That the setting up of a Feniton FAS project board as outlined in the report to be able to make swift decisions to aid project completion, be agreed. 2. That the setting up of a Exmouth BMP project board as outlined in the report to be able to make swift decisions to aid project completion, be agreed. REASON: Currently as per the project management policy at EDDC, unless otherwise appointed, SLT act as the project board, responsible for making quick decisions to keep the respective project. SLT meet fortnightly and are not familiar with the project’s details, so a bespoke group able to meet on demand who were familiar with the project’s details would be beneficial for project progress and making swift decisions.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Date of Meeting 3 January 2024 Document classification: Part A Public Document Exemption applied: None Review date for release N/A
Setting up a project Board for Feniton Flood Alleviation Scheme and a project board for the Exmouth Beach Management Plan (BMP) Project Report summary: Feniton Flood alleviation Scheme (FAS) offering improved flood resilience to over 60 properties is due to start on site in 2024. To aid delivery of the project, the report outlines and proposes the setting up of a project board.
Exmouth BMP is a project to study the physical beach and provide recommendations to best manage the beach into the future to maintain sand levels and good amenity value. To aid delivery of the project, the report outlines and proposes the setting up of a project board.
Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: 1) That cabinet agree to the setting up of a Feniton FAS project board as outlined in the report to be able to make swift decisions to aid project completion.
2) That cabinet agree to the setting up of a Exmouth BMP project board as outlined in the report to be able to make swift decisions to aid project completion.
Reason for recommendation: 1) Currently, as per the project management policy at EDDC, unless otherwise appointed, SLT act as the project board, responsible for making quick decisions to keep the respective project. SLT meet fortnightly, and are not familiar with the project’s details, so a bespoke group able to meet on demand who are familiar with the project’s details would be beneficial for project progress and making swift decisions. 2) As above
Portfolio(s) (check which apply): ☒ Climate Action and Emergency Response ☒ Coast, Country and Environment ☐ Council and Corporate Co-ordination ☐ Communications and Democracy ☐ Economy ☐ Finance and Assets ☐ Strategic Planning ☐ Sustainable Homes and Communities ☐ Culture, Leisure, Sport and Tourism
Equalities impact Low Impact Climate change Medium Impact Risk: Medium Risk; There are reputational risks to EDDC Links to background information Feniton FAS Project Board’s roles and responsibilities - Appendix 1 Exmouth BMP Project Board’s roles and responsibilities - Appendix 2 Link to Council Plan Priorities (check which apply) ☐ Better homes and communities for all ☐ A greener East Devon ☒ A resilient economy
Flooding in New Feniton has been an issue since the development was built in the late 1960s; with flooding occurring every year and internal flooding every 2 to 3 years.
The biggest well recorded event was in late October 2008 when there was serious flooding in the main estate. This event resulted in the internal flooding of 58 properties with flood depths of up to 1.0m.
A Scheme was designed in 2015 and updated to current design guidance in 2023. The scheme will provide protection to 72 properties at risk of flooding (this includes 63 properties which are currently considered at very significant risk) and peace of mind for the whole community of Feniton. The scheme has been split into 4 phases, consisting of Phase 1 – bypass channel downstream of the railway to take the increased flows from the new culvert.
Phase 3 – undertrack crossing (UTX) of the Exeter to Waterloo line.
Phase 4 – completion of culvert linking the whole scheme together. Phase 1 and Phase 2 were completed in 2016. Phase 3 was completed in Autumn 2022. Phase 4 is due to start in Spring 2024 1.2. Setting up a Project board – See appendix 1 for further information.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.