CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Dorset Council
Cabinet, Tuesday 28 July 2026 at 6.30pm

Dorset History Centre - approval sought to proceed with development of capital project

Approved Executive 1 paper

AI summaryCabinet approves Dorset History Centre's £5.28 million Past Lives, Future Proofed project, with council acting as financial guarantor for a £110,000 funding gap.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProceed with development work and NLHF Stage 2 application
Money£5.28 million total projectCouncil pledge £540,000, NLHF £3.8 million
What happens nextNLHF Stage 2 application November 2027Delivery Phase from mid-2028
Who it affectsDorset History Centre, archive users, residentsJoint service for Dorset and BCP councils

What was decided

Cabinet approved proceeding with externally funded development work on the Past Lives, Future Proofed project, ahead of a Stage 2 application to the National Lottery Heritage Fund in November 2027 for £3.8 million. Report P8

Authority was delegated to the Executive Director for Economy and Environment, in consultation with the Cabinet Member for Regeneration, Economic Growth and Strategic Assets, for spend, procurement and contract decisions within the total scheme budget. Report P8

Dorset Council will act as financial guarantor, meeting any remaining budget shortfall if the £110,000 fundraising gap cannot be bridged, to protect the larger NLHF grant. Report P8, 4.3

Why

The project would deliver significant inward investment in Dorset's cultural infrastructure, capital improvements to Dorset History Centre and a pan-Dorset public engagement programme running into 2031. Report P9, P6

The building, opened in 1991, is at 96% storage capacity and the project would provide around 30 more years of collections storage space. Report 1.2, P16

Dorset Council's match funding was seen by NLHF as evidence of commitment, and the project offers an approximately 1:9 return on investment for the council. Report 4.6

What happens next

The Dorset History Centre team will focus on scoping the capital and engagement elements to support a high-quality Stage 2 NLHF application in November 2027. Report 5.3

Recruitment of a Project Archivist (1.0 fte, 18 months) and a Project Community Engagement Officer (0.8 fte, 18 months), plus design team and evaluation consultants, will begin. Report 3.1, P19

The proposal will go to the Property Asset Management Group on 2 July and the Capital Strategy Asset Management Group on 13 July, with a Delivery Phase start planned for mid-2028. Report 5.2, 3.5

The money

  • £603,000 NLHF Development Phase grant, confirmed 5 March Report 1.1, P29
  • £80,000 DHC service reserves, ringfenced match funding Report 1.1, P29
  • £684,000 Development Phase cost, fully funded Report P26
  • £3,800,000 Anticipated NLHF Delivery Phase grant, subject to Stage 2 application Report P31, 2.1
  • £540,000 Dorset Council pledge from capital programme, contingent on Stage 2 success Report P31, 1.2
  • £50,000 Dorset Council Community Infrastructure Levy Report P31
  • £50,000 Dorset Archives Trust contribution Report P31
  • £5,000 Dorchester Town Council contribution Report P31
  • £45,000 Dorset Council Section 106 funding Report P31
  • £110,000 Budget gap to be raised; council will underwrite if needed Report P31, 4.3
  • £4,600,000 Delivery Phase cost Report P26
  • £5,283,000 Total project value across both phases Report P32
  • £150,000 Notional value of in-kind volunteer contribution Report 4.4

Options considered

  • Chosen: Approve development work and act as financial guarantor for the £110,000 gap. Secures large NLHF investment and around 30 years of additional archive storage Report P8, 4.6
  • Rejected: Reject or delay the project. No alternative archive delivery model is under consideration; building is at 96% capacity Report 5.3, 1.2

Implications

  • Financial: Council's £540,000 capital contribution could rise to a maximum of £650,000 if the £110,000 fundraising gap cannot be closed. Report 4.3
  • Financial: Project offers an approximately 1:9 return on investment for Dorset Council across both phases. Report 4.6
  • Legal: All work to comply with applicable law, Contract Procedure Rules and governance; NLHF retrospectively funds projects in quarterly arrears. Report P40, 3.5
  • Staffing: Temporary posts: Project Archivist (1.0 fte, 18 months) and Project Community Engagement Officer (0.8 fte, 18 months), plus consultants. Report 3.1, P19
  • Risk: Current and residual risk both rated Medium, with archive accommodation pressure partly mitigated by the NLHF Development Phase award. Report P57
  • Equalities: A full EQIA has been completed; further work planned with younger people, black and ethnic minority groups, religious minorities, and remote users via improved digital access. Report P58
  • Climate: Project aims for a zero carbon new build and will review low carbon heating options; current building is already highly energy efficient with solar PV. Report P42, P46, P45

Who and where

  • Dorset History Centre users and depositors across Dorset and BCP Report P6, 1.1
  • Dorset History Centre staff and Joint Archives Board Report 1.1, 3.1
  • Dorset Council taxpayers and residents benefiting from cultural infrastructure Report P6, 4.6
  • Dorset Archives Trust and partner funders Report 4.5, P31
  • Schools, researchers and visitors using the centre and engagement programme Report P6, P16

Timeline

  • 2013: Original options appraisal and feasibility study began Report 1.2
  • 2017: Unsuccessful application to Heritage Lottery Fund Report 1.2
  • November 2025: Stage 1 NLHF application submitted Report 1.1
  • 5 March 2026: NLHF confirmed Development Phase grant of £603,000 Report 1.1, P6
  • 2 July 2026: Proposal discussed at Property Asset Management Group Report 5.2
  • 13 July 2026: Proposal discussed at Capital Strategy Asset Management Group Report 5.2
  • 28 July 2026: Cabinet decision to approve the project Report P1
  • November 2027: Stage 2 NLHF application intended for submission Report P6, 2.1
  • mid-2028: Planned start of Delivery Phase Report 3.5
  • into 2031: Public engagement programme expected to run Report P6

Plain English for the jargon

  • DHC: Dorset History Centre, the home of the Joint Archives Service for Dorset Council and BCP Council
  • JAS: Joint Archives Service, shared archive service for Dorset Council and BCP Council
  • NLHF: National Lottery Heritage Fund
  • Stage 2 application: Second stage bid to NLHF seeking the main Delivery Phase grant of £3.8 million
  • Delivery Phase: The construction and engagement phase of the project, planned to start mid-2028
  • Match funding: Funds from non-NLHF sources required to unlock the NLHF grant
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item40

Resolved

(a) That the Dorset History Centre’s request to proceed with externally funded development work on its capital project Past Lives, Future Proofed further to the anticipated submission of a Stage 2 application to the National Lottery Heritage Fund in November 2027 for £3.8 million and subsequent Delivery Phase of the project whose total value over both phases is £5.28 million, be approved. (b) That authority be delegated to the Executive Director for Economy and Environment, in consultation with the Cabinet Member for Regeneration, Economic Growth and Strategic Assets to approve spend decisions, including procurement, contract award, and payment of invoices, within the Total Scheme Budget for the Dorset History Centre capital project as detailed in paragraph 4.2, of the Cabinet report of 28 July 2026. All activity will be undertaken in accordance with Dorset Council’s Contract Procedure Rules, Financial Regulations, Scheme of Delegation and applicable law. Procurement of services for the Delivery Phase of the project is contingent upon a successful Stage 2 application to NLHF. (c) That Dorset Council acts as financial guarantor: Dorset History Centre intends to bridge the current budget gap of £110,000 (see para 4.3 of the Cabinet report of 28 July 2026) by fundraising from a variety of sources. In the event that this proved challenging, Dorset Council will meet the budget shortfall to ensure the viability of the project and the securing of the large capital grant from National Lottery Heritage Fund. Reason for the decision To support and endorse the development of a project that would result in significant inward investment in Dorset’s cultural infrastructure through the provision of capital improvements to Dorset History Centre and a pan-Dorset public engagement programme.
Word for word from the decision Dorset published for this meeting. Source: moderngov.dorsetcouncil.gov.uk

Follow this further

Built from Dorset's papers

What the report saysPro

Report to Cabinet

Cabinet 28 July 2026 Dorset History Centre – approval sought to proceed with development of capital project For Decision Cabinet Member: Cllr R Biggs, Regeneration, Economic Growth and Strategic Assets

Local Councillor(s): All

Senior Leadership Team: J Mair - Director, Assurance and Governance

Report author and job title: Sam Johnston, Service Manager for Archives and Records Email: [email protected] Statutory Authority: Local Government Acts 1962 &1972; Public Records Act 1958; Freedom of Information Act 2000; Environmental Information Regulations 2004; Data Protection Act (GDPR) 2018.

Report status: Public (the exemption paragraph is N/A)

Executive summary: This report provides an update to the Cabinet on the work of the Joint Archives Service (Dorset History Centre) further to the positive result of the service’s application to the National Lottery Heritage Fund (NLHF). The 5 March decision and the £603,000 of funding it provided means that development work needs to start on a major project Past Lives, Future Proofed which it is expected will result in major capital investment in the Dorset History Centre and a significant programme of public engagement lasting into 2031. The total cost of the project (2 phases) is £5.28 million and is contingent upon a successful Stage 2 application to NLHF. Dorset Council has pledged £540,000 match funding built into the capital programme. This report therefore is seeking the Cabinet’s approval to proceed with the development of the project in preparation for the Stage 2 application in November 2027. The project will provide another 30 years of collections storage and extend the working life of Dorset History Centre by decades.

Recommendations: It is recommended that that the Cabinet:

1. Approves Dorset History Centre’s request to proceed with externally funded development work on its capital project Past Lives, Future Proofed further to the anticipated submission of a Stage 2 application to the National Lottery Heritage Fund in November 2027 for £3.8 million and subsequent Delivery Phase of the project whose total value over both phases is £5.28 million. 2. Delegates authority to the Executive Director for Economy and Environment, in consultation with the Cabinet Member for Regeneration, Economic Growth and Strategic Assets to approve spend decisions, including procurement, contract award, and payment of invoices, within the Total Scheme Budget for the Dorset History Centre capital project as detailed in paragraph 4.2. All activity will be undertaken in accordance with Dorset Council’s Contract Procedure Rules, Financial Regulations, Scheme of Delegation and applicable law. Procurement of services for the Delivery Phase of the project is contingent upon a successful Stage 2 application to NLHF. 3. Acts as financial guarantor: DHC intends to bridge the current budget gap of £110,000 (see para 4.3) by fundraising from a variety of sources. Work is already underway and we are confident that we will meet our target. However, in the event that this proves challenging, it is requested of Dorset Council that it meets the budget shortfall to ensure the viability of the project and the securing of the large capital grant from NLHF.

Reason for the recommendation: To support and endorse the development of a project that will result in significant inward investment in Dorset’s cultural infrastructure through the provision of capital improvements to Dorset History Centre and a pan-Dorset public engagement programme.

1. Introduction and background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Dorset History Centre: approval sought to proceed with development of capital projectReport 572 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 51 attended
NI
Councillor Nick IrelandChair, present
RB
Councillor Richard BiggsVice-Chair, present
JA
Councillor Jon AndrewsCommittee Member, present
SB
Councillor Shane BartlettCommittee Member, present
MB
Councillor Matt BellCommittee Member, present
SC
Councillor Simon CliffordCommittee Member, present
SR
Councillor Steve RobinsonCommittee Member, present
CS
Councillor Clare SuttonCommittee Member, present
GT
Councillor Gill TaylorCommittee Member, present
BW
Councillor Ben WilsonCommittee Member, present
SD
Susan DallisonOfficer, expected
SC
Sean CremerOfficer, in attendance

All 51 on the meeting page

On this subject at Dorset

Search all
  1. Dorset History Centre - approval sought to proceed with development of capital projectThis decision
  2. Dorset History Centre - Capital Project UpdateDecided
  3. Dorset History Centre - Capital Project UpdateDecided
  4. Dorset History Centre - Capital Project UpdateAgreed

More from Dorset Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 July 2026 (period 4) financial management report 26/27Decision (a) That the Senior Leadership Team’s forecast as of July 2026 including progress in addressing demand for s... Noted Open
8 Sep 2026 Additional Procurement Pipeline Report - over £500k (2026 - 27) and Modern Slavery Transparency Statement 2025 - 2026Decision (a) Cabinet considered the contents of the report (of 8 September 2026) in respect of proposed additional mo... Approved Open
8 Sep 2026 Exempt BusinessDecision That the press and the public be excluded for the following item(s) in view of the likely disclosure of exem... Decided Open
28 Jul 2026 Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ... Noted Open
28 Jul 2026 Dorset Local Visitor Economy Partnership Destination Management Plan(a) That the Dorset Local Visitor Economy Partnership Destination Management Plan (DLVEPDM) be adopted and (b) That a... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies