That the carrying out of emergency (and potentially permanent) repairs to Exmouth seafront and delegated authority be given to the Director of Housing Health and Environment in respect of the project, in consultation with the Director of Finance and the Director of Governance and Licensing, be approved. 2. Given the emergency nature of the works, the exemption to contract standing orders in respect of the consultancy spend for the sum of £60,000 has been approved by S151 Officer and Monitoring Officer as provided for in the Constitution, be noted. 3. That the exemption to contract standing orders in the sum of £1.1m in respect of the awarding of the contract in respect of the construction works for repairs to the sea wall, be approved. RECOMMENDED to Council: 4. That the sum of up to £1.1m is allocated to the project to carry out emergency works to Exmouth Seafront; such works may also act as the permanent solution. It is noted that external contributions may be received which may reduce the spend. REASON: Given the location of the failed and failing wall, it was not an option to do nothing and allow the sea to erode the seafront further. Therefore, the most cost-effective option (option C) had been selected to proceed as it would restore the sea defence and reduce impact on public and businesses and allow options going forward for aesthetic improvements if required by planning conditions. Meeting adjourned at 8.05pm for a 10 minute comfort break. The meeting recommenced at 8.15pm
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Date of Meeting 29th November 2023 Document classification: Part A Public Document Exemption applied: None Review date for release N/A
Exmouth Sea Wall Emergency Repairs Budget Report summary: Report to outline emergency repairs to Exmouth Seawall, highlight ongoing risks and seek authority for the council to spend up to £1.1m to carry out an emergency repair which could also act as the permanent solution
Is the proposed decision in accordance with: Budget Yes ☐ No ☒ Policy Framework Yes ☒ No ☐ Recommendation: 1. That cabinet approves the carrying out of emergency (and potentially permanent) repairs to Exmouth seafront and grants delegated authority to the Director of Housing Health and Environment in respect of the project, in consultation with the Director of Finance and the Director of Governance and Licensing. 2. That cabinet recommends to council that the sum of up to £1.1m is allocated to the project to carry out emergency works to Exmouth Seafront; such works may also act as the permanent solution. It is noted that external contributions may be received which may reduce the spend. 3. Given the emergency nature of the works, Cabinet notes the exemption to contract standing orders in respect of the consultancy spend for the sum of £60,000 has been approved by S151 Officer and Monitoring Officer as provided for in the Constitution. 4. Cabinet approves the exemption to contract standing orders in the sum of £1.1m in respect of the awarding of the contract in respect of the construction works for repairs to the sea wall
Reason for recommendation: Given the location of the failed and failing wall, it is not an option to do nothing and allow the sea to erode the seafront further. Therefore, the most cost effective option (option C) has been selected to proceed as it will restore the sea defence and reduce impact on public and businesses and allow options going forward for aesthetic improvements if required by planning conditions.
Portfolio(s) (check which apply): ☒ Climate Action and Emergency Response ☒ Coast, Country and Environment ☐ Council and Corporate Co-ordination ☐ Communications and Democracy ☐ Economy ☐ Finance and Assets ☐ Strategic Planning ☐ Sustainable Homes and Communities ☐ Culture, Leisure, Sport and Tourism
Equalities impact Medium Impact Damaged wall is currently impeding a section of the long flat Exmouth seawall walk. Repairing the wall will restore this important link. Climate change High Impact Risk: High Risk; Works are required likely due to climate change. Links to background information Exemption to contract standing orders – Consultant Link to Council Plan Priorities (check which apply) ☒ Better homes and communities for all ☐ A greener East Devon ☒ A resilient economy
Report in full 1. Background 1.1. In late August, EDDC engineers were made aware of cracks in the seawall in front of the Sideshore development, and appointed Moffatt and Nichol to gain all the required permissions to carry out trial holes and carry out investigations. 1.2. However, a storm over the weekend of 28 th/29th October significantly dropped beach levels and caused the wall to crack and slump, putting the wall at serious risk of collapse. 1.3. Emergency works were completed in the following days to shore up the wall through the next storm, with the wall surviving. Due to limited time, the works consisted of concrete blocks placed at the base of the wall, and lots of sand being placed on the wall. This kept the wall intact. 1.4. Following the storm, a large void opened out in the old lifeboat slipway and required fixing to enable access to the beach. 1.5. Further blocks and sand are being placed prior to the next set of high tides, and this activity may need to be repeated throughout the winter. ] Image 1.5. Wall damage and temporary repairs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.