Procurement of a replacement system for Parking enforcement and permits
ApprovedExecutive1 paper
AI summaryDorset Council Cabinet approved procurement of a replacement parking enforcement and permit system worth up to £700,000 via a Crown Commercial Service framework, with contract award expected in late 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedvia CCS framework RM6347 Lot 3
Moneyup to £700,000maximum over 6 year contract term
What happens nextAward late 2026system operational early 2027
Who it affectsParking service usersdrivers, permit holders, CEOs in Dorset
What was decided
Cabinet approved the procurement of a replacement parking enforcement and permits system with a maximum value of £700,000 over a maximum six-year term. Report 2.1
Cabinet approved using the Crown Commercial Service Transport Technology Framework RM6347, Lot 3, as the procurement route, with a 60/40 quality/price evaluation. Report 2.1
Authority was delegated to the Executive Director for Economy and Environment, in consultation with the Section 151 Officer, the Monitoring Officer, and the Cabinet Member for Place Services, to approve final terms, award the contract, and approve modifications. Report 2.1
Why
Existing systems inherited from legacy authorities are unintegrated, hard to use, inefficient and beyond their original contract terms, forcing Civil Enforcement Officers to switch between multiple systems. Report P1, 4.1
A modern integrated system would improve efficiency, data integration and customer experience, and increase CEO focus on higher-value enforcement.
Market research indicates the contract may exceed the £500,000 Key Decision threshold, so Cabinet authorisation is required for governance compliance. Report 7.1
What happens next
Engage the Crown Commercial Service and IT experts to validate the approach, specification and route to market.
Run a competitive procurement under framework RM6347 Lot 3 and award the contract in late 2026, with the system going live in early 2027. Report P1
Share costs between Parking and ICT Services, with any cost increases funded from Parking budgets through process efficiency.
The money
£700,000 anticipated maximum contract value Report 2.1
£450k to £550k or more anticipated total contract value range depending on duration and bid values Report 7.1
£500,000 Key Decision threshold likely to be exceeded Report 7.1
Options considered
Rejected: Do Nothing (Status Quo). Current systems are difficult to use, inefficient, not integrated and weaken compliance Report 5.1
Rejected: Partial integration of legacy systems. Would not resolve inefficient fragmentation between separate legacy systems
Chosen: Fully integrated enforcement and permit system. Single joined-up system improves efficiency, data integration, customer experience and value for money Report P6
Rejected: Continuing current contract arrangements. Exposes the Council to governance, legal and financial risk and does not improve integration or service quality
Rejected: Open procurement procedure. Would take much longer and offers no clear advantage over pre-vetted framework routes
Chosen: Crown Commercial Service Transport Technology Framework RM6347, Lot 3 (Parking Management). Access to pre-qualified suppliers, standardised terms, framework management and a compliant competitive process Report P8
Implications
Financial: Costs are revenue in nature, shared between Parking and ICT Services, with any increase funded from Parking budgets through process efficiency; automatic CPI-based indexation will manage routine inflation.
Legal: Parking operations must comply with the Traffic Management Act 2004 and Road Traffic Regulation Act 1984, and the new system is described as a PA2023 compliant digital solution. Report 6.1
Risk: Current risk is medium, reflecting public and member sensitivity to parking changes and operational complexity; residual risk is low to medium subject to ongoing monitoring. Report 11.1
Equalities: The upgrade will maintain and improve accessibility through digital payments, digital permits and better user interfaces, with no changes to policy or eligibility criteria. Report 12.1
Climate: The proposal supports the Council's Natural Environment, Climate and Ecology Strategy and Net Zero commitments by managing parking effectively, reducing congestion and improving safety. Report 8.1, P12
Other: Depending on which supplier wins, members of the public may need to download a different app to manage permits. Report P8
Other: If future parking revenue increases, the Council may consider investing in improved countywide bus transport routes. Report 10.1
Who and where
Civil Enforcement Officers Report 4.1
Dorset Council Parking and ICT Services
Drivers and permit holders across Dorset
Town centre visitors and people with mobility needs Report 9.1
Early 2027: System implementation fully operational Report P1
3 years plus three single-year extensions (+1, +1, +1): Contract term structure (maximum six years total)
Plain English for the jargon
CEO: Civil Enforcement Officer, the council staff who check parking compliance
CCS: Crown Commercial Service, a government body that runs procurement frameworks
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item24
Resolved
(a) That the procurement of this contract, with an anticipated maximum value of £700,000 and a maximum six-year contract duration, be approved. (b) That the procurement of a new contract via the Crown Commercial Service Transport Technology Framework RM6347, Lot 3 (Parking Management), be approved. (c) That authority be delegated to the Executive Director for Economy and Environment, in consultation with the Section 151 Officer, the Monitoring Officer, and the Cabinet Member for Place Services, to approve the final contract terms, award the proposed contract, and approve contract modifications throughout the term where these are compliant with legal advice. Reason for the decision To enable the continuity of an essential service via a compliant contract. To improve efficiency, data integration and customer experience. To comply with Key Decision governance when the £500k limit is exceeded.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
This report seeks Cabinet’s advance approval and delegated authority to proceed with the procurement and contract award of a replacement system for parking enforcement and permit management. The existing systems, inherited from legacy authorities, are unintegrated, hard to use, inefficient and beyond their original contract. A replacement integrated system is needed to ensure service continuity, improve operational efficiency and enhance customer experience. Market research found that the total contract term value may exceed £500,000 (the Key Decision threshold). To comply with governance rules, Cabinet’s authorisation is requested for the delegated authority to proceed with the procurement and contract award. It is anticipated that the contract will be awarded in late 2026, with system implementation fully operational in early 2027. 2. Recommendations
2.1That Cabinet: • Approves the procurement of this contract, with an anticipated maximum value of £700,000 and a maximum six-year contract duration. • Approves the procurement of a new contract via the Crown Commercial Service Transport Technology Framework RM6347, Lot 3 (Parking Management). • Delegates authority to the Executive Director for Economy and Environment, in consultation with the Section 151 Officer, the Monitoring Officer, and the Cabinet Member for Place Services, to approve the final contract terms, award the proposed contract, and approve contract modifications throughout the term where these are compliant with legal advice.
Reasons for the recommendations
3.1To enable the continuity of an essential service via a compliant contract. 3.2 To improve efficiency, data integration and customer experience. 3.3 To comply with Key Decision governance when the £500k limit is exceeded.
4. The report
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.