Exmouth Sea Wall Emergency Repairs Update and Phase 2

Approved Executive 1 paper

Cabinet approved this item on Wednesday 5 June 2024. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

RESOLVED that Cabinet: 1. Approves the carrying out of further emergency (and permanent) repairs to Exmouth seafront in respect of Phase 1, Phase 2 and associated emergency works and grants delegated authority to the Director of Housing Health and Environment (initially and then to the new Director of Place) in respect of the project, in consultation with the Director of Finance, the Director of Governance and the Portfolio Holder Coast, Country and Environment. 2. Approves total budget spend for the Phase 1 and Phase 2 works of £3.312m. Note no additional budget from EDDC required over the £1.5m already approved. £1.812m obtained from external funding. 3. Supports the recommended option alignment and target start date for Phase 2 seawall repairs. However due to ongoing investigations, the final alignment decision being with the delegated officers as per recommendation 1. 4. Given the emergency nature of the works, Cabinet notes the exemption to contract standing orders in respect of the design consultancy total spend for the sum of £300,000 that has been approved by S151 Officer and Monitoring Officer as provided for in the Constitution. This is an increase from 6th March 2024. 5. Notes the decisions made to date on repairing the slipway. 6. Notes the Outline Business Case submission to the Environment Agency for access to national funding. REASON: Given the location of the failed and failing wall, it was not an option to do nothing and allow the sea to erode the seafront further. Therefore Phase 2 must start in October prior to the winter storms. Starting in October dictates the wall alignment. Further spend and costs have been incurred due to further storms in April.
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to Cabinet

Report to: Cabinet

Date of Meeting 5 June 2024 Document classification: Part A Public Document Exemption applied: None Review date for release N/A

Exmouth Sea Wall Emergency Repairs Update and Phase 2 Report summary: Report to update emergency repairs to Exmouth Seawall phase 1. Report also explains various options for Phase 2 and sets out recommended alignment of phase 2. It also outlines the financial situation and gives an update on the Slipway repairs and cladding options.

Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: 1. That cabinet approves the carrying out of further emergency (and permanent) repairs to Exmouth seafront in respect of phase 1, phase 2 and associated emergency works and grants delegated authority to the Director of Housing Health and Environment (initially and then to the new Director of Place) in respect of the project, in consultation with the Director of Finance and the Director of Governance and Licensing. 2. That cabinet approves total budget spend for the phase 1 and phase 2 works of £3.312m Note no additional budget from EDDC required over the £1.5m already approved. £1.812m obtained from external funding. 3. That cabinet supports the recommended option alignment and target start date for phase 2 seawall repairs. However due to ongoing investigations, the final alignment decision being with the delegated officers as per recommendation 1. 4. Given the emergency nature of the works, Cabinet notes the exemption to contract standing orders in respect of the design consultancy total spend for the sum of £300,000 has been approved by S151 Officer and Monitoring Officer as provided for in the Constitution. This is an increase from 6th March 2024 5. That cabinet notes the decisions made to date on repairing the slipway. 6. That cabinet notes the Outline Business Case submission to the Environment Agency for access to national funding.

Reason for recommendation: Given the location of the failed and failing wall, it is not an option to do nothing and allow the sea to erode the seafront further. Therefore Phase 2 must start in September prior to the winter storms. Starting in September dictates the wall alignment. Further spend and costs have been incurred due to further storms in April.

Officer: Tom Buxton- Smith, Engineering Projects Manager. [email protected] 01395 571630 Portfolio(s) (check which apply): ☒ Climate Action and Emergency Response ☒ Coast, Country and Environment ☐ Council and Corporate Co-ordination ☐ Communications and Democracy ☐ Economy ☐ Finance and Assets ☐ Strategic Planning ☐ Sustainable Homes and Communities ☐ Culture, Leisure, Sport and Tourism

Equalities impact Medium Impact Damaged wall is currently impeding a section of the long flat Exmouth seawall walk. Repairing the wall will restore this important link Climate change High Impact Risk: High Risk; Works are required likely due to climate change . Links to background information Queens Drive Sea Wall Exmouth OBC Link to Council Plan Priorities (check which apply) ☒ Better homes and communities for all ☐ A greener East Devon ☒ A resilient economy

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Exmouth Sea Wall Emergency Repairs Update and Phase 2Report 985 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 31 attended
MR
Councillor Marianne RixsonCommittee Member, present
GJ
Councillor Geoff JungCommittee Member, present
DL
Councillor Dan LedgerCommittee Member, present
SJ
Councillor Sarah JacksonCommittee Member, present
JL
Councillor John LoudounCommittee Member, present
NH
Councillor Nick HookwayCommittee Member, present
SH
Councillor Sam HawkinsCommittee Member, present
PA
Councillor Paul ArnottChair, present
PH
Councillor Paul HaywardVice-Chair, present
TO
Councillor Todd OliveCommittee Member, present
TB
Thea BilleterOfficer, in attendance
TB
Tom Buxton-SmithOfficer, in attendance

All 31 on the meeting page

On this subject at East Devon

Search all
  1. Exmouth Sea Wall Emergency Repairs Update and Phase 2This decision
  2. Recommendation from Cabinet - 4 September 2024: Placemaking in Exmouth Town and Seafront GroupApproved
  3. Engineering Projects Contracts over £100k - Exmouth and SeatonNoted
  4. Exmouth Sea Wall Emergency Repairs BudgetApproved
  5. Progress Update on Placemaking in Exmouth Town and SeafrontNoted

More from East Devon Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 LGR in Devon: Government Decision and Implications for EDDCRESOLVED that Cabinet: 1. Notes the Government’s July decision and the subsequent review 2. Notes the concerns regard... Agreed Open
16 Sep 2026 Financial Strategy 2027 - 2029RESOLVED that Cabinet : 2. Agrees that the 2027/28 budget process should continue to be developed within the principl... Agreed Open
16 Sep 2026 Financial Monitoring Report and Annual Treasury Management Review 2025/26RESOLVED that Cabinet: Acknowledge the variances identified as part of the Revenue and Capital Monitoring process up ... Approved Open
16 Sep 2026 Woodbury Neighbourhood Plan to be formally 'made'RESOLVED that Cabinet: 1. Agree that the Woodbury Parish Neighbourhood Plan be ‘made’. 2. Note that once made the Pla... Agreed Open
16 Sep 2026 Green Team Project Standing Order ExemptionRESOLVED that Cabinet: 1. Notes and supports the exemption to Contract Standing Orders under the provision relating t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies