Entering Contract above £100k - Feniton Flood Alleviation Scheme

Agreed Executive 1 paper

Cabinet agreed this item on Wednesday 3 January 2024. Below is the council's own wording, with the papers it was decided on.

Item115

Resolved

That an agreement to enter contract with Kier Integrated services to enter a contract of a value of up to £3m to deliver the construction of Feniton Flood Alleviation Scheme, be agreed. REASON: That Kier Integrated Services had been procured correctly and to aid speedy contract award to get Feniton on site in Spring 2024.
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to Cabinet

Report to: Cabinet

Date of Meeting 3 January 2024 Document classification: Part A Public Document Exemption applied: None Review date for release N/A

Entering Contract above £100k – Feniton Flood Alleviation Scheme Report summary: The report seeks to gain agreement to enter a contract with Kier Integrated services of up to a value of £3million. It outlines the procurement process, framework agreement and compliance with contract standing orders.

Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: That cabinet agree to enter contract with Kier Integrated services to enter a contract of a value of up to £3m to deliver the construction of Feniton Flood Alleviation Scheme

Reason for recommendation: That Kier Integrated Services has been procured correctly and to aid speedy contract award to get Feniton on site in Spring 2024

Officer: Tom Buxton-Smith. Engineering Projects Manager. [email protected] 01395 571630

Portfolio(s) (check which apply): ☐ Climate Action and Emergency Response ☒ Coast, Country and Environment ☐ Council and Corporate Co-ordination ☐ Communications and Democracy ☐ Economy ☒ Finance and Assets ☐ Strategic Planning ☐ Sustainable Homes and Communities ☐ Culture, Leisure, Sport and Tourism

Equalities impact Low Impact Climate change High Impact Risk: Medium Risk; With all construction projects there is a risk of additional cost incurred by unforeseen risks. There is a healthy risk budget, however EDDC would be liable for additional spend above central government eligibility. Links to background information N/A Link to Council Plan Priorities (check which apply) ☒ Better homes and communities for all ☒ A greener East Devon ☐ A resilient economy

Report in full 1. Background 2. 1.1. Feniton Flood Alleviation Scheme (FAS) Background

Flooding in New Feniton has been an issue since the development was built in the late 1960s; with flooding occurring every year and internal flooding every 2 to 3 years.

The biggest well recorded event was in late October 2008 when there was serious flooding in the main estate. This event resulted in the internal flooding of 58 properties with flood depths of up to 1.0m.

A Scheme was designed in 2015 and updated to current design guidance in 2023. The scheme will provide protection to 72 properties at risk of flooding (this includes 63 properties which are currently considered at very significant risk) and peace of mind for the whole community of Feniton. The scheme has been split into 4 phases, consisting of  Phase 1 – bypass channel downstream of the railway to take the increased flows from the new culvert.

 Phase 2 – property level resilience measures of downstream properties.

 Phase 3 – undertrack crossing (UTX) of the Exeter to Waterloo line.

 Phase 4 – completion of culvert linking the whole scheme together.

Phase 1 and Phase 2 were completed in 2016. Phase 3 was completed in Autumn 2022. Phase 4 is due to start in Spring 2024 3. Procurement process

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Entering Contract above £100k: Feniton Flood Alleviation SchemeReport 310 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 41 attended
MR
Councillor Marianne RixsonCommittee Member, present
GJ
Councillor Geoff JungCommittee Member, present
DL
Councillor Dan LedgerCommittee Member, present
MH
Councillor Matt HallCommittee Member, present
OD
Councillor Olly DaveyCommittee Member, present
SJ
Councillor Sarah JacksonCommittee Member, apologies
JL
Councillor John LoudounCommittee Member, present
NH
Councillor Nick HookwayCommittee Member, present
PA
Councillor Paul ArnottChair, present
PH
Councillor Paul HaywardVice-Chair, present
BB
Councillor Brian BaileyGuest, in attendance
KB
Councillor Kevin BlakeyGuest, in attendance

All 41 on the meeting page

More from East Devon Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 LGR in Devon: Government Decision and Implications for EDDCRESOLVED that Cabinet: 1. Notes the Government’s July decision and the subsequent review 2. Notes the concerns regard... Agreed Open
16 Sep 2026 Financial Strategy 2027 - 2029RESOLVED that Cabinet : 2. Agrees that the 2027/28 budget process should continue to be developed within the principl... Agreed Open
16 Sep 2026 Financial Monitoring Report and Annual Treasury Management Review 2025/26RESOLVED that Cabinet: Acknowledge the variances identified as part of the Revenue and Capital Monitoring process up ... Approved Open
16 Sep 2026 Woodbury Neighbourhood Plan to be formally 'made'RESOLVED that Cabinet: 1. Agree that the Woodbury Parish Neighbourhood Plan be ‘made’. 2. Note that once made the Pla... Agreed Open
16 Sep 2026 Green Team Project Standing Order ExemptionRESOLVED that Cabinet: 1. Notes and supports the exemption to Contract Standing Orders under the provision relating t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies