3/12/0411/FP – Site improvements involving conversion of 67 existing pitches into hard standing, standardise 24 "L" shaped hard standings, resurface existing caravan storage area and resurface existing internal access road at The Camping an

Agreed Committee 2 papers

Development Management Committee agreed this item on Wednesday 15 August 2012. Below is the council's own wording, with the papers it was decided on.

Item251

Resolved

RESOLVED – that in respect of application 3/12/0411/FP, planning permission be granted subject to the conditions detailed in the report and with the amended condition 7: 1. The development hereby permitted shall be carried out in accordance with the drainage details received on 25July 2012 unless otherwise agreed in writing by the Local Planning Authority. Reason: To ensure surface and foul water is treated appropriately to prevent pollution of groundwater in accordance with Policy ENV20 of the East Herts Local Plan Second Review April 2007.
Word for word from the decision East Hertfordshire published for this meeting. Source: democracy.eastherts.gov.uk

Follow this further

Built from East Hertfordshire's papers

What the report saysPro

Report to Development Management Committee

Recommendation

That planning permission be GRANTED subject to the following conditions:

1. Three Year Time Limit (1T12)

2. Approved Plans (2E10): ‘STAND/007/CED, STAND/015/LMM, HER010JS, HER011JS and HER012JS’

3. Prior to the commencement of works in relation to the caravan storage element, detailed plans of the proposed bunding, together with a plan of all existing trees on site with a stem diameter of 100mm or greater, shall be submitted to and approved in writing by the Local Planning Authority and therafter implemented in accordance with the approved details. The details to be submitted shall include the following information: a) location, species, girth or stem diameter, accurately plotted crown spread and an assessment of condition. b) existing ground levels at the base of trees where nearby changes in level are proposed c) trees to be removed in conjunction with the proposed development which shall be clearly marked as such on a plan and d) positions and details of fencing or hoardings, prohibited areas and other physical means of protecting trees.

Reason: To ensure that trees and hedges are retained and adequately protected from the development in accordance with Policies ENV2 and ENV11 of the East Herts Local Plan Second Review April 2007.

4. Landscape Design Proposals (4P12) ‘(e), (i), (j), (k) and (l)’

5. Landscape Works implementation (4P13)

6. The development hereby permitted shall only be carried out in accordance with the approved Flood Risk Assessment. The surface water run-off generated by the 1 in 100 year critical storm including a 3/12/0411/FP

30% allowance for climate change shall be limited so that it will not exceed the run-off from the existing site and not increase the risk of flooding off site. The mitigation measures as outlined within the Assessment shall be fully implemented prior to use of the pitches.

Reason: To ensure that the development does not increase flood risk on or off site in accordance with Policies ENV19 and ENV21 of the East Herts Local Plan Second Review April 2007.

7. Prior to the commencement of work, a scheme to dispose of foul and surface water (Drainage plan) shall be submitted to and approved in writing by the Local Planning Authority and thereafter implemented in accordance with the approved details.

Reason: To ensure surface and foul water is treated appropriately and prevent pollution of groundwater in accordance with Policy ENV20 of the East Herts Local Plan Second Review April 2007.

8. No infiltration of surface water drainage into the ground at this site is permitted other than with the express written consent of the local planning authority, which may be given for those parts of the site where it has been demonstrated that there is no resultant unacceptable risk to controlled waters. The development shall be carried out in accordance with the approval details.

Reason: To protect groundwater in accordance with Policy ENV20 of the East Herts Local Plan Second Review April 2007.

9. The development hereby permitted shall be carried out in accordance with the submitted Groundwork Methodology, unless otherwise agreed in writing by the Local Planning Authority.

Reason: To secure the protection of and proper provision for any archaeological remains in accordance with policies BH2 and BH3 of the East Herts Local Plan Second Review April 2007.

Directives:

1. Other legislation (010L)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
3/12/0411/FP: Site improvements involving conversion of 67 existing pitches into hard standing, standardise 24 "L" shaped hard standings, resurface existing caravan storage area and resurface existing internal access road at The Camping and Caravan Site, Mangrove Road, Hertford for The Camping andReport 44 KB DownloadRead as text
PDF
3120411FP PlanReport 853 KB Download

At this meeting

Whole meeting

More from East Hertfordshire Development Management Committee

All decisions
MeetingDecisionOutcome
12 Aug 2026 3/25/1986/FUL - Erection of 4 x industrial units (use classes E[g], B2 and B8) with associated parking and external works at Buntingford Business Park, Baldock Road, BuntingfordRESOLVED - in accordance with paragraph 6.5.6 of the constitution, Fergus Alexander be permitted to address the Commi... Decided Open
12 Aug 2026 Items for Reporting and NotingRESOLVED – that the following reports be noted: (A) Appeals against refusal of planning permission / non-determinatio... Noted Open
15 Jul 2026 Appointment of Vice-Chair for the 2026/27 civic yearRESOLVED – that Councillor J Thomas be appointed Vice-Chair of the Development Management Committee for the 2026/27 c... Decided Open
15 Jul 2026 Minutes - 15 April 2026RESOLVED – that the Minutes of the meeting held on 15 April 2026, be confirmed as a correct record and signed by the ... Decided Open
15 Apr 2026 Minutes - 11 March 2026RESOLVED – that the Minutes of the meeting held on 11 March 2026, be confirmed as a correct record and signed by the ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies