East Devon District Council
Cabinet, Wednesday 29 November 2023 at 6.00pm

Exmouth Sea Wall Emergency Repairs Budget

Approved Executive 1 paper

Cabinet approved this item on Wednesday 29 November 2023. Below is the council's own wording, with the papers it was decided on.

Item90

Resolved

That the carrying out of emergency (and potentially permanent) repairs to Exmouth seafront and delegated authority be given to the Director of Housing Health and Environment in respect of the project, in consultation with the Director of Finance and the Director of Governance and Licensing, be approved. 2. Given the emergency nature of the works, the exemption to contract standing orders in respect of the consultancy spend for the sum of £60,000 has been approved by S151 Officer and Monitoring Officer as provided for in the Constitution, be noted. 3. That the exemption to contract standing orders in the sum of £1.1m in respect of the awarding of the contract in respect of the construction works for repairs to the sea wall, be approved. RECOMMENDED to Council: 4. That the sum of up to £1.1m is allocated to the project to carry out emergency works to Exmouth Seafront; such works may also act as the permanent solution. It is noted that external contributions may be received which may reduce the spend. REASON: Given the location of the failed and failing wall, it was not an option to do nothing and allow the sea to erode the seafront further. Therefore, the most cost-effective option (option C) had been selected to proceed as it would restore the sea defence and reduce impact on public and businesses and allow options going forward for aesthetic improvements if required by planning conditions. Meeting adjourned at 8.05pm for a 10 minute comfort break. The meeting recommenced at 8.15pm
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to Cabinet

Report to: Cabinet

Date of Meeting 29th November 2023 Document classification: Part A Public Document Exemption applied: None Review date for release N/A

Exmouth Sea Wall Emergency Repairs Budget Report summary: Report to outline emergency repairs to Exmouth Seawall, highlight ongoing risks and seek authority for the council to spend up to £1.1m to carry out an emergency repair which could also act as the permanent solution

Is the proposed decision in accordance with: Budget Yes ☐ No ☒ Policy Framework Yes ☒ No ☐ Recommendation: 1. That cabinet approves the carrying out of emergency (and potentially permanent) repairs to Exmouth seafront and grants delegated authority to the Director of Housing Health and Environment in respect of the project, in consultation with the Director of Finance and the Director of Governance and Licensing. 2. That cabinet recommends to council that the sum of up to £1.1m is allocated to the project to carry out emergency works to Exmouth Seafront; such works may also act as the permanent solution. It is noted that external contributions may be received which may reduce the spend. 3. Given the emergency nature of the works, Cabinet notes the exemption to contract standing orders in respect of the consultancy spend for the sum of £60,000 has been approved by S151 Officer and Monitoring Officer as provided for in the Constitution. 4. Cabinet approves the exemption to contract standing orders in the sum of £1.1m in respect of the awarding of the contract in respect of the construction works for repairs to the sea wall

Reason for recommendation: Given the location of the failed and failing wall, it is not an option to do nothing and allow the sea to erode the seafront further. Therefore, the most cost effective option (option C) has been selected to proceed as it will restore the sea defence and reduce impact on public and businesses and allow options going forward for aesthetic improvements if required by planning conditions.

Officer: Tom Buxton- Smith, Engineering Projects Manager. [email protected] 01395 571630

Portfolio(s) (check which apply): ☒ Climate Action and Emergency Response ☒ Coast, Country and Environment ☐ Council and Corporate Co-ordination ☐ Communications and Democracy ☐ Economy ☐ Finance and Assets ☐ Strategic Planning ☐ Sustainable Homes and Communities ☐ Culture, Leisure, Sport and Tourism

Equalities impact Medium Impact Damaged wall is currently impeding a section of the long flat Exmouth seawall walk. Repairing the wall will restore this important link. Climate change High Impact Risk: High Risk; Works are required likely due to climate change. Links to background information Exemption to contract standing orders – Consultant Link to Council Plan Priorities (check which apply) ☒ Better homes and communities for all ☐ A greener East Devon ☒ A resilient economy

Report in full 1. Background 1.1. In late August, EDDC engineers were made aware of cracks in the seawall in front of the Sideshore development, and appointed Moffatt and Nichol to gain all the required permissions to carry out trial holes and carry out investigations. 1.2. However, a storm over the weekend of 28 th/29th October significantly dropped beach levels and caused the wall to crack and slump, putting the wall at serious risk of collapse. 1.3. Emergency works were completed in the following days to shore up the wall through the next storm, with the wall surviving. Due to limited time, the works consisted of concrete blocks placed at the base of the wall, and lots of sand being placed on the wall. This kept the wall intact. 1.4. Following the storm, a large void opened out in the old lifeboat slipway and required fixing to enable access to the beach. 1.5. Further blocks and sand are being placed prior to the next set of high tides, and this activity may need to be repeated throughout the winter. ] Image 1.5. Wall damage and temporary repairs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Exmouth Sea Wall Emergency Repairs BudgetReport 788 KB DownloadRead as text

At this meeting

Whole meeting
72Minutes of the previous meetingOn the agenda 77Minutes of Scrutiny Committee held on 5 October 2023On the agenda 78Minutes of Strata Joint Executive Committee held on 5 October 2023On the agenda 79Minutes of Placemaking in Exmouth Town and Seafront Group held on 7 November 2023On the agenda 80Minutes of Overview Committee held on 12 October 2023On the agenda 81Minutes of Recycling and Waste Partnership Board held on 25 October 2023On the agenda 82Minutes of Arts and Culture Forum held on 8 November 2023On the agenda 83Minutes of Housing Review Board held on 9 November 2023On the agenda 84Minutes of Overview Committee held on 9 November 2023On the agenda 85Review of bin collection service and town and parishes' service chargesAgreed 86Housing Benefit Modified Scheme PolicyAgreed 87Safeguarding update following recommendations from Council 11 July 2023Noted 88Safeguarding Policy update reportDecided 89Homelessness Service updateNoted
90Exmouth Sea Wall Emergency Repairs BudgetThis decision
91Peer challenge update reportNoted 92Car Park Summer Income reportNoted 93Mill Street Reserved Permits & Devon County LEVI (EV) Funding BidDeferred 94Treasury Management Performance 2023/24 - 1 April to 30 September 2023On the agenda 95Financial Monitoring Report 2023/24 - Month 6 September 2023Decided 96Application to designate West Hill Neighbourhood AreaApproved 97Consultation on draft Cemetery RegulationsAgreed 98Local Government (Access to Information) Act 1985 - Exclusion of Press and PublicDecided 99Discretionary Rate Relief (Broadclyst Ward)Private 100Site Acquisition OpportunityPrivate

Who was there

9 of 37 attended
MR
Councillor Marianne RixsonCommittee Member, present
GJ
Councillor Geoff JungCommittee Member, present
DL
Councillor Dan LedgerCommittee Member, apologies
MH
Councillor Matt HallCommittee Member, present
OD
Councillor Olly DaveyCommittee Member, present
SJ
Councillor Sarah JacksonCommittee Member, present
JL
Councillor John LoudounCommittee Member, present
NH
Councillor Nick HookwayCommittee Member, present
PA
Councillor Paul ArnottChair, present
PH
Councillor Paul HaywardVice-Chair, present
TB
Tom Buxton-SmithOfficer, in attendance
RE
Richard EasthopeOfficer, in attendance

All 37 on the meeting page

On this subject at East Devon

Search all
  1. Exmouth Sea Wall Emergency Repairs BudgetThis decision
  2. Recommendation from Cabinet - 4 September 2024: Placemaking in Exmouth Town and Seafront GroupApproved
  3. Engineering Projects Contracts over £100k - Exmouth and SeatonNoted
  4. Exmouth Sea Wall Emergency Repairs Update and Phase 2Approved
  5. Progress Update on Placemaking in Exmouth Town and SeafrontNoted

More from East Devon Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 LGR in Devon: Government Decision and Implications for EDDCRESOLVED that Cabinet: 1. Notes the Government’s July decision and the subsequent review 2. Notes the concerns regard... Agreed Open
16 Sep 2026 Financial Strategy 2027 - 2029RESOLVED that Cabinet : 2. Agrees that the 2027/28 budget process should continue to be developed within the principl... Agreed Open
16 Sep 2026 Financial Monitoring Report and Annual Treasury Management Review 2025/26RESOLVED that Cabinet: Acknowledge the variances identified as part of the Revenue and Capital Monitoring process up ... Approved Open
16 Sep 2026 Woodbury Neighbourhood Plan to be formally 'made'RESOLVED that Cabinet: 1. Agree that the Woodbury Parish Neighbourhood Plan be ‘made’. 2. Note that once made the Pla... Agreed Open
16 Sep 2026 Green Team Project Standing Order ExemptionRESOLVED that Cabinet: 1. Notes and supports the exemption to Contract Standing Orders under the provision relating t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies