21/2604/OUT (Other) BROADCLYST

Approved Planning 1 paper

Planning Committee approved this item on Tuesday 25 February 2025. Below is the council's own wording, with the papers it was decided on.

Item261

Resolved

RESOLVED : Approved as per officer recommendation subject to the adoption of an Appropriate Assessment and completion of a Section 106 Agreement and conditions .
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to Planning Committee

Executive summary

The outline planning application proposes the development of the site for the erection of 7 dwellings.

Planning Committee resolved to approve this application on the 30th September 2022 and since that time negotiations have been underway with the applicant to secure the required legal agreement. In 2024 it became apparent that due to challenges with viability the originally envisaged agreement could not be secured and therefore work was switched to better understanding the viability constraints for the site and what could be considered affordable while making sure the site remained deliverable.

Until that time contributions were being sought at the same rate as the major expansion areas that comprise the principle form of development in the town. However a development of 7 dwellings on an infill style plot is distinctively different and the viability work has demonstrated that in this instance it can’t carry the same level of contributions. In particular, differences arise due to the economies of scale that the larger sites can benefit from (build costs), their ability to blend land value across larger tracts of land and the ability to deliver some obligations on site (rather than having to deliver all contribution as off site financial equivalents).

Having worked through the viability appraisal submitted by the applicant and having had this independently assessed for the Council, it was concluded that a headline value of c. £72,000 could reasonably secured from the scheme without compromising its viability. This would provide for appropriate contributions towards affordable housing and habitat mitigation. In addition and based on the Councils evidence it was identified that an additional contribution could also be secured towards other infrastructure in the town. Through negotiation this was agreed as an extra £28,000 bringing the total to £100,000. Although comprising a

21/2604/OUT reduction of a little over 50% in overall contributions to that initially sought, it represents a meaningful and justified total and one that allows the development to come forward.

Since the original report was provided and considered by members a number of policy update need to be noted. These comprise:

1. the adoption of the Cranbrook Plan meaning that the application site is now part of the Built Up Area Boundary for Broadclyst Station.

2. the Broadclyst Neighbourhood Plan has been made.

3. The emerging East Devon Local Plan is currently out for its Regulation 19 consultation.

Both the Cranbrook Plan and Broadclyst Neighbourhood Plan form part of the development plan and represent the starting point for determination of the application. In addition policies in the emerging Local Plan can attract limited weight dependant on the level of unresolved objection for those of relevance. As such it is a material consideration.

Importantly (and as a result of the Cranbrook Plan’s adoption), the principle for development of this site is established.

The remainder of this summary replicates that from the report in September 2022:

***

The site is a rectangular parcel of land and current boundary treatment means that the impact of the development would in part be mitigated in the short term, and more particularly seen within an urban context when the expansion development is brought forward.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
21/2604/OUT (Other) BROADCLYSTReport 603 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 29 attended
BB
Councillor Brian BaileyCommittee Member, apologies
IB
Councillor Ian BarlowCommittee Member, present
KB
Councillor Kim BloxhamCommittee Member, present
CB
Councillor Colin BrownCommittee Member, present
JB
Councillor Jenny BrownCommittee Member, present
SC
Councillor Sarah ChamberlainCommittee Member, apologies
MC
Councillor Maddy ChapmanCommittee Member, present
OD
Councillor Olly DaveyChair, present
PF
Councillor Peter FaithfullCommittee Member, present
SG
Councillor Steve GazzardCommittee Member, present
DH
Councillor Del HaggertyCommittee Member, present
AH
Councillor Anne HallCommittee Member, present

All 29 on the meeting page

On this subject at East Devon

Search all
  1. 21/2604/OUT (Other) BROADCLYSTThis decision
  2. 26/1048/FUL (Other) SIDMOUTH SIDFORDApproved
  3. 24/2057/VAR (Other) EXMOUTH LITTLEHAMApproved
  4. 25/2454/OUT (Other) YARTYApproved
  5. 25/1279/OUT (Other) DUNKESWELL & OTTERHEADApproved
  6. 25/0810/FUL (Other) SIDMOUTH TOWNApproved

More from East Devon Planning Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 25/2471/MRES (Major) CRANBROOKApproved with conditions in accordance with officer recommendation. Approved Open
1 Sep 2026 26/1143/PIP (Other) CLYST VALLEYThe Appropriate Assessment be adopted. 2. Permission in Principle be approved. Approved Open
1 Sep 2026 26/0854/FUL (Minor) BROADCLYSTApproved with conditions in accordance with officer recommendation. Approved Open
1 Sep 2026 26/0534/MOUT (Major) WHIMPLE & ROCKBEAREThe Appropriate Assessment be adopted. 2. Approved with conditions in accordance with officer recommendation subject ... Approved Open
1 Sep 2026 26/0535/MFUL (Major) WHIMPLE & ROCKBEAREThe Appropriate Assessment be adopted. 2. That the SANGS application be approved, subject to conditions and to the co... Approved Open