CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
East Devon District Council
Planning Committee, Wednesday 6 January 2021 at 10.00am

20/2089/MFUL (Major) BUDLEIGH AND RALEIGH

Approved Planning 1 paper

Planning Committee approved this item on Wednesday 6 January 2021. Below is the council's own wording, with the papers it was decided on.

Item189

Resolved

Approved as per Officer recommendation but with the following additional conditions: 1. Prior to the commencement of development, and following consultation with the affected residents of Frogmore Road as identified by the Local Planning Authority, details of any additional mitigation works and future monitoring to protect residents of Frogmore Road from flooding as a result of the proposal hereby approved shall have been submitted to the Local Planning Authority for approval. Thereafter the development shall be carried out in full accordance with the approved details. Reason: In order to protect the amenity of residents from flood risk in accordance with Policies D1 (Design and Local Distinctiveness) and EN21 (River and Coastal Flooding) of the East Devon Local Plan 2013-2031. 2. Prior to commencement of development, a Landscape and Ecological Management Plan (LEMP) shall be submitted to the local planning authority for its approval. This shall establish site objectives and management prescriptions to deliver mitigation and enhancement measures and include provision for: a) Mitigation and management of retained habitats during the pre-construction, construction and post construction phases of the development. b) Creation and management of new habitats during the construction and post construction phases of the development. c) Mitigation for legally protected and notable species during the pre-construction, construction and post construction phases of the development. Once approved the pre-construction, construction and operation of the development shall proceed in accordance with the approved details of the LEMP, unless otherwise approved in writing by the local planning authority and retained thereafter in accordance with the approved details Reason: In order to protect and enhance habitat in accordance with Policy EN5 (Wildlife Habitats and Features) of the East Devon Local Plan 2013-2031. 3. A comprehensive habitat monitoring plan shall be submitted to and approved in writing by the local planning authority prior to commencement of development. It shall show the following measures to be agreed: The methodology and monitoring of new inter-tidal areas for establishment of saltmarsh and mudflat habitat. The monitoring of impacts on the Otter Estuary SSSI and predicted changes to the MCZ as a result of natural erosion processes in the existing estuary and mouth. Reason: In order to conserve the biodiversity and geodiversity of these protected habitats and landscapes in accordance with Strategy 47 (Nature Conservation and Geology) of the East Devon Local Plan 2013-2031. 4. Prior to commencement of development, further details showing how ... view the full minutes text for item 189.
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to Planning Committee

Executive summary

This application is before members as the officer recommendation is contrary to the views of the parish councils.

This is an application for the restoration of the historic floodplain of the lower Otter river and creation of intertidal saltmarsh, mudflats and freshwater habitat, together with the realignment of South Farm Road, creation of a new car park and new footbridge. The application is accompanied by an environmental statement which assesses impact on habitat, ecology, flood risk, archaeology, landscape and conservation.

The application has been widely consulted on and statutory bodies are generally supportive of the proposal.

Although the purpose of the scheme is to allow the river at this point to be inundated with water, both from the river and the sea, the flood risk assessment and flood modelling results indicate that in fluvial events there will be a reduction in flood depth throughout the study area for all modelled flood events.

20/2089/MFUL A thorough review of the FRA by the Environment Agency (independent of the project team) found that flood risk will not be detrimental for third parties. Concerns have been raised regarding the positioning and size of the proposed car park; the highway authority would like this to include more car parking spaces and connect by footpath along South Farm Road. Concerns were also raised regarding the consultation process, both in terms of prior consultation undertaken by the applicant and the timing of site notices.

The impacts on trees, local landscape, the setting of heritage assets, use of the estuary and contamination have all been addressed.

It is considered that the proposal is acceptable subject to appropriately worded conditions relating to archaeology, materials of the footbridge, access details and public rights of way, contamination, a construction management plan, groundwater levels, adequate car parking, the provision of a footpath, arboricultural and tree protection details.

CONSULTATIONS

Local Consultations

Budleigh Salterton Town Council

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20/2089/MFUL (Major) BUDLEIGH AND RALEIGHReport 1 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 32 attended
EW
Councillor Eileen WraggChair, present
SC
Councillor Sarah ChamberlainVice-Chair, present
KB
Councillor Kim BloxhamCommittee Member, present
CB
Councillor Colin BrownCommittee Member, apologies
AC
Councillor Andrew ColmanCommittee Member, present
OD
Councillor Olly DaveyCommittee Member, present
BD
Councillor Bruce De SaramCommittee Member, present
SG
Councillor Steve GazzardCommittee Member, present
MH
Councillor Mike HoweCommittee Member, present
DK
Councillor David KeyCommittee Member, present
KM
Councillor Kathy McLauchlanCommittee Member, present
GP
Councillor Geoff PookCommittee Member, present

All 32 on the meeting page

On this subject at East Devon

Search all
  1. 20/2089/MFUL (Major) BUDLEIGH AND RALEIGHThis decision
  2. 26/0535/MFUL (Major) WHIMPLE & ROCKBEAREApproved
  3. 25/0965/MFUL (Major) WHIMPLE & ROCKBEARERefused
  4. 24/0841/MFUL (Major) HONITON ST PAULSRefused
  5. 25/2397/MFUL (Major) & 25/2398/LBC EXMOUTH TOWNApproved
  6. 25/1259/MFUL (Major) HONITON ST MICHAELSApproved

More from East Devon Planning Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 25/2471/MRES (Major) CRANBROOKApproved with conditions in accordance with officer recommendation. Approved Open
1 Sep 2026 26/1143/PIP (Other) CLYST VALLEYThe Appropriate Assessment be adopted. 2. Permission in Principle be approved. Approved Open
1 Sep 2026 26/0854/FUL (Minor) BROADCLYSTApproved with conditions in accordance with officer recommendation. Approved Open
1 Sep 2026 26/0534/MOUT (Major) WHIMPLE & ROCKBEAREThe Appropriate Assessment be adopted. 2. Approved with conditions in accordance with officer recommendation subject ... Approved Open
1 Sep 2026 26/0535/MFUL (Major) WHIMPLE & ROCKBEAREThe Appropriate Assessment be adopted. 2. That the SANGS application be approved, subject to conditions and to the co... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies