Procurement - Dorset Highways Contractor Resource (Labour Top up) Framework

Decided Executive 1 paper

AI summaryDorset Council Cabinet raises the estimated total value of the Highways Contractor Resource Labour Top-up Framework from £20m to £60m over its 8-year term, to correct a drafting error and keep spending within procurement rules.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedReplaces £20m with £60m over 8-year term
Money£60mRevised framework total, up from £20m
What happens nextTender to be issuedCorrection required before tender goes to market
Who it affectsDorset Highways and BCP CouncilBCP Council continues as named user

What was decided

Replace the 'Estimated DC Total Spend over Contract Term' figure of £20m in Appendix 1 to the 12 March 2024 Cabinet report with £60m, to correct a drafting error in the original paper. Report P7

The amendment is administrative; no expenditure has been incurred and no financial threshold has been reached. Report P7

Why

To ensure compliant spend in line with the Council's Contract Procedure Rules.

The lower approved value would materially constrain the framework and create risks of non-compliance, service interruption, and an unplanned re-procurement exercise. Report P7

What happens next

The tender can be issued to the market once the value has been corrected. Report P7

Any subsequent contract award is delegated to the relevant Portfolio Holder, in consultation with the relevant Executive Director, under the original March 2024 decision. Report 4.3

The money

  • £20m Original estimated DC total spend over the 8-year contract term in Appendix 1 Report P7
  • £60m Revised estimated total spend over the 8-year contract term, covering Dorset Council and BCP Council Report P7
  • £7.5m Estimated annual framework value including BCP Council, allowing for inflation
  • £3.95m Estimated annual Dorset Council share of framework value
  • £3.55m Estimated annual BCP Council share of framework value
  • £31.6m Projected total spend for Dorset Council over the full 8-year term
  • £28.4m Projected total spend for BCP Council over the full 8-year term
  • £500k Threshold above which Cabinet approval is required for procurement activity Report 4.3

Options considered

  • Chosen: Amend the estimated maximum contract value to £60m. Corrects a drafting error, prevents the framework value being reached in under 3 years, and avoids non-compliance and service interruption. Report P7
  • Rejected: Do not amend the estimated maximum contract value. Would materially constrain the framework, risk non-compliance, possible service interruption, and an unnecessary further procurement exercise.

Implications

  • Financial: The framework contract does not commit to any expenditure; there is no guarantee as to the value or volume of work awarded to any supplier, so it can adapt to budget changes.
  • Financial: There is sufficient provision within existing highway maintenance budgets, supported by the confirmed four-year central government funding settlement for 2026 to 2030.
  • Risk: Current risk assessed as Medium due to insufficient numbers of employed staff for critical services such as winter maintenance and safety critical works; residual risk assessed as Low because additional labour can be hired in and off-hired flexibly.
  • Other: Continuing BCP Council's participation as a named user increases framework value and attractiveness to suppliers, and supports Dorset Council in securing central government highway maintenance funding.

Who and where

  • Dorset Highways service, which delivers alongside private sector suppliers through a mixed economy model
  • Bournemouth, Christchurch and Poole Council, proposed to continue as a named user on the framework
  • Private sector suppliers providing supplementary labour such as traffic management operatives, highway maintenance staff, and HGV drivers

Timeline

  • 12 March 2024: Cabinet approved the procurement of the Highways Contractor Resource Labour Top-up Framework as part of the Procurement Forward Plan Report, with an estimated DC total spend of £20m over 8 years. Report P7, 4.3
  • 28 July 2026: Cabinet decision to amend the estimated DC total spend to £60m over the same 8-year term. Report P1
  • 2026 to 2030: Period covered by the confirmed four-year central government funding settlement referenced in the report.
  • 8-year contract term: Overall duration of the framework; scope and duration remain unchanged from the original March 2024 approval. Report P7

Plain English for the jargon

  • DC: Dorset Council
  • BCP Council: Bournemouth, Christchurch and Poole Council, a neighbouring local authority
  • HGV: Heavy Goods Vehicle, a large goods vehicle
  • Framework (agreement): An arrangement with pre-qualified suppliers that allows the council to call off work without re-tendering each time
  • PID / Sourcing Plan: Project Initiation Document and sourcing plan listed as background papers
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item41

Resolved

That the ‘Estimated DC Total Spend over Contract Term’ value of £20m as set out in Appendix 1 to the Cabinet report of 12 March 2024 be replaced with a value of £60m. Reason for the decision To ensure compliant spend in line with the Council’s Contract Procedure Rules.
Word for word from the decision Dorset published for this meeting. Source: moderngov.dorsetcouncil.gov.uk

