Resolved
RESOLVED – that, subject to the completion of a legal agreement in respect of application 3/10/1583/OP, outline planning permission be granted, subject to the conditions detailed in the report now submitted.
Development Management Committee agreed this item on Wednesday 17 August 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – that, subject to the completion of a legal agreement in respect of application 3/10/1583/OP, outline planning permission be granted, subject to the conditions detailed in the report now submitted.
That, subject to the completion of a legal agreement to cover the following matters:
1. completion and occupation of only one of the approved residential units prior to the provision of the public house; 2. provision of the public house within 12 months of the occupation of the first of the residential units approved; 3. state of provision of the public house, such that it is complete and capable of operation, be specified in the legal agreement.
That planning permission be GRANTED with the following planning conditions:
1. Outline permission time limit (1T131)
2. Outline – submission of details (2E012)
3. Construction hours of working – plant and machinery (6N072)
4. Contaminated land survey and remediation (2E333)
Directives:
1. Other legislation (01OL1)
2. Street name and numbering (19SN4)
Summary of Reasons for Decision
The proposal has been considered with regard to the policies of the Development Plan (East of England Plan May 2008, Hertfordshire County Structure Plan, Minerals Local Plan, Waste Local Plan and the 'saved' policies of the East Herts Local Plan Second Review April 2007), and in particular policies GBC2, GBC3, ENV1, STC8, LRC11 and OSV8. The balance of the considerations having regard to those policies, and the benefit of providing a replacement public house for the local community, is that permission should be granted. 3/10/1583/OP
(158310OP.MP)
1.1The application site is shown on the attached OS extract. Members may recall that this application was reported to the 09 March 2011 Committee Meeting. The proposals involve the provision of two residential dwellings to enable the provision of a new public house on the site. Appendix A1 contains the previous report which was presented to the 9 March 2011 meeting of the committee and the minute.
1.2Members will note that refusal of the proposals was recommended, however, it was resolved to grant planning permission subject to the formulation of appropriate conditions and a legal agreement which would secure the provision of the public house. It is with respect to those two issues and particularly the triggers in the legal agreement that Officers now report back to Members.
2.0Considerations:
2.1A trigger is required in the legal agreement so that there is clarity with regard to the timing of the provision of the public house. This matter was discussed at the 9 March 2011 meeting and, whilst the conclusion was not specifically highlighted in the resolution, it appeared to officers that Members were of the view that the public house should be provided prior to the completion and occupation of either of the two residential properties.
2.2The applicant is concerned that this is not a practical arrangement. It requires all the costs associated with the development and fitting out of the public house building to be incurred before any income is generated from the sale of the new properties. It has been suggested that a compromise is to allow the completion and occupation of one of the two properties, and then require the completion of the public house within 12 months of the date of the first property occupation.
2.3This, in officer’s opinion, is a reasonable approach. It still provides a degree of assurance that the public house will be implemented on the site. Members are reminded, of course, that the Council can require the development and fitting out of the public house building to ensure that it is ‘ready for operation’. It cannot however, insist on the operation of the use. The understanding of ‘ready for operation’ can be set out in the legal agreement. It is unlikely that there are greater safeguards that can be implemented in this situation. The applicant is in agreement with the approach suggested. 3/10/1583/OP
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
3/10/1583/OP: The erection of a public house and two dwellings at the former Cock Public House, Stocking Pelham for Mr D Lyle SmithReport | 28 KB | DownloadRead as text |
PDF |
Former Cock PH, Stocking PelhamAppendix A | 504 KB | Download |
PDF |
Former Cock PH, Stocking PelhamReport | 115 KB | Download |
PDF |
Former Cock Public House: Appendix A1Appendix | 62 KB | Download |
Follow Development Management Committee at East Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Aug 2026 | 3/25/1986/FUL - Erection of 4 x industrial units (use classes E[g], B2 and B8) with associated parking and external works at Buntingford Business Park, Baldock Road, BuntingfordRESOLVED - in accordance with paragraph 6.5.6 of the constitution, Fergus Alexander be permitted to address the Commi... | Decided | Open |
| 12 Aug 2026 | Items for Reporting and NotingRESOLVED – that the following reports be noted: (A) Appeals against refusal of planning permission / non-determinatio... | Noted | Open |
| 15 Jul 2026 | Appointment of Vice-Chair for the 2026/27 civic yearRESOLVED – that Councillor J Thomas be appointed Vice-Chair of the Development Management Committee for the 2026/27 c... | Decided | Open |
| 15 Jul 2026 | Minutes - 15 April 2026RESOLVED – that the Minutes of the meeting held on 15 April 2026, be confirmed as a correct record and signed by the ... | Decided | Open |
| 15 Apr 2026 | Minutes - 11 March 2026RESOLVED – that the Minutes of the meeting held on 11 March 2026, be confirmed as a correct record and signed by the ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.