Long Lane Enhancement Scheme

Agreed Executive 2 papers

Cabinet agreed this item on Wednesday 4 March 2020. Below is the council's own wording, with the papers it was decided on.

Item157

Resolved

that the spend of £2.55m for the Long Lane Enhancement works to be funded through the Enterprise Zone programme, be agreed. REASON: To enable the Long Lane Enhancement works to be implemented.
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to Cabinet

Report to: Cabinet Date of Meeting: 4 March 2020 Public Document: Yes Exemption: None Review date for None release

Subject: Long Lane Enhancement Scheme

Purpose of report: To seek final budgetary approval for the Long Lane Enhancement works.

Recommendation: That Cabinet agree a budget of £2.55m for the Long Lane Enhancement works to be funded through the Enterprise Zone programme

Reason for To enable the Long Lane enhancement works to be implemented. recommendation:

Officer: Andy Wood, tel 01395 571743, email [email protected]

Portfolio Holder: Portfolio Holder for Finance Financial Council has approved £8m of borrowing for projects to facilitate implications: economic growth in the Enterprise Zone with funding to come from ring fenced EZ business rate income. Detailed approval of schemes within this sum were to be approved by Cabinet.

In line with this approval Cabinet agreed a £3m spend on Long Lane Enhancement scheme with contributions to be secured of £970k (£300k Airpark and £670k FAB) giving a net spend of £2.03m. The scheme was subsequently scaled down because of the inability to secure the FAB funding, this was approved by Cabinet with a reduction in spend of £1.4m, but with no FAB contribution of £670k, giving a net budget of £1.3m.

This report updates the costs involved in delivering the scaled down project to £2.55m which after deducting £300k Airpark contribution gives a revised net cost budget of £2.25m which Cabinet are being asked to approve.

Legal implications: The report does not alter the overall legal position which was commented on in the reports to Cabinet of March and July 2019. As detailed, the outcome of the first report was a decision to proceed with the enhancement works but the second report agreed to revise the works and reduce the overall projects costs to minimise potential risk. Notwithstanding that, the costs have now risen for the reasons set out and it is therefore necessary to obtain Cabinet’s agreement to the revised spend which remains within the overall approved budget. Otherwise there are no specific legal implications requiring comment and the legal advice in relation to the project remains as per the March 2019 and July 2019 Cabinet reports. Equalities impact: Low Impact Climate change: High Impact The works will help to create a public transport loop and cycleway which will serve a major employment area. This will help to reduce reliance on the private car and promote sustainable modes of travel.

Risk: Medium Risk The County Council are leading the delivery of the scheme including procuring contractors. Residual risks in relation to landownership and drainage are being managed by the County Council. Links to background Cabinet March 2019 Item 19 information: Cabinet July 2019 item 14

Link to Council Plan: Outstanding Economic Growth, Productivity and Prosperity Outstanding Council and Council Services.

Background 1.1 Long Lane runs in an east/west direction immediately to the south of Exeter Airport. It connects to the B3184 and provides the main point of access to the Airport, Flybe Hangar and Training Academy and the Airport Hotel. When travelling in an easterly direction the Lane quickly narrows to below the standard (6.5m) needed to accommodate the two way flow of HGV traffic. This includes substantial stretches of single carriageway. The inadequate nature of the current highway is a major barrier to bringing forward the Airpark Enterprise Zone site.

1.2Cabinet received a paper in March 2019 which set out a proposal for funding an enhancement and upgrading scheme for the Lane. This comprised of three main sections and included the stretch to the east of the Flybe Training Academy towards Harrier Court. This was itself connected with the need to provide enhanced access for the convertor station for the proposed France-Alderney-Britain Link project. The proposals are illustrated in plan form in Appendix A.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Long Lane Appendix AAppendix 860 KB Download
PDF
Long Lane Enhancement SchemeReport 173 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 29 attended
BI
Councillor Ben InghamChairman, present
MA
Councillor Megan ArmstrongCommittee Member, apologies
JB
Councillor Jess BaileyCommittee Member, present
KB
Councillor Kevin BlakeyCommittee Member, present
PF
Councillor Peter FaithfullCommittee Member, present
GJ
Councillor Geoff JungCommittee Member, present
GP
Councillor Geoff PookCommittee Member, present
IT
Councillor Ian ThomasCommittee Member, present
RC
Richard CohenOfficer, in attendance
HG
Henry Gordon LennoxOfficer, in attendance
JG
John GoldingOfficer, in attendance
KS
Karen SimpkinOfficer, in attendance

All 29 on the meeting page

On this subject at East Devon

Search all
  1. Long Lane Enhancement SchemeThis decision
  2. Local Development Order for Land off Long LaneApproved
  3. Long Lane Enhancement SchemeApproved
  4. Long Lane Enhancement SchemeAgreed
  5. Long Lane EnhancementNoted

More from East Devon Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 LGR in Devon: Government Decision and Implications for EDDCRESOLVED that Cabinet: 1. Notes the Government’s July decision and the subsequent review 2. Notes the concerns regard... Agreed Open
16 Sep 2026 Financial Strategy 2027 - 2029RESOLVED that Cabinet : 2. Agrees that the 2027/28 budget process should continue to be developed within the principl... Agreed Open
16 Sep 2026 Financial Monitoring Report and Annual Treasury Management Review 2025/26RESOLVED that Cabinet: Acknowledge the variances identified as part of the Revenue and Capital Monitoring process up ... Approved Open
16 Sep 2026 Woodbury Neighbourhood Plan to be formally 'made'RESOLVED that Cabinet: 1. Agree that the Woodbury Parish Neighbourhood Plan be ‘made’. 2. Note that once made the Pla... Agreed Open
16 Sep 2026 Green Team Project Standing Order ExemptionRESOLVED that Cabinet: 1. Notes and supports the exemption to Contract Standing Orders under the provision relating t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies