Framework to which strategic risks are aligned.
Risk appetite: The agreed level of risk the council is willing to accept, set for each principal risk (for example, Open or Averse).
DSG: Dedicated Schools Grant, the ring-fenced funding for schools.
ICT: Information and Communications Technology.
LTP: Local Transport Plan.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item205
Resolved
Decision - That the selected Strategic Risks and their associated risk appetites, as context for the committee’s consideration of the “Annual Information Governance Report” and “Protecting our council - cyber security risk management and future improvement plans” papers presented to this meeting of the committee be noted. - That the adequacy of current risk controls and the appropriateness of the stated risk appetite for each principal risk was considered. - To receive an update on the progress of the review of Dorset Council’s risk scoring matrix at the next risk management update on 29 June 2026 be agreed. - That the Quarter 3 risk data (Appendix A) be noted.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
1.1This report provides the Audit and Governance Committee with the first thematic risk management update, following the committee’s agreement in January 2026 to adopt a more dynamic and analytical approach to risk reporting. The thematic model is designed to strengthen the committee’s ability to provide independent assurance on the adequacy and effectiveness of Dorset Council’s risk management framework, and internal control environment.
1.2For this first cycle, the committee expressed interest in undertaking deeper analysis of two strategic level risks aligned to the Data and Information Management and Security Principal Risks. These risks, Risk 22 (Digital Information Management) and Risk 91 (Cyber Security), have been identified as among the most significant in their potential impact on delivering Dorset Council’s key organisational objectives. Both sit at the higher end of the risk profile, with clear implications for operational resilience, information integrity, and service continuity. Their associated risk appetites (Open for information management and Averse for security) provide an important framing for consideration of the “Annual Information Governance Report” and “Protecting our council - cyber security risk management and future improvement plans” papers presented to this same committee meeting.
1.3The transition to thematic reporting represents an opportunity to offer richer insights and support more targeted committee assurance activity, enabling the committee to assess the adequacy of controls and make recommendations to strengthen the internal control environment where appropriate.
1.4Progress continues across several key areas of improvement within the risk management framework. Work remains ongoing with directorate leads to review and strengthen the Risk Scoring Matrix, ensuring clearer definitions of impact and likelihood, improved granularity, and embedding of risk appetite into scoring. This work also aims to introduce appropriate automation to enhance usability and the quality of risk data. An update on progress will be presented to the committee in June 2026.
1.5The Policy, Intelligence and Performance Service is advancing its programme of work to align Southwest Audit Partnership (SWAP) audit activity with the Council’s risk management framework. This alignment supports a more risk- based approach to managing audit recommendations, ensuring that outstanding actions can be viewed through the lens of residual exposure and organisational risk appetite. A detailed account of progress will be provided in the “Audit actions update Report” to this same committee meeting.
1.6Quarter 3 has achieved 100% Risk Register compliance, maintaining strong organisational discipline in the review and maintenance of strategic risks. This supports continued transparency and consistency in how risks are articulated, assessed, and monitored.
1.7The next risk management update, scheduled for 29 June 2026, will present Quarter 4 risk data, along with updates on the Risk Scoring Matrix and further thematic analysis of the risk environment.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.