RESOLVED that Cabinet: 1. Approves the full scheme value for approval of £6.075m (No further EDDCs funds are required at this time, with additional project budget found from external sources) 2. Agrees to postpone commencing Phase 4 until the planning permission is granted. 3. Approves EDDC entering a contract with Kier Construction to deliver Phase 4, to mobilise asap once the planning permission has been secured, noting that the current additional external funds not yet been formally approved. 4. Subject to recommendation 3, Cabinet grants authority for EDDC to enter a contract for construction with Kier up to the value of £3.5m REASON: 1. To ensure project has authority to proceed. 2. To support the planning process and not risk starting a scheme with a planning objection, 3. To remove any further delay to starting on the project. As delay will likely raise costs, with more fundraising needed. 4. To enable a speedy contract signing to get to site soon.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Date of Meeting 5 June 2024 Document classification: Part A Public Document Exemption applied: None Review date for release N/A
Feniton Phase 4 Resolving risks to get to site Report summary: This report updates cabinet on the latest set of issues the project has faced prior to getting to site, and the reason for the delay in getting to site. It also highlights the remaining risks to the project and what is being done to mitigate risks and also updates the total project costing and asks for approval for additional total project spend
Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: 1. That cabinet approves the full scheme value for approval of £6.075m (No further EDDCs funds are required at this time, with additional project budget found from external sources) 2. That cabinet agrees to postpone commencing Phase 4 until the planning permission is granted. 3. That cabinet approves EDDC entering into a contract with Kier Construction to deliver Phase 4, to mobilise asap once the planning permission has been secured, noting that the current additional external funds not yet been formally approved. 4. Subject to recommendation 3, cabinet grants authority for EDDC to enter a contract for construction with Kier up to the value of £3.5m
Reason for recommendation: 1. To ensure project has authority to proceed. 2. To support the planning process and not risk starting a scheme with a planning objection, 3. To remove any further delay to starting on the project. As delay will likely raise costs, with more fundraising needed. 4. To enable a speedy contract signing to get to site soon.
Climate change High Impact Risk: High Risk; There are financial and planning risks with this project outlined in the report Links to background information N/A Link to Council Plan Priorities (check which apply) ☒ Better homes and communities for all ☐ A greener East Devon ☒ A resilient economy
Report in full 1. Background 1.1. Feniton Flood Alleviation Scheme (FAS) Background
Flooding in New Feniton has been an issue since the development was built in the late 1960s; with flooding occurring every year and internal flooding every 2 to 3 years.
The biggest well recorded event was in late October 2008 when there was serious flooding in the main estate. This event resulted in the internal flooding of 58 properties with flood depths of up to 1.0m.
A Scheme was designed in 2015 and updated to current design guidance in 2023. The scheme will provide protection to 72 properties at risk of flooding (this includes 63 properties which are currently considered at very significant risk) and peace of mind for the whole community of Feniton. The scheme has been split into 4 phases, consisting of Phase 1 – bypass channel downstream of the railway to take the increased flows from the new culvert.
Phase 3 – undertrack crossing (UTX) of the Exeter to Waterloo line.
Phase 4 – completion of culvert linking the whole scheme together. Phase 1 and Phase 2 were completed in 2016. Phase 3 was completed in Autumn 2022. Phase 4 is now hoped to start in August 2024
1.2Feniton FAS has been progressing with Atkins redesigning Howicks Scheme. This has been in part to meet current regulations and guidance, but also to reflect landowner changes over time. 1.3. Atkins have designed a better performing scheme giving higher return period protection and increased performance, such as a larger trash screen. 1.4. The newer standards, plus construction cost inflation has meant that last year’s scheme costs have increased. 1.5. Aside from costs, three further risks remain outstanding.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.