Approved as per officer recommendation subject to the adoption of an Appropriate Assessment and completion of a Section 106 Agreement and conditions including: Amendment to condition 9 to require smart water butts to be provided on each plot with a minimum capacity of 100 litre per bedroom Condition to require first floor windows of affordable housing apartment block to be obscure glazed. Condition to require details of solar panels to be submitted and agreed and to be installed on each dwelling prior to its occupation. Condition requiring a bat or bird box and a bee brick to be provided on each dwelling prior to occupation in accordance with details that have previously been approved by the LPA.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
This proposal seeks planning consent for the creation of 35 dwellings with associated infrastructure. The proposed development conflicts with the development plan as it seeks to build residential housing in the countryside outside the defined Built-Up Area Boundary (BUAB) for Feniton. Further, the proposal would result in the loss of a former employment building and there are ambiguities remaining over the marketing exercise, such that limited harm has been identified to employment opportunities. Nevertheless, the loss of such employment space must weigh against the proposal.
The district cannot currently demonstrate a sufficient five-year housing land supply. The latest changes to the National Planning Policy Framework (NPPF) emphasises the need to significantly boost the supply of housing across England. This proposal would deliver a meaningful number of dwellings, including 51% affordable housing, addressing the need for housing in the district. It would also generate short-term economic benefits during the construction phase and longer-term social benefits by providing much-needed housing. The provision of affordable housing thereby meeting a demonstrable need, is a key priority of the NPPF and government policy, and one which carries substantial weight in the planning balance.
The site lies within a Critical Drainage Area (CDA) which raises potential flood risk concerns. However, this risk has been satisfactorily addressed through a robust Flood Risk Assessment (FRA) and the inclusion of a suitable Sustainable Drainage System (SuDS) scheme to manage surface water effectively. Ongoing flood mitigation works involving the Council have been approved and are in progress to address wider drainage issues – however this can only be attributed limited weight at this time. South West Water (SWW) has also deemed the proposed foul drainage scheme acceptable, subject to appropriate Grampian-
23/0296/MFUL style conditions. Further, the site has been chosen as a preferred allocation under the regulation 19 emerging local plan process. Therefore, the flood risk to the development and surrounding areas is considered to be adequately mitigated.
The site is reasonably close to the services and facilities in Feniton, which are accessible via safe pedestrian routes. The distance to these services ensures that reliance on private vehicles by future residents would not be necessary.
The ecological impact of the development has also been appropriately mitigated and the landscape issues raised can be suitably addressed within conditions and a legal agreement.
The benefits of the development, including the delivery of housing to improve the district’s land supply and the provision of much-needed affordable housing, outweighs the identified conflict with the development plan. Accordingly, the harm of being sited outside the BUAB does not demonstrably and significantly outweigh the benefits. It is therefore recommended that a resolution to grant planning permission is made subject to conditions and the completion of a Section 106 agreement.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
26/0534/MOUT (Major) WHIMPLE & ROCKBEAREThe Appropriate Assessment be adopted. 2. Approved with conditions in accordance with officer recommendation subject ...
26/0535/MFUL (Major) WHIMPLE & ROCKBEAREThe Appropriate Assessment be adopted. 2. That the SANGS application be approved, subject to conditions and to the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.