Approved contrary to officer recommendation with powers delegated to the Development Manager to agree conditions which will include restricting the use of the building to Class E(e) medical and health only, in consultation with the Chair, Vice Chair and Ward Members. Members determined that their previous concerns regarding flooding had been addressed and that the landscape impact was not substantial and that the public benefit of retaining the building for use as a NHS Covid Surge Centre if a pandemic reoccurred demonstrated exceptional circumstances to depart from the Local Plan.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Applicant [name removed] NHS Vaccination Centre Greendale Business Park Woodbury Salterton EX5 1EW
Proposal Permanent use of the building and car park for use class E (e) medical and health facility, and ancillary parking.
RECOMMENDATION: Refusal
Crown Copyright and database rights 2024 Ordnance Survey 100023746 Committee Date: 22.10.2024
Woodbury And Target Date: Lympstone 23/2749/MFUL 20.03.2024 (Woodbury)
Applicant: [name removed]: NHS Vaccination Centre Greendale Business Park
Proposal: Permanent use of the building and car park for use class E (e) medical and health facility, and ancillary parking
RECOMMENDATION: REFUSAL
UPDATE TO REPORT
This application was deferred at the Planning Committee meeting on 26th March 2024 so that Members could undertake a site visit to better understand the relationship of the site and development with its surroundings and to allow the applicant the opportunity to submit details relating to surface water drainage and management.
Surface Water Management:
Members will note from the appended report that officers recommend refusal of the application on the basis that the applicants have not provided a surface water drainage management plan which demonstrates how surface water from the development will be disposed of in a manner that does not increase flood risk elsewhere. The County Council’s Flood Risk Management Team have objected to the application on the basis that the applicant has not submitted sufficient information in order to demonstrate that all aspects of the surface water drainage management plan have been considered. As the application is retrospective and the building and hard standing that has been installed has a significant footprint, officers are of the opinion that a detailed surface water management plan needs to be provided to the satisfaction of the LLFA before planning permission can be granted.
Members of the committee deferred the application to allow the applicant the opportunity to provide the appropriate drainage information. The applicant has engaged in the services of AWP who have prepared a surface water drainage plan for the development along with a technical note which provides further detail in respect of the existing site drainage and a proposed scheme for the drainage of surface water from the site.
23/2749/MFUL The report sets out that at present, the site has a series of surface water gullies and oil interceptors along the eastern and southern margins of the hardstanding areas. Existing runoff is conveyed to a surface water sewer running from north to south within the eastern margin of the site, discharging to an existing manhole to the south with subsequent discharge into the Grindle Brook. The existing site comprises areas of tarmac and concrete surfaces used as parking for the vaccination centre. Run-off from the site drains through the existing private surface water sewer network, discharging south to the Grindle Brook.
Based on a review of ground conditions and due to the extent of made ground, infiltration has been precluded an in line with the drainage hierarchy, discharge to a surface water body is being proposed. The surface water strategy proposed is for the surface water runoff generated from the building and parking areas is to be intercepted by a new swale and filter drain that would be directed towards a new cellular attenuation tank beneath the tarmac yard area. The cellular tank would then discharge flows at greenfield rates to an existing as-built storm water outfall which discharges into the Grindle Brook.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
26/0534/MOUT (Major) WHIMPLE & ROCKBEAREThe Appropriate Assessment be adopted. 2. Approved with conditions in accordance with officer recommendation subject ...
26/0535/MFUL (Major) WHIMPLE & ROCKBEAREThe Appropriate Assessment be adopted. 2. That the SANGS application be approved, subject to conditions and to the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.