Resolved
that the Housing Review Board note the progress made in the mobilisation of the new contract with confirmation that the new contracting arrangements wold begin on 1 July 2019.
Housing Overview and Scrutiny Committee (formerly Housing Review Board) noted this item on Thursday 20 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
that the Housing Review Board note the progress made in the mobilisation of the new contract with confirmation that the new contracting arrangements wold begin on 1 July 2019.
Integrated Asset Management Contract; July 2019- July 2020
www.eastdevon.gov.uk A new dawn….
Current contracts coming to an end The opportunity to review and design a new service
www.eastdevon.gov.uk The journey so far…..
September 2016 In depth review of current service commenced
June 2017 HRB recommended the adoption of an outsourcing model
January 2018 Procurement commenced
September 2018 Contract awarded
November 2018 Mobilisation commenced
July 2019 Start of new contracting arrangement with Ian Williams Ltd
www.eastdevon.gov.uk Drivers for change
Better value for money
Improving Better IT communication integration
Improved 2 contractors= appointment inconsistencies system
Culture of ‘right first time’
www.eastdevon.gov.uk The options
• Outsourcing V Wholly owned subsidiary ( WOS) • Careful consideration of advantages and disadvantages to both, detailed SWOT ( strengths, weaknesses, opportunities and threats) in the June 2017 paper of the housing review board • Significant risks involved with WOS, limited financial benefits as a Local Authority • Size of our stock, relatively small compared to some who have gone down this route making this potentially an unattractive route for bidders • Current contracting arrangements have served us well over a number of years • Good levels of customer satisfaction
www.eastdevon.gov.uk The model
• Single provider • Formal partnering contract (TPC2005) • Contract with minimum term of 10 years • Initially all day to day repairs, void management and servicing • Introduction of price per property and price per void model • Incentivised commercial model- adding planned/cyclical work • A new void specification and associated costs target • A robust customer satisfaction survey process • Appointments made for all repairs at first point of contact- text message alerts • Weekend slots • A renewed ‘right first time’ assessment with a fix and stay fixed requirement • Introduction of a complete property service model – contractor undertakes an annual physical check of all ‘working’ components and structure of property (MOT) • Introduction of new suite of KPIs (key performance indicators) • Handyperson scheme • Customer portal • Co-location- One team!
www.eastdevon.gov.uk The Procurement process
• Established a project team to drive and manage the process • Assistance from Devon County Council procurement team and Echelon Consultancy • Form of procurement; Competitive procedure with Negotiation • 3 stage evaluation process • Two bidders day • Bidders scored: 60% on Quality, 40% on price • 7 companies submitted a bid ( 24 registered an interest) • 3 taken through to final round • 7 areas of scrutiny..
www.eastdevon.gov.uk Project Delivery
Performance ICT management
Health and Social Value Safety
Customer Cost control Care www.eastdevon.gov.uk Competitive Procedure with Negotiation
OJEU Notice SSQ (Standard issued Selection (including all Questionnaire) tender documents) (30 days)
Award without ISIT ISIT Bidders ISIT (Invitation SSQ negotiation Evaluations Briefing to submit initial Evaluations tender) (30 days) (approx. 6 Tenderers)
Shortlist Negotiation Negotiation Negotiation Negotiations Stage 1 Stage 2 Stage 3 Document (can reduce Review (minimum 3 Tenderers after tenderers) each stage)
ISFT ISFT ISFT Issue ISFT Prepare ISFT Final Selection Evaluations Clarifications (Invitation to Report (responded to submit final atleast 6 days before submission) tender)
Standstill Contract Mobilisation Contract Period Award Stage Start
www.eastdevon.gov.uk The winning bid
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
1 Integrated Asset management contractAppendix e | 172 KB | Download |
PDF |
IAMC HRB June 2019Report | 1.7 MB | DownloadRead as text |
PDF |
Integrated asset management contract updateReport | 209 KB | Download |
Follow Housing Overview and Scrutiny Committee (formerly Housing Review Board) at East Devon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Apr 2026 | Forward planto note the Housing Review Board forward plan. | Noted | Open |
| 30 Apr 2026 | Finance reportthat the initial variances identified in the revenue and capital monitoring process be noted. | Noted | Open |
| 30 Apr 2026 | Housing complaints - performance report 2025-26 (Q4)that the Housing Review Board note the content ... view the full minutes text for item 108. | Noted | Open |
| 30 Apr 2026 | Tenancy services - performance report 2025-26 (Q4)that the housing performance report – tenancy services quarter 4 (2025/26) is ... view the full minutes text for item... | Decided | Open |
| 22 Jan 2026 | Housing Review Board forward planTo note the Housing Review Board forward plan. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.