Follow this further

Built from Dorset's papers

What the report saysPro

Report to Cabinet

Cabinet 28 July 2026 Procurement - Dorset Highways Contractor Resource (Labour Top up) Framework For Decision Cabinet Member: Cllr J Andrews, Place Services

Local Councillor(s): All Councillors

Senior Leadership Team: J Britton - Executive Director, Economy and Environment

Report author and job title: David Blackburn, Waste and Recycling Manager; Highways, Engineering and Transport Email: [email protected]

Statutory Authority:

Report status: Public (the exemption paragraph is N/A)

1. Executive summary Re-procurement of the Highways Contractor Resource (Labour Top up) was approved by Cabinet as part of the Procurement Forward Plan Report considered at its meeting on 12 March 2024. Cabinet agreed to begin each of the procurement procedures, as listed at Appendix 1 to the Cabinet report of 12 March 2024. The table set out in the Appendix erroneously set the ‘Estimated DC Total Spend over Contract Term’ value at £20million over an 8-year contract term. This report seeks Cabinet’s approval to amend the ‘Estimated DC Total Spend over Contract Term’ value in Appendix 1 of this report from £20m to £60m over the same 8-year contract period as the previous decision could have the unintended effect of materially constraining the use of the framework and creates risks of non- compliance, interruption to service provision, and the need for an unplanned re- procurement exercise. The amendment is required to correct a drafting error in the original report and is necessary to ensure the procurement documentation accurately reflects the intended scope and value of the framework. This correction must be made before the tender can be issued to the market and is not related to any expenditure having been incurred or any financial threshold being reached. 2. Recommendation 2.1 That the ‘Estimated DC Total Spend over Contract Term’ value of £20m in Appendix 1 to the Cabinet report of 12 March 2024 be replaced with a value of £60m. 3. Reason for the recommendation(s) 3.1 To ensure compliant spend in line with the Council’s Contract Procedure Rules.

4. The report 4.1 At its meeting on TUESDAY 12 MARCH 2024 the Cabinet Member for Finance, Commercial and Capital Strategy presented a report seeking Cabinet’s consideration of the contents of the report in respect of proposed over £500k procurement activity for 2024-25 that are listed in Appendix 1 and to agree to begin each of the procurement procedures listed in Appendix 1 to the Report. 4.2 Appendix 1 to the Report was as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement: Dorset Highways Contractor Resource (Labour Top up) FrameworkReport 295 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 51 attended
NI
Councillor Nick IrelandChair, present
RB
Councillor Richard BiggsVice-Chair, present
JA
Councillor Jon AndrewsCommittee Member, present
SB
Councillor Shane BartlettCommittee Member, present
MB
Councillor Matt BellCommittee Member, present
SC
Councillor Simon CliffordCommittee Member, present
SR
Councillor Steve RobinsonCommittee Member, present
CS
Councillor Clare SuttonCommittee Member, present
GT
Councillor Gill TaylorCommittee Member, present
BW
Councillor Ben WilsonCommittee Member, present
SD
Susan DallisonOfficer, expected
SC
Sean CremerOfficer, in attendance

All 51 on the meeting page

On this subject at Dorset

Search all
  1. Procurement - Dorset Highways Contractor Resource (Labour Top up) FrameworkThis decision
  2. Officer delegation decision for procurement of Gigabit hub Connectivity in Rural Dorset (GHCiRD)Agreed
  3. Dorset Council Procurement Strategy 2020 - 2022Approved
  4. Christchurch and East Dorset Procurement Action PlanNoted

More from Dorset Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 July 2026 (period 4) financial management report 26/27Decision (a) That the Senior Leadership Team’s forecast as of July 2026 including progress in addressing demand for s... Noted Open
8 Sep 2026 Additional Procurement Pipeline Report - over £500k (2026 - 27) and Modern Slavery Transparency Statement 2025 - 2026Decision (a) Cabinet considered the contents of the report (of 8 September 2026) in respect of proposed additional mo... Approved Open
8 Sep 2026 Exempt BusinessDecision That the press and the public be excluded for the following item(s) in view of the likely disclosure of exem... Decided Open
28 Jul 2026 Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ... Noted Open
28 Jul 2026 Dorset Local Visitor Economy Partnership Destination Management Plan(a) That the Dorset Local Visitor Economy Partnership Destination Management Plan (DLVEPDM) be adopted and (b) That a... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies