SEND Inclusion Hubs Phase 2

Approved Executive 1 paper

AI summaryDorset Council Cabinet approved £4.3 million capital and £2 million a year revenue for Phase 2 SEND Inclusion Hubs in mainstream schools, with delegation to officers to award contracts within the budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCapital, revenue and delegations all agreed
Money£4.3m capital, £2m a year revenuePlus £5,544,672 HNPCA in 2026/27
What happens nextOfficers to procure and award contractsWithin agreed programme budget
Who it affectsChildren with SEND in DorsetMore local specialist places in mainstream schools

What was decided

Cabinet approved a capital budget of £4.3 million and the funding allocations for Phase 2 Inclusion Hubs set out in the Business Case at Appendix A. Report 2.1

Cabinet approved a recurrent High Needs Block revenue allocation of £2m per year, factored into Dorset’s High Needs Block SEND reform modelling. Report 2.3

Cabinet delegated authority to named Executive Directors, with the Director Resources and relevant Cabinet Members, to procure and award contracts and release funding, provided costs stay within the approved allocations. Report 2.2, 2.4

Why

To let projects move forward at pace, deliver cost savings, and improve the sufficiency of SEND placements and support. Report 3.1, 4.1

To put appropriate oversight and authority in place so projects can progress from inception to delivery. Report 3.2

To evidence delivery against the SEND Local Reform Plan, which is needed to secure High Needs Stability Grant funding. Report 3.3, 4.5, 11.2

What happens next

Officers will procure and award contracts, or release agreed funding, to Multi Academy Trusts and other third parties delivering the Phase 2 Inclusion Hubs, subject to costs staying within the programme budget. Report 2.2, 6.3

High Needs revenue funding will be released by the Executive Director, Children’s Services to operators of the hubs, within the agreed annual allocation. Report 2.4

The Council must secure Department for Education approval of its Local SEND Reform Plan to receive a High Needs Stability Grant in 2026/27 covering 90% of eligible high needs DSG deficit accrued to end 2025/26. Report 4.5, 7.1, 11.2

The money

  • £4.3 million Capital budget for Phase 2 SEND Inclusion Hubs Report 2.1
  • £2m per year recurrent High Needs Block revenue allocation for Phase 2 Inclusion Hubs Report 2.3
  • £5,544,672 2026/27 High Needs Provision Capital Allocations (HNPCA) within the SEND Capital Programme Report 7.1
  • approximately £19.5k per annum Cost of an Inclusion Hub place Report 2.3
  • in the region of £64k per annum Cost of an independent placement, used for comparison Report 2.3

Options considered

  • Chosen: Proceed with Inclusion Hubs as part of the SEND Capital Programme. Considered a successful, tried and tested part of SEND delivery in Dorset and aligned with the SEND White Paper 2026 direction. Report 5.1, 5.2
  • Rejected: Alternative ways of addressing the SEND situation in Dorset. The SEND Reform Plan has already considered the most appropriate approaches, with Inclusion Hubs as a key element. Report 5.1

Implications

  • Financial: Inclusion Hub places are about £19.5k a year, against independent placements of around £64k, supporting cost savings on the High Needs Block. Report 2.3
  • Legal: The Council has signed a Memorandum of Understanding with the Department for Education for 2026/27 HNPCA and must evidence outcomes or risk reduced future funding. Report 6.2, 11.3
  • Equalities: More specialist places in mainstream schools are intended to reduce the number of Dorset pupils placed outside the area or in independent special schools. Report 12.1
  • Risk: Current risk and residual risk both identified as Medium, with delays risking failure to evidence outcomes under the MoU. Report P42, P43, 11.3
  • Climate: Climate and ecology assessment records a major negative impact on Energy, mixed impact on Buildings and Assets, and a major positive impact on Water. Report P58

Who and where

  • Dorset children with SEND and their families Report 4.1, 12.1
  • Mainstream schools hosting the Inclusion Hubs Report 4.3, 4.4
  • Multi Academy Trusts acting as responsible bodies for contractual arrangements Report 6.3

Timeline

  • September 2022: SEND Capital Strategy Implementation Plan agreed by Cabinet Report 4.1, 14.2
  • November 2025: Children’s Services Capital Programme report to Cabinet formalised capital decisions and delegations, including SEND Inclusion Hubs Report 4.2, 14.1
  • 2026/27: High Needs Provision Capital Allocations of £5,544,672 and potential High Needs Stability Grant covering 90% of eligible DSG deficit, subject to DfE approval of the Local SEND Reform Plan Report 4.5, 7.1, 11.2
  • 23 June 2026: Cabinet decision approving Phase 2 Inclusion Hubs capital and revenue Report 2.1, 2.3

Plain English for the jargon

  • SEND: Special Educational Needs and Disabilities
  • HNPCA: High Needs Provision Capital Allocations, Department for Education capital funding for SEND provision
  • DSG: Dedicated Schools Grant, the ring-fenced schools funding stream including the High Needs Block
  • MoU: Memorandum of Understanding between the Council and the Department for Education for HNPCA
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item21

Resolved

(a) That the capital budget of £4.3 million and funding allocations to projects set out in the Business Case within Appendix A of the Cabinet report dated 23 June 2026 be approved. (b) That authority be delegated to the Executive Director, Economy and Environment in consultation with the Executive Director, Children’s Services, Cabinet Member for Regeneration, Economic Growth and Strategic Assets and Cabinet Member for Children, Families and Education and, together with the Director Resources to procure and award contracts or release agreed funding to third parties delivering projects, for any Phase 2 Inclusion Hub as set out in the Business Case at Appendix A of this Cabinet report, provided the project costs are contained within the programme budget. (c) That the High Needs Block revenue allocation of £2m per year recurrent, as set out in the Business Case within Appendix A of this Cabinet report dated 23 June 2026 be approved. This has been factored into Dorset’s High Needs Block SEND reform modelling. Inclusion Hub places are approximately £19.5k per annum compared with an independent placement in the region of £64k per annum. (d) That authority be delegated to the Executive Director, Children’s Services, in consultation with the Cabinet Member for Children, Families and Education and the Director, Resources to release high needs revenue funding to third parties operating any Phase 2 Inclusion Hub as set out in the Business Case at Appendix A of this Cabinet report, provided the funds are within the high needs revenue allocation. Reason for the decision 1. To ensure that the projects can move forward at pace, to provide cost savings and improve the sufficiency of SEND placements and support. 2. To ensure appropriate oversight and authority is in place to allow projects to progress through from inception to delivery. 3. To evidence delivery against the SEND Local Reform Plan.
Word for word from the decision Dorset published for this meeting. Source: moderngov.dorsetcouncil.gov.uk

Follow this further

Built from Dorset's papers

What the report saysPro

Report to Cabinet

Recommendations

2.1That the capital budget of £4.3 million and funding allocations to projects set out in the Business Case within Appendix A of this Cabinet Report dated 23 June 2026 be approved.

2.2That authority be delegated to the Executive Director, Economy and Environment in consultation with the Executive Director, Children’s Services, Cabinet Member for Regeneration, Economic Growth and Strategic Assets and Cabinet Member for Children, Families and Education and, together with the Director Resources to procure and award contracts or release agreed funding to third parties delivering projects, for any Phase 2 Inclusion Hub as set out in the Business Case at Appendix A of this Cabinet Report, provided the project costs are contained within the programme budget.

2.3That the High Needs Block revenue allocation of £2m per year recurrent, as set out in the Business Case within Appendix A of this Cabinet Report dated 23 June 2026 be approved. This has been factored into Dorset’s High Needs Block SEND reform modelling. Inclusion Hub places are approximately £19.5k per annum compared with an independent placement in the region of £64k per annum.

2.4That authority be delegated to the Executive Director, Children’s Services, in consultation with the Cabinet Member for Children, Families and Education and the Director, Resources to release high needs revenue funding to third parties operating any Phase 2 Inclusion Hub as set out in the Business Case at Appendix A of this Cabinet Report, provided the funds are within the high needs revenue allocation.

3. Reason for the recommendation(s)

3.1To ensure that the projects can move forward at pace, to provide cost savings and improve the sufficiency of SEND placements and support.

3.2To ensure appropriate oversight and authority is in place to allow projects to progress through from inception to delivery.

3.3To evidence delivery against the SEND Local Reform Plan. V3/26

4. The report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SEND Inclusion Hubs Phase 2Report 369 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 50 attended
NI
Councillor Nick IrelandChair, present
RB
Councillor Richard BiggsVice-Chair, present
JA
Councillor Jon AndrewsCommittee Member, present
SB
Councillor Shane BartlettCommittee Member, present
MB
Councillor Matt BellCommittee Member, present
SC
Councillor Simon CliffordCommittee Member, apologies
SR
Councillor Steve RobinsonCommittee Member, present
CS
Councillor Clare SuttonCommittee Member, present
GT
Councillor Gill TaylorCommittee Member, present, as expected, virtual
BW
Councillor Ben WilsonCommittee Member, present
SD
Susan DallisonOfficer, expected
SC
Sean CremerOfficer, in attendance

All 50 on the meeting page

More from Dorset Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 July 2026 (period 4) financial management report 26/27Decision (a) That the Senior Leadership Team’s forecast as of July 2026 including progress in addressing demand for s... Noted Open
8 Sep 2026 Additional Procurement Pipeline Report - over £500k (2026 - 27) and Modern Slavery Transparency Statement 2025 - 2026Decision (a) Cabinet considered the contents of the report (of 8 September 2026) in respect of proposed additional mo... Approved Open
8 Sep 2026 Exempt BusinessDecision That the press and the public be excluded for the following item(s) in view of the likely disclosure of exem... Decided Open
28 Jul 2026 Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ... Noted Open
28 Jul 2026 Dorset Local Visitor Economy Partnership Destination Management Plan(a) That the Dorset Local Visitor Economy Partnership Destination Management Plan (DLVEPDM) be adopted and (b) That a... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies