East Devon District Council
Cabinet, Wednesday 10 July 2019 at 5.30pm

Long Lane Enhancement Scheme

Agreed Executive 3 papers

Cabinet agreed this item on Wednesday 10 July 2019. Below is the council's own wording, with the papers it was decided on.

Item30

Resolved

RESOLVED : that the scope of the Long Lane enhancement scheme was reduced to delete the section between the Flybe Training Academy and Harrier Court, be agreed. REASON: To adequately manage the risk associated with securing financial contributions towards the enhancement scheme and to protect the Council’s position.
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to Cabinet

Report to: Cabinet Date of Meeting: 10 July 2019 Public Document: Yes Exemption: None

Review date for None release

Subject: Long Lane Enhancement Scheme

Purpose of report: To provide an update on progress with securing financial contributions towards the Long Lane enhancement scheme. To recommend a reduction to the extent of the scheme to reflect a change in the risk profile associated with the works It is recommended that the scope of the Long Lane enhancement Recommendation: scheme is reduced to delete the section between the Flybe Training Academy and Harrier Court.

Reason for To adequately manage the risk associated with securing financial recommendation: contributions towards the enhancement scheme and to protect the Council’s position. Officer: Andy Wood, [email protected], 01395 571743 Financial This report recommends an appropriate approach to deal with the implications: financial risk highlighted in the report. The net funding for this scheme will be met from Enterprise Zone receipts as previously agreed by Council. Legal implications: The report does not alter the overall legal position which was commented on in the report to Cabinet in March 2019 when the decision to proceed was taken. Legal have been involved in the discussions on the security arrangements and have advised of the need to ensure security (of some description) given the potential risk to the Council. Given that this appears incapable of satisfactory resolution, the solution is to lower the total project cost and thereby the associated risk profile to the Council. This seems a pragmatic approach in terms of moving the project forward (albeit not desirable) and is entirely lawful. Otherwise the legal advice remains as per the March 2019 Cabinet report. Equalities impact: Low Impact Risk: High Risk This report seeks to address a specific risk to the Council, namely the ability to secure a financial contribution towards the Long Lane enhancement scheme. The report outlines a change in the risk profile for the project and recommends a course of action that will effectively mitigate this. Links to background Cabinet Paper – March 2019 information: Link to Council Plan: Developing an outstanding local economy Report in full 1. Background

1.1Long Lane runs in an east/west direction to the south of Exeter Airport. It connects to the B3184 and provides the main point of access to the Airport, Flybe Hangar and Training Academy and the Airport Hotel. When travelling in an easterly direction the Lane quickly narrows to below the standard (6.5m) needed to accommodate the two way flow of HGV traffic. This includes substantial stretches of single carriageway. The inadequate nature of the current highway is a major barrier to bringing forward the Airpark Enterprise Zone site.

1.2The Cabinet received a paper in March 2019 which set out a proposal for funding an enhancement and upgrading scheme for the Lane. This comprised of three main sections including the stretch to the east of the Flybe Training Academy towards Harrier Court. This was itself connected with the need to provide enhanced access for the convertor station for the proposed France-Alderney-Britain Link project. The proposals and estimated costs are set out in the plan in Appendix A and also illustrated in aerial form in Appendix B.

1.3Cabinet resolved to make up to £3m available to fund the enhancement scheme. This was subject to securing contributions from both the Airpark (£300k) and FAB (£670k) projects. Delegation was approved to the Chief Executive in consultation with the Leader and Strategic Leads for Finance and Governance and Licensing to agree the terms and complete the funding agreement and any other necessary legal documentation.

2. Current Position

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Long Lane Enhancement SchemeReport 159 KB DownloadRead as text
PDF
Long Lane Scheme Map Appendix AAppendix 2.5 MB Download
PDF
Long Lane photo Appendix BAppendix 707 KB Download

At this meeting

Whole meeting

Who was there

9 of 36 attended
BI
Councillor Ben InghamChairman, present
MA
Councillor Megan ArmstrongCommittee Member, present
JB
Councillor Jess BaileyCommittee Member, present
KB
Councillor Kevin BlakeyCommittee Member, present
PF
Councillor Peter FaithfullCommittee Member, present
GJ
Councillor Geoff JungCommittee Member, present
PM
Councillor Paul MillarCommittee Member, present
GP
Councillor Geoff PookCommittee Member, present
IT
Councillor Ian ThomasCommittee Member, present
RC
Richard CohenOfficer, in attendance
AC
Amanda CoombesOfficer, in attendance
SD
Simon DaveyOfficer, in attendance

All 36 on the meeting page

On this subject at East Devon

Search all
  1. Long Lane Enhancement SchemeThis decision
  2. Local Development Order for Land off Long LaneApproved
  3. Long Lane Enhancement SchemeApproved
  4. Long Lane Enhancement SchemeAgreed
  5. Long Lane EnhancementNoted

More from East Devon Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 LGR in Devon: Government Decision and Implications for EDDCRESOLVED that Cabinet: 1. Notes the Government’s July decision and the subsequent review 2. Notes the concerns regard... Agreed Open
16 Sep 2026 Financial Strategy 2027 - 2029RESOLVED that Cabinet : 2. Agrees that the 2027/28 budget process should continue to be developed within the principl... Agreed Open
16 Sep 2026 Financial Monitoring Report and Annual Treasury Management Review 2025/26RESOLVED that Cabinet: Acknowledge the variances identified as part of the Revenue and Capital Monitoring process up ... Approved Open
16 Sep 2026 Woodbury Neighbourhood Plan to be formally 'made'RESOLVED that Cabinet: 1. Agree that the Woodbury Parish Neighbourhood Plan be ‘made’. 2. Note that once made the Pla... Agreed Open
16 Sep 2026 Green Team Project Standing Order ExemptionRESOLVED that Cabinet: 1. Notes and supports the exemption to Contract Standing Orders under the provision relating t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies