Dorset Council, Thursday 16 July 2026 at 6.30pm

Capital Programme Review

Approved Committee 6 papers

AI summaryDorset Council has approved a reset of its capital programme, cutting stalled and legacy schemes and raising the capital contingency budget from £2m to £10m.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedNew framework, standing items, revised schemes
Money£2m to £10mCapital Contingency budget increase
What happens nextNew approval framework appliesTo future capital project decisions
Who it affectsCouncil capital projectsLegacy, stalled and inactive schemes removed

What was decided

Full Council approved a new structured approval framework for capital projects, set out in Appendix A of the Cabinet report of 23 June 2026. Report P2

Full Council endorsed a fundamental reset of the capital programme, including removal of legacy, stalled and inactive schemes. Report P3

Full Council approved the Capital Contingency budget increase from £2m to £10m, funded by removing stalled, low-value and legacy schemes with no recent activity. Report P5

Why

The report describes the change as a fundamental reset of the capital programme, removing schemes described as legacy, stalled, inactive or of low value with no recent activity. Report P3, P5

What happens next

The new approval framework is to be used for capital projects going forward, and revised lists of standing items and approved capital schemes are included in the programme. Report P2, P4, P5

The money

  • £2m to £10m Increase to the Capital Contingency budget, funded by removal of stalled, low-value and legacy schemes with no recent activity Report P5

Implications

  • Financial: Capital Contingency budget rises from £2m to £10m, funded by removing other schemes from the programme. Report P5
  • Risk: Legacy, stalled and inactive schemes are removed from the capital programme, with funding redirected to the contingency budget. Report P3, P5

Who and where

  • Sponsors and delivery teams for capital schemes, particularly those classed as legacy, stalled or inactive Report P3, P5
  • Future capital project proposals, which will be assessed under the new approval framework Report P2

Timeline

  • 23 June 2026: Cabinet considered the Capital Programme Review report and appendices Report P6, P7
  • 2026-07-16: Full Council took the decision on the Capital Programme Review

Plain English for the jargon

  • Capital programme: The council's planned spending on long-term assets and projects, as opposed to day-to-day revenue spending.
  • Capital Contingency: Money held back within the capital programme to cover unforeseen costs or changes in capital schemes.
  • Standing items: Recurring capital items included in the programme each year, as listed in Appendix B.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item23

Resolved

Decision That Full Council: 1. Approve the new structured approval framework for capital projects, as outlined in Appendix A of the report to Cabinet of 23 June 2026 2. Endorse a fundamental reset of the capital programme, including removal of legacy, stalled, and inactive schemes 3. Approve the “Standing items” to be included in the capital programme, as shown in Appendix B of the report 4. Approve the revised “Approved capital schemes” to be included in the capital programme, as shown in Appendix C of the report 5. Approve the increase to the Capital Contingency budget from £2m to £10m, funded from the removal of stalled, low-value and legacy schemes with no recent activity.
Word for word from the decision Dorset published for this meeting. Source: moderngov.dorsetcouncil.gov.uk

Follow this further

Built from Dorset's papers

What the report saysPro

Report to Dorset Council

Recommendation

Full Council are asked to:

1. Approve the new structured approval framework for capital projects, as outlined in Appendix A of the report to Cabinet of 23 June 2026

2. Endorse a fundamental reset of the capital programme, including removal of legacy, stalled, and inactive schemes.

3. Approve the “Standing items” to be included in the capital programme, as shown in Appendix B of the report.

4. Approve the revised “Approved capital schemes” to be included in the capital programme, as shown in Appendix C of the report. 5. Approve the increase to the Capital Contingency budget from £2m to £10m, funded from the removal of stalled, low-value and legacy schemes with no recent activity.

Appendices

Capital Programme Review Report to the meeting of Cabinet - 23 June 2026 including appendices Appendix A – Approval Framework for Capital Projects Appendix B – Standing items Appendix C – Approved capital schemes Appendix D – Capital Pipeline

Agenda and papers for Cabinet on Tuesday, 23rd June, 2026, 6.30 pm - Dorset Council

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix-A-Capital Bid Process-Flow-ChartAppendix 88 KB Download
PDF
Appendix-B-Standing-itemsAppendix 107 KB Download
PDF
Appendix-C-Approved-itemsAppendix 179 KB Download
PDF
Appendix-D-Capital-PipelineAppendix 118 KB Download
PDF
Capital Programme ReviewReport 68 KB DownloadRead as text
PDF
Capital-Programme-Review-Cabinet-report-23-June-2026Report 178 KB Download

At this meeting

Whole meeting

Who was there

73 of 93 attended
SJ
Councillor Stella JonesChair, present
LF
Councillor Les FryVice-Chair, present
JA
Councillor Jon AndrewsCommittee Member, present
JA
Councillor Jindy AtwalCommittee Member, present, as expected, virtual
MB
Councillor Mike BakerCommittee Member, present
SB
Councillor Shane BartlettCommittee Member, present
BB
Councillor Belinda BawdenCommittee Member, present
LB
Councillor Laura BeddowCommittee Member, present
DB
Councillor Derek BeerCommittee Member, apologies
MB
Councillor Matt BellCommittee Member, present
RB
Councillor Richard BiggsCommittee Member, present
BB
Councillor Bridget BolwellCommittee Member, present

All 93 on the meeting page

On this subject at Dorset

Search all
  1. Capital Programme ReviewThis decision
  2. Climate programme capital workstreams over £500KApproved
  3. Highways Capital Programme StrategyApproved
  4. Children's Services Capital ProgrammeApproved
  5. Urgent items - SEND Capital ProgrammeDecided
  6. Capital Programme 2023/2024 - 2026/2027Agreed

More from Dorset Dorset Council

All decisions
MeetingDecisionOutcome
16 Jul 2026 Joint Local Transport PlanDecision 1. That the Local Transport Plan 2026 – 2041 be adopted 2. That authority be delegated to the Executive Dire... Approved Open
16 Jul 2026 Motion on Notice - submitted by Cllr HollowayDecision That this council writes to the Secretary of State for Transport RH Heidi Alexender MP calling for the law t... Decided Open
14 May 2026 Election of ChairDecision That Cllr S Jones be elected as Chair of the Council for the 2026/27 municipal year. Cllr Jones thanked the ... Decided Open
14 May 2026 Election of Vice-ChairDecision That Cllr L Fry be elected as Vice-Chair of the Council for the 2026/27 municipal year. Cllr Fry thanked the... Decided Open
14 May 2026 Election of Leader of CouncilDecision That Cllr N Ireland be elected as Leader of the Council for the 2026/27 municipal year. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